Wednesday 4 December 2013

METHOD STATEMENT FOR PRECAST CONCRETE ELEMENTS PRODUCTION, ERECTION & WELDING FINISHING !!

 

TABLE OF CONTENTS


1.    PURPOSE.......................................................................................................... 3
2.    SCOPE................................................................................................................ 3
3.    REFERENCE.................................................................................................... 3
4.    PROCEDURE.................................................................................................... 3
5.    DEMOULDING / DETENSIONING STRENGH............................................ 5
6.    CONCRETE SAMPLING................................................................................. 5
7.    SANDBLASTING / ARCHITECTURAL FINISH........................................... 5
8.    RESPONSIBLITIES.......................................................................................... 7
9.    SAFETY.............................................................................................................. 7
10. TRANSPORTATION......................................................................................... 7
11. ATTACHMENTS.............................................................................................. 10


1.            Purpose


·         The purpose of this method statement is to set guidelines and methodology to be followed during precast concrete elements production.

2.            Scope


·         The scope of this procedure is to standardized method of the precast concrete elements production. Hence, execution of the work shall be done be done as per the acceptable standards and the relevant project specifications.


3.            References


·         Project Specification and Design Drawing
·         SAUDI ARAMCO Standards

4.            Procedure


4.1. Prior to Casting

Prior to casting, the checks below are to be carried out to ensure that all items are in accordance with standards, drawings and accepted procedures. In the event of there being any variation the inspector is to ensure that it is corrected before casting is authorized or that the matter is reported to his superior.

4.1.2 Mould Condition

Ensure that the basic table, plate or special mould is level, robust and free from any inherent defects.

4.1.3 Mould Dimension

Ensure that the dimension of the mould conform in all respect with the drawings. These must be checked prior to the initial cast in the case of a new set-up or a mould change and thereafter, at intervals of not more than 50 casts. A record, in the prescribed form, is to be kept of these checks. Allowable tolerances on first set-up shall be half those detailed in Appendix A to this manual.

4.1.4 Mould Fixing & Cleanliness

Ensure that all side closers and other formers are fixed in such a manner that they will not move during the casting process. Ensure that the mould of form-liner is clean and free from deleterious matters or foreign substances.



4.1.5 Release Agent

Ensure that the type being uses is approved and that it is being applied in accordance with the manufacturer’s instructions and in such a manner that the mould surfaces are evenly covered.


4.2. Casting

4.2.1 Placement of Reinforcement

Ensure that the reinforcement is fabricated in accordance with the drawings. Ensure that reinforcement is positioned in the mould, by means of spaces or any other method, in such a way that, it remains in the correct position during casting.

Follow the good practice for ensuring the correct concrete cover, correct hook length, correct splice length.

4.2.2 Placement of Cast-in Items

Ensure that cast-in items are of the approved type and size shown on the drawings and that they are securely fixed in the correct positions.

4.2.3 Placing

The following test must be done prior to placing the concrete:
-                         Concrete temperature should not be more than 32°C.
-                         Slump test as per mix design requirement:

Ensure that concrete is placed in the manner most appropriate to the type of element being cast. Where two different mixes are employed in the same element, as in the case of some exposed aggregate finishes, particular care must be taken to ensure that there is a satisfactory bond between the two mixes but that no leeching occurs. In case of using two different mix for one element, e.g. (facing mix and backing mix), time gap must be minimized.

4.2.3 Consolidation

Inspector must ensure that adequate mechanical consolidation is carried out for the concrete to form one homogeneous mass. Particular attention must be paid to up-stands, recesses and other small cross-section areas. The method of consolidation most suited to the mix and type of element is to be used.




4.2.4 Surface finish

All non-mould surfaces are to be screeded level and trawled smooth. Inspectors are to pay particular attention to the thickness of table cast elements and the standard of the trowelled finish.

4.2.5 Movement

Sudden or violent movement of any filled mould must be avoided between the times of initial and final set of the concrete.

4.2.6 Curing
At sub contractor factory curing is done as per the factory set-up and sub contractorQMS Standard Operating Procedure (Doc. No. 1.11) as one of the following:
•  Steam Curing
•  Indirect Heating
•  Curing Compounds

No need for continuous curing if the elements reach 70% of the 28 days compressive strength.

Element can be transported to the site after 3 days of casting date.

5.            Demoulding / Detensioning Strength


The needed concrete strength for demoulding / detensioning (cube strength):
•     For non-prestressed elements:        20 MPa (or as specified on drawing).
•     For prestressed solid slabs:             25 MPa (or as specified on drawing).
•     For other prestressed elements:      35 MPa (or as specified on drawing).

Special instructions for striping strength can be submitted by Design Dept.

6.            Concrete Sampling


For every concrete mix design that is currently used the frequency for take out of test samples is once every, not less than once for every 120 m3 of concrete (ACI 318.5.6.1). By every take out of test samples five (5) samples are taken for test of strength as either cube specimens or cylinder specimens. By casting on site only four (4) samples is taken for test of strength.

Sampling of freshly mixed concrete shall comply ASTM C 172. It shall take place at the place of casting and at the time of casting. The samples for strength tests shall be taken at the same time in one work operation (ASTM C172:3.1). The samples shall be taken in a way that ensures that the samples represent an average of the mix (ASTM C172:4.2.1).



7.            Sandblasting / Architectural Finish


Architectural finish like sandblasting or exposed aggregate can be added to almost all types of elements like wall panels, columns and slabs. Mostly that kind of finish is done with special selected aggregates with white or colored concrete.

Before starting the performance of the finishing work it is important to read the fabrication drawing and clarify the kind of finishing wanted and on which parts of the elements.

Sandblasted finish is done with compressed air and sand blown in high speed through a nozzle on to the element. The finish is depending on the degree of sandblasting usually distinguishing between:

•      Heavy sandblasting (HSB):
Leaves all stones exposed and in some degree outstanding

•      Medium sandblasting (MSB):    
Between hard sandblasting and light sandblasting

•      Light sandblasting (LSB):
Leaves the stones only just visible.

However any degree of sandblasting can be requested by the client.

The quality controller marks on the elements the limits and the degree of sandblasted wanted. By chamfered corners and by false joins it must be known exactly where the limit for sandblasting goes, leaving no doubt whether the chamfer or joint is sandblasted or not.

Exposed finish is done by adding retarding chemicals before casting to the parts of the mold where that finish is wanted. After curing the outer not hardened layer of concrete is washed off with a strong water jet. Thereby the stones are exposed giving the wanted surface finish.

The finish quality is depending on how the retarder chemical is added in the mold and how the casting is performed. The retarder chemical must be added evenly and in correct thickness. It is also important that the correct limits between exposed and not exposed areas is observed especially by chamfers and false joints.

By casting one must be careful by the non-horizontal parts of the mold, the concrete must not slide on the mold moving the retarder and distributing it unevenly. Generally bigger vertical mold parts with exposed finish should be avoided because of the problems the to get the good finish.

Approved sample must be available if the client requests a special finish. The approved sample must be marked by the client and in addition marked clearly as approved and for which elements and project it shall be used. If copies of the sample are made then they must be marked clearly as well. All elements assigned for a sample must be controlled to have the same appearance on the finish as the sample.

By all kinds of architectural finishing it is important that elements to the same project have a uniform appearance. Seen together they must not stand out and look different because eventually they will be installed on the same building. Therefore all elements with the same finish must be compared with not only with the approved sample but also with each other.





8.           Responsibilities


a.)   QC Manager have to ensure that the Plant QC section is provide by the necessary facilities and cooperation from all supervisors, foremen and laborers to enable satisfactory inspection and verification of activities performed by the civil section.
b.)   Safety Manager have to ensure that all safety requirements will be enforced by manners to prevent injury to personnel, damage to plants and equipment's. He should provide written instructions to established work methods; explain the sequence of the operation, outline the potential hazards at each stage ad indicate precautions to be adopted.
c.)   Production Manager is solely responsible about casting of precast concrete elements assuring all works being implemented are in conformance with specifications.

9.           Safety


a.)   All personnel shall wear personal protective equipment (PPE) and should be instructed how to use the PPE correctly.
b.)   Signs and barriers have been provided when warranted to isolate the job site from public and unauthorized personnel.
c.)   Conduct tool box meeting related to work activities. Safety officer shall conduct the activities all the time.
d.)   All equipment shall be inspected/passed Saudi Aramco requirements.
e.)   All requirement operators must have their valid license/certificate.
f.)    Housekeeping.


10.          Transportation


Precast concrete element can be transported to site if its gain 70% strength of 28 days of compressive strength.

10.1 Transportation of Wall Panel

For transportation of wall panels the following type of trailers are used.
                          1.        A- frame trailers (flat bed trailer fitted with steel frame having the shape of letter “A”), to be used to transport elements which need to be transported vertically, such as wall panels, claddings at normal height.
                          2.        Low bed –A frame trailers fixed in such away to give more clear height to pass under the bridges etc.



After the loading is completed the loading supervisor will fill the dispatch delivery note form which will be distributed as per the form. The dispatch deliver note is to be signed and approved the QC Engineer and the driver.

10.2 Transportation of Double Tee Slabs
For transportation of Double Tee Slabs normal flat bed trailers 12m long, 2.5m wide are used. If the length of Double Tee Slab is exceeding, long flat bed trailer with length ranges between 13m ~ 22m long, 2.5m wide are used.
After the loading is completed the loading supervisor will fill the dispatch delivery note form which will be distributed as per the form. The dispatch deliver note is to be signed and approved the QC Engineer and the driver.

Speed Limit
-         Inside Factory not to exceed 20 KM/H
-         On high way to site: speed limit as per traffic police instructions
-         At site as per site instruction but should not exceed 20 KM /H

Securing the Loads
-         Use steel chain with come along hook to tighten the DTT slabs
-         Use protection at the touching point between the chain and DTT slab such as rubber sheet, steel or plastic angles.
-         Be aware not to use excessive force while tightening the chain to avoid damage to DTT flange.
-         The line of chin should be along wooden donnage under the DTT slabs.

Transport Permit

ARA or their Transport subcontractor will secure the required permit to transport DTT slab from ARA Factory in Riyadh to job site in Jubail City as per trip rout between the two cities.

Safety Convoy Vehicle

ARA or their transport subcontractor will provide pilot Vehicle as needed by Transport Authority and will coordinate with highway police as needed.

Access to Site

Upon approaching to the site, drivers will call site supervisor to specify waiting location near by the site in safe public Area.

Site super visor or his assistance will meet the drivers at that point and give them instruction on when to come to site in certain sequence as per erection sequence at site.

Also he will explain to them how to enter to the site and where to park near to offloading crane.

Site supervisor should assign signal man of Flag man to help and guide the drivers to the unloading place near to crane.

Driver maneuvering inside the site should be minimum in straight line without the need to make Turing unless it is Must.

Trailer conditions and Maintenance

Sub contractor will make sure that all Trailers used in delivering DTT Slabs and maintained well and in running safe conditions.

Unloading of DTT Slabs

Driver should use safety hard hat, gloves and safety shoes and reflecting jackets.

Driver should not leave or come down from his tractor head unless he receive instruction from unloading Foreman to un-tight the chains for unloading. He should go back to his cabin till receiving instruction to leave the site or any other instruction from site supervisor.


11.        Attachments


11.1 Design Process Flowchart
11.2 Production Process Flowchart
11.3  Sub Con Quality Assurance
11.4 Hot Weather Concreting
11.5 Equipments Calibration Summary
11.6 Raw Material Frequency Test Plan
11.7 QCIR Forms
11.8 ITP




 ERECTION TABLE OF CONTENTS


1.    PURPOSE.......................................................................................................... 3
2.    SCOPE................................................................................................................ 3
3.    REFERENCE.................................................................................................... 3
4.    PROCEDURE.................................................................................................... 3
5.    DEMOULDING / DETENSIONING STRENGH............................................ 5
6.    CONCRETE SAMPLING................................................................................. 5
7.    SANDBLASTING / ARCHITECTURAL FINISH........................................... 5
8.    RESPONSIBLITIES.......................................................................................... 7
9.    SAFETY.............................................................................................................. 7
10. ATTACHMENTS................................................................................................ 7









1.            Purpose


·         The purpose of this method statement is to set guidelines and methodology to be followed during precast concrete elements erection at site.

2.            Scope


·         The scope of this procedure is to standardized method of the precast concrete elements erection. Hence, execution of the work shall be done be done as per the acceptable standards and the relevant project specifications.


3.            References


·         Project Specification and Design Drawing
·         SAUDI ARAMCO Standards

4.            Procedure


4.1. Storage of Precast Concrete Elements at site

4.1.1. Wall Panels

Wall panels shall be stored vertically in fixed or moveable racks supported by dowels in top and dunnages down under (see Fig 1.0). Any wall panel rack must either be fixed by bolts or welding or it must be designed for moveable use.
By the use of a moveable rack the wall panel must always rest on the foot beam of the rack.
No moveable rack with damaged or missing foot beam must be used.
Special attention must be paid to wall panels with cutouts at the bottom line (see fig. 2.0). Following is important:
The wall panel is turned with the cutout away from the supporting dowels as shown on Fig 2.0.
The support at the panel end with the cutout is stabilizing horizontally. Do not use a simple stud.
For insulated panels always place the dunnages under the structural skin (see fig. 3.0). Never place dunnages under delicate parts of wall panel (see fig. 4.0.)
Panels with architectural surface must be paid special attention to avoid damaging by handling. Architectural surfaces should be directed so that they do not get direct sunshine.
Transport of wall panels takes place in trucks with A-frames. Note that the rules given under point 2 for placing of dunnages under insulated panels also counts for transport.
Fig. 1.0
Fig. 2.0

           Fig. 3.0                                                                     Fig. 4.0
4.1.2. Double Tee Slabs

The DT-slabs must only be placed on a plain and stable surface so that no twisting can occur. Dunnages type 1 shall be used, they shall be placed as close as possible to ends of element.
The DT-slabs can be stacked in up to 3.5 meters, number of elements accordingly. The number of dunnages needed increases downward in the stack. The two elements on the top needs one dunnage under each leg in both ends of element, the next element under needs two, the next element three, and so on downwards. Note: The dunnages must be placed in one layer only, never pile them.
By transport of max. cantilever is 2 meters.
Fig. 1.0





4.2. Erection of Precast Concrete Elements

4.2.1. Wall Panels

The installation of the precast wall panel shall be done according to the following methodologies:
·         Before the installation the area should be properly barricaded with visible sign postings indicating that installation operation is going on.
·         A watcher should be posted in the area to warn unauthorized persons or vehicles that may suddenly enter the area.
·         Prior to lifting the crane must be located in a level and well compacted ground immediately adjacent to the building and the vehicle carrying the precast elements or storage area.
·         Top surface must be flat and even.
·         Check that no obstruction for erection.
·         Layout Wall Panels position marking out width of each Wall Panel on the surface of the beam.
·         Place plastic shims on the location of wall panels.
·         As soon as the hooks are lowered by the crane operators, the erection crew will attach these to the precast elements making sure it is properly latched before making a hand signal to the rigger to start lifting.
·         The riggers will make a hand signal to the crane operators to start lifting, and blow a whistle or by any means to warn everyone that lifting process is going on.
·         The crane operator will slowly lower the element and the erection crew will pull tag line (if necessary) to bring the element in its proper position.
·         The rigger will give hand signals to crane operator to make small adjustment to fit element in its final position.
·         For the panel, once the panel is fitted in correct position, the erection crew will fix the adjustable props and install the necessary anchor bolts to hold the panel element in its position.
·         As soon as the anchor bolts and adjustable props are properly fixed the erectors crews will unlatched the crane hook, and the rigger will signal the crane operator to raise the crane chain out of the panel element.
·         Anchor Bolts hole with Non Shrink Grout will commence after the alignment of wall panels.
4.2.2. Double Tee Slabs

·         Conduct survey of the structure and check the following:
-       Top surface must be flat and even.
-       Measure distance between the supports, the distance should within the required length of DTT slabs including tolerances.
-       Check that no obstruction for erection.
-       Layout Double Tee Slabs position marking out width of each slabs on the surface of the support.
-       Install neoprene pad on the location of Double Tee legs.
·         Crane should be positioned to the nearest distance against the position of the last elements according to the crane position plan.
·         The main hoist of the crane is used to lift the PC elements on its lifting points.
·         Lifting cables must be at minimum 45 degrees angle from the horizontal.
·         DTT Slab will be lifted directly from the trailer to its proper position.
·         Release the DTT Slab from the crane when the elements is properly aligned and leveled.
·         After erection completion, start welding the adjacent double tee slab plates, as required by the approved shop drawing and approved WPS.

4.2.3. Post Erection

Once the lift has been safely completed and the load has been secured in its final position:
-       The rigging crew shall remove all tag lines, rigging and temporary barriers.
-       Equipment operators shall remove all transportation, positioning or manoeuvring and lifting equipment from the area (if no longer needed).
-       The responsible superintendent shall restore the work area for future construction work.
-       Rigging supervisor shall ensure that transporting, positioning or manoeuvring and lifting equipment that is no longer required for the project is safely disassembled, loaded on to transport equipment, and removed from the construction site.


5.           Responsibilities


   5.1 Main Contractor Engineer

         Site Engineer or his representative is the overall in-charge of the site, and coordinates all activities related to storage and installation of all pre-cast panels. His responsibilities are, but not limited to the following:
§  Inform all persons involved in the lifting and installation of the schedule for storage or installation of pre-cast element, making sure of their presence during the operation.
§  Prepare the site for the installation, ensuring that there are no objects or other activities going on in the site that will disrupt the lifting the lifting and installation of the pre-cast elements.
§  Provide an area in the site for the storage of pre-cast element which is safe from other on-going activities hard well compacted.
§  Coordinate equipments and manpower as necessary for the safe and successful lifting and installation of pre-cast element.
5.2 Erection Supervisor / Foreman (Sub contractor)
The Erection Supervisor / Forman are directly responsible for the receiving, stocking, lifting and installation of the precast elements. They directly supervise all persons involved in the operation. Their responsibilities are as:
§  Full coordination with client’s  engineers.
§  Receive all precast elements arriving to the site.
§  To unload precast elements and stock them in the correct place or directly erect them to their final position.
§  Ensure that equipments are in good operating conditions prior to the start of the site lifting and installation of precast elements.
§  Make sure that the riggers, equipment operators and erection crews are competent and know their job properly.
§  He must be present at all times during the lifting and installation operation, and will leave the area only when replaced by an equally competent person.
§  Qualified rigger is responsible for the specific area of stocking, lifting or installation and exact equipments needs.
   5.3 Site QC Engineer

Site QC Engineer have to ensure that the QC section is provide by the necessary facilities and cooperation from all supervisors, foremen and laborers to enable satisfactory inspection and verification of activities performed.


5.4 Site Safety Officer

Site Safety Officer have to ensure that all safety requirements will be enforced by manners to prevent injury to personnel, damage to plants and equipments. He should provide written instructions to established work methods; explain the sequence of the operation, outline the potential hazards at each stage ad indicate precautions to be adopted.


6.           Safety


a.)   All personnel shall wear personal protective equipment (PPE) and should be instructed how to use the PPE correctly.

b.)   Signs and barriers have been provided when warranted to isolate the job site from public and unauthorized personnel.

c.)   Conduct tool box meeting related to work activities. Safety officer shall conduct the activities all the time.

d.)   All equipment shall be inspected/passed Saudi Aramco requirements.

e.)   All requirement operators must have their valid license/certificate.

f.)    Housekeeping.


7.          Attachments


7.1 Erection Process Flowchart
7.2 Checklist – site inspection of element upon arrival
7.3 ITP
7.4 JSA (Job Safety Analysis)


WELDING FINISHING TABLE OF CONTENTS


1.    PURPOSE.......................................................................................................... 3
2.    SCOPE................................................................................................................ 3
3.    REFERENCE.................................................................................................... 3
4.    PROCEDURE.................................................................................................... 3
5.    RESPONSIBLITIES.......................................................................................... 7
6.    ATTACHMENTS................................................................................................ 8









1.            Purpose


·         The purpose of this method statement is to set guidelines and methodology to be followed for welding activities during precast concrete elements erection works at site.

2.            Scope


·         The scope of this procedure is to standardized method of the weldingo f connection for precast concrete elements during erection. Hence, execution of the work shall be done be done as per the acceptable standards and the relevant project specifications.


3.            References


·         Project Specification and Design Drawing
·         SAUDI ARAMCO Standards
·       Sub Contractor Quality Management  system
·         Erection Method Statement
·         Risk Assessment & Safety Plan
·         Welding Details as per Approved Shop Drawings
·         AWS D1.1 and D1.4.
·         ARA-WPS-01 Rev. 00
·         ARA-PQR-01


4.            Procedure


4.1. Planning of welding works

Hot work permit shall be obtained 24 hrs prior to start of welding activity.
Raise RFI minimum 24 hours prior to start of work to inform client & main contractor.
Prior to start welding activity explain to the crew the job description and requirements and each individual scope of work.
Make sure that all safety requirements are fulfilled.

4.2. Materials

Welding Electrodes E7018 (see attached datasheet)
4.3 Tools
1.    Welding Machine (either electrical or diesel – to be specify later stage)
2.    Welding Cables
3.    Welding Rod Oven
4.    Welding Torch
5.    Welding Hammer
6.    Grinder
4.4 Personal Protective Equipments (PPE)

1.    Welding Machine (either electrical or diesel – to be specify later stage)
2.    Welding Jacket
3.    Welding Mask (Helmet Type)
4.    Welding Gloves
5.    Fire Extinguisher
6.    Fire Blanket
4.5 Welders

·         Only certified welders are allowed to do welding on site. A welder can only do welding that is covered by his certification.
·         Welder must hold his ID card all time with him.
4.6 Safety Precautions

·         No welding activity will take place under boom radius during crane operation.
·         Hot work permit shall be obtained prior to start any welding job.
·         Welders must wear protective clothing and eye protection when welding or chipping slag from welds.
·         A fire extinguisher should be kept in close proximity to welding operations.
·         Any combustible material should be removed from the vicinity of welding operations; where removal is not possible the material should be protected.
·         The area around the welding operation should be cordoned off to protect other people from welding sparks or spatter.
·         Welders should not interfere or tamper with welding equipment.
·         The mains supply to the welding machine should be transformed down to a safe working voltage (usually between 80 and 110 volts).
·         The actual welding circuit should be isolated from the mains.
·         Trailing leads should be as short as possible, armoured and visible to avoid trip hazards or damage.
·         All equipment should be properly earthed.
·         All connections should be made with proper fittings or equipment.
·         Connections to the work to be welded should be made with clamps or lugs.
·         When not in use, all welding equipment should be disconnected from the main supply, or isolated, and protected if left unattended for any length of time.
·         The welding equipment must be well maintained and in good condition.
·         When welding the welder must always use standard protection equipment for welders. If welding is done on galvanized steel or steel with toxic paint then a mask that protects against toxic fumes must be used.
·         Welding on close containers, tanks and pipes are not allowed.
·         The gas cylinders used by the flame cutting must be supplied with intact pressure gauges.
·         The fire hazard must be observed by welding and flame cutting. If the welding or cutting take place near flammable materials then the welder must have a helper looking for fire while the welding or cutting is ongoing.
4.7 Welding Consumable Control Procedure

·         All Electrodes shall be kept in welding rod oven.
·         Any combustible material should be removed from the vicinity of welding operations; where removal is not possible the material should be protected.
·         Particular care must be exercised in damp weather to avoid contact with the welding electrode or holder.
·         Electrode stubs should be rejected into a metal container or other non-combustible receptacle.
·         In case of non-availability of Welding Rod Oven, vacuum packed electrodes shall be used.
4.8 Basic Principles of Welding Process

The basic principles are illustrated in below Figure. One pole of the power source is connected to the clamped (chuck) end of the electrode via the welding lead and the electrode holder, the other to the workpiece. With DC welding, it is the electrode which is normally the minus pole. The plus pole is only on the electrode when high alloy or basic electrodes are involved. Welding current can be also alternating depending on the welding appliance. After ignition the arc burns between the electrode and the workpiece. The welder draws the electrode in the direction of the weld while at the same time constantly compensating for the gradual melting of the electrode itself. The arc melts both the workpiece material and the filler material, which then form a bead which is covered with slag from the electrode coating. This slag is removed after the welding operating.
Welding Basic Principles

4.9 PREPARATION OF MATERIALS

Surfaces and edges to be welded shall be smooth, uniform, clean and free from cracks or other defects which may weaken the effective quality or strength of the weld.
Surfaces of the parent-metal shall be free from scale, slag, rust, moisture, oil, grease or other harmful materials that will prevent achievement of good welds. Before welding every materials shall be checked and inspected in detail for any defects.

4.10 TACK WELD

Prior to performing main welds, tack welds shall be done by shielded metal arc welding, under the same conditions as for actual welds.
All parts shall be adequately supported to provide the best possible alignment and minimize stresses on tack welds and root passes.
Every defective tack weld shall be cut out before completion of finished welds.
Care shall be taken while removing tack welds. Temporary fittings will be used for assembly ensuring the base metal is not damaged.
4.11 CLEANING
All slag and flux shall be ground or brush cleaned from each bead before depositing the next successive layer. The edges of the parts to be welded shall be free of rust, paint, sand, tar, oil and grease.
If they are wet, they must be dried before proceeding with the weld.
4.12 REPAIR OF DEFECTS
-       Blow holes, irregularities of deposit, undercut sharp corners of other unacceptable defects shall be removed by grinding or chipping before depositing the next successive layer of welding.
-       Cracks shall be removed by grinding, chipping or arc grouging and rewelded in accordance with this specification.
-       Defects such as porous slag including lack of penetration irregularities of deposit shall be removed by chipping, grinding or arc grouging and rewelded in accordance with this specification.
4.13 Finishing of Welded Connection
After all welding is completed the total connection should be painted with an anti-corrosive paint.
4.14 Testing (BY OTHERS)
Non-Destructive Test (by others)
-             Dye Penetration Test
           or
-             Magnetic Particle Test
           or
-             Ultrasonic Test
Testing shall be done on random location at least 10% of total weld spots or If there is doubt about certain location.

5.           Responsibilities


   5.1 Main Contractor Engineer

         Site Engineer or his representative is the overall in-charge of the site, and coordinates all activities related to welding works of all pre-cast elements. His responsibilities are, but not limited to the following:
§  Inform all persons involved in the welding work of pre-cast elements, making sure of their presence during the operation.
§  Prepare the site for the welding, ensuring that there are no objects or other activities going on in the site that will disrupt the welding works of the pre-cast elements.
§  Coordinate equipments and manpower as necessary for the safe and successful welding works.


5.2 Erection Supervisor / Foreman (Sub Contractor )

The Erection Supervisor / Forman are directly responsible for the welding works of the precast elements. They directly supervise all persons involved in the operation. Their responsibilities are as:
§  Full coordination with client’s  engineers.
§  Ensure that equipments are in good operating conditions prior to the start of the welding works of precast elements.
§  Make sure that the welders, helpers are competent and know their job properly.
§  He must be present at all times during the welding operation, and will leave the area only when replaced by an equally competent person.
   5.3 Site QC Engineer

Site QC Engineer have to ensure that the QC section is provide by the necessary facilities and cooperation from all supervisors, foremen and laborers to enable satisfactory inspection and verification of activities performed.


5.4 Site Safety Officer

Site Safety Officer have to ensure that all safety requirements will be enforced by manners to prevent injury to personnel, damage to plants and equipments. He should provide written instructions to established work methods; explain the sequence of the operation, outline the potential hazards at each stage ad indicate precautions to be adopted.




6.          Attachments


6.1 Sub Contractor-WPS-01 
6.2 Sub Contractor-PQR-01 
6.3 ITP
6.4 JSA (Job Safety Analysis)


No comments:

Post a Comment