- What are the
main duties of the piping inspector?
Material receiving inspection à Storage &
preservation à Cutting, assembly &
fit-up à Pre-welding inspection à Visual inspection of
socket & threaded joints à Pneumatic test for
reinforcing pad à Pickling &
passivation à Database reporting à Visual inspection of
completed spools à Piping pre-inspection
& spool erection à orifice flange
inspection à Pipe support inspection
à Verification of slope à Internal cleanliness à Valve installation à Piping flange joint
inspection à Pre-test punch listing à Hydro testing à pre-commissioning.
- How many types
of gaskets do you know?
Full face (Asbestos)
Spiral wound metallic
Ring type
Metal jacketed
Inside bolt circle
- What
are the different types of mating flanges? Name the 4 most common
Flat face
Raised face
RTJ( Ring type Joint)
Tonge & groove
Male & female
- What type of
information do you get from Isometric drawings?
Line routing, Line
orientation, Northing, easting & elevation, Bill of mat’l , Insulation type,
NDT requirement, Revision status, Material class’n , Design, operating &
testing temp/pressure, paint system, P&ID, slope, Service details, flow
direction, support details, notes;
- What type of
codes and standards do you use as a piping inspector?
ASME B31.3, ASME B31.1, ASME B31.5, ASME
B31.9;
JERES-A-004,
JERES-A-007, JERES-A-206, JERES-A-301, JERES-L-105, JERES-L-108, JERES-L-110,
JERES-L-150, JERES-L-130, JERES-L-310, JERES-L-350, JERES-L-351, JERES-W-011,
JERES-W-016
- What are the
types of Valves?
Gate valve, Globe valve,
Butterfly valve, Needle valve, Check valve, Control valve, Knife gate valve,
Based on
function: -non-return valve, isolation valve, regulation valve, special purpose
valve,
- What are the
main things you will check before Bolt
torquing ?
Size of bolt, Calibration of torque wrench,
Manual /hydraulic require, Lubricant, Friction factor for threaded lubricant,
torque value, JERES-L-109 / 351
- Write 3 Saudi
Aramco piping standards (L-Series)?
SAES-L-105, SAES-L-108, SAES-L-110, SAES-L-150, SAES-L-130, SAES-L-310, SAES-L-350,SAES-L-351
- Write minimum
ten hydrostatic test punch list items prior to
commence hydrotest atsite ? Indicate which is YES item & NO item
1.
All hot work shall be completed
2.
Strainers shall be removed
3.
All NDT & DT completion
4.
PWHT completion
5.
Adequate attachment
6.
Coating on weld joint shall be removed.
7.
Calibration of equipments used. Test blind MTC.
8.
Test certificates of testing fluid
9.
Components in new piping systems which interfere
with filling, venting, draining or flushing shall not be installed. (orifice plates,
flow nozzles, sight glasses)
10. All joints (flange,
threaded, welded or mechanical seals) are left exposed for visual leak
detection during the strength test.
11. All permanent flange joints
were inspected, gasket mat'l verified & properly torqued .
12. Drains shall be provided at
all low points of the piping system.
13. Vents and drain valves,
both temporary and permanent, conforms with the piping class or rating.
14. Supports are installed.
Additional temporary support may be installed as required.
15. Expansion joints and spring
hangers or spring supports are provided with temporary restraints.
16. Arc strikes, gouges, and
other indications of careless workmanship (such as surface porosity, uneven
weld profiles, and undercut) shall be removed by grinding and inspected by
magnetic particle or liquid penetrant method.
17. Drains are provided
immediately above check valves (vertical lines)
18. All threaded joints up to
the first block valve of hydrocarbon pipeline are seal welded. Thread
engagement has been verified & accepted.
19. The pressure testing
manifold is separately pressure tested to at least 1.2 times the system test
pressure but not less than the discharge pressure of the pump used for the pressure
testing.
20. Line compliance with
Isometrics:
i. Correct Materials utilized
grade/schedule (Bill of Mat'ls)
ii. Correct flange and fittings
rating
iii. Construction tolerances per SAES-L-350
- Which type of
documents/reports attached in hydrostatic test package?
Refer Attached
- Weep hole size
shall be drilled for dummy pipe support will be ________mm
Weep hole shall be located near base plate
for all vertical dummy pipe support & near run pipe at 6’O clock position
for horizontal dummy. (SAES-L-350 13.2.3 & L-310 14.7.2)
- What is dead
leg and explain?
·
Dead Legs: Piping sections that are potential for
internal corrosion due to flow stagnation.
·
Dead legs are created mainly by flow
stagnation enhanced with presence of settled water and solid deposits.
·
When the length of
the section or branch , for 2 inch pipes and larger, is longer than three times
its pipe diameter, or 1.22 m (4 ft) in length, the length of the dead leg is
the distance measured from the outside diameter of the header (or run) to the
near end of the branch valve.
·
For branch
connections of 1-½ inch NPS and smaller, the length of the dead leg is the
distance measured from the end of the boss to the near end of the valve.
- Write any 2
types of piping supports?
Shoe, Spring loaded, resting, weer pad,
- Line class 103CS3C
is listed on the Isometric Drawing. Explain each________
1 03 CS 3 C
Raised face Flange rating 300 Carbon steel C.A-4.5mm Caustic
As per JERES-L-105 page 375-377
- What
type of connection is acceptable for a 24” header, 12” branch?
- How
many minimum Pressure gauges to be installed during hydro test?
Two( JERES-A-004, para 7.1.5)
Relief valve calibration period would be___________
One week, per JERES-A-004 para 5.5.1
- What
is a PIP?
Process industry practices
- Name
the different types of
Service Conditions ?
NFS : - Normal services, Category M,
Category D, High pressure fluid services( ASME-B31.3)
- How
do you verify (name several items to check) that the correct piping
material is used?
Material specification, Pipe size,
schedule, length, flange face rating, olet size rating, threaded/socket weld
type, MTC, PMI report.
- How
do you identify fittings and flanges?
By material classification, size, rating,
joint type (lap, socket, threaded, butt), face;
- How
do you check piping for the correct schedule?
Verify pipe material thickness by Vernier
at the end or UT on surface or stenciling done by the manufacturer (visual) or
heat number, traceability by MTC of product.
- What
is the standard mill tolerance for piping 2’’ & less?
12% of nominal wall thickness
- What
is the tolerance for
ovality of piping?
5% of nominal diameter at any cross section
other than weld end & 3% at weld end (JERES-L-350 para 9.2)
25.
What is the difference between
torqueing CS and SS bolting?
CS: - Yield strength High; Torque value High
SS: -
Yield strength low ; Torque value low
- What
are
jackscrews and when are they required?
Used in flange joint
assemblies which often require frequent separation includes orifice plate,
spectacle plates, spacers, screens, and drop out spools shall be provided with
jack screw to facility separation and opening for the maintenance. When flange
separations are used, jackscrews are not required. Jackscrews shall be installed
to be accessible from both sides of the pipe. For orifice flanges, jack screws
shall be installed at 3 & 9 o’ clock positions. (JERES-L-310 para 17.7)
- What
is often overlooked during orifice flange fabrication?
·
Inside surface of welded joints at @ orifice
flanges shall be ground & machined smooth (JERES-L-350 para 10.4.2)
·
Orientation of taps are as per JERSD-J-0001
·
All parallel pipe lines with adjascent orifice
fittings shall have a min spacing of 300 mm (12 in) between flanges outside
diameters if horizontal taps are required. Where this spacing is not practical
follow JERSD-J-0001.
Orifice flanges in adjacent lines shal be
staggered so that no two pairs of orifice flanges are less than 1 m( 3ft) apart.
28.
What is the maximum diameter piping
allowed in hazardous service?
Socket weld: - 2” for maintenance &
minor modification & 1-½” for new construction
Threaded: - 1-½” for standard fitting &
valve, and 2” maximum when required for maintenance, minor field minor
modification of existing piping system( JERES-L-110 para 7.2)
29.
What is the minimum sized piping that
can be installed on pipe racks?
Ø1”
30.
Can Teflon tape be used prior to seal
welding?
No, (JERES-L-110 para 8.5)
31.
How many threads can be visible after
seal welding threaded joints?
No, should cover all exposed
threads( JERES-W-011 para 12.15.3)
- What
is the gap requirement for socket welds for new construction?
1.5mm-3mm (ASME B31.3 fig 328.5.2C)
33.
Give examples of unique support
details that allow piping freedom of movement for thermal expansion?
Guide support, Moving saddle support,
Expansion ballons , shoe support, Spring loaded
- When you will
apply 24 hours recorded hydro test?
If for justifiable safety reasons the UG
line must be backfilled, then the joints shall remain exposed during testing,
otherwise the test shall be a 24 hour recorded test . (JERES-L-150 para 7.4.2)
- Difference
between carbon steel and stainless steel?
CS: - Low cost, no chromium content,
suitable for non-corrosive service upto 350 degree C, max carbon 0.3%.
SS: - Contains more than 12% Cr, 0.08% C,
Suitable for corrosive, cryogenic, High temp services, costly.
- Difference
between RT & UT?
RT: - Uses X-ray or Gamma ray to detect
discontinuities, reveals mostly volumetric . planar defects & subsurface
defects not detectable easily
UT: -Uses ultrasonic beam to detect
discontinuities reveals both planar & volumetric defects, but size &
exact location of defects are not easily identifiable. Possible only on
materials that do not defract UT waves.
- Difference
between PT & MT?
MT: - Only
Applicable for ferromagnetic materials & able to detect both surface &
sub surface discontinuities, compare to PT examination it takes less time for
testing & inspection; Applicable for large temp range.
PT: -
Applicable for both ferromagnetic & non ferromagnetic materials & able
t detect only surface discontinuities, It requires more time; Applicable for
small temp range.
- How do you
control material in fabrication shop?
1)
All materials shall have material spec and grade
stamped or stenciled & clearly marked with permanent marker.
2)
All materials, heat no. will be made traceable to
MTC from approved vendor & no material substitution will be done without
proper approval from the company.
3)
All materials shall be stored & stacked
separately as per material grade.
4)
Heat no. shall be transferred before cutting into
pipes that have to be cut.
5)
All materials shall be color coded as per
tracebility procedure
- Write
inspection items during valve installation?
1.
Valve type corrects at the location
2.
Valve test certificate
3.
Valve tag as per P&ID
4.
Valve direction of flow as per P&ID
5.
Gasket bolts as per isometric & type
6.
Handle direction
7.
Chain wheel installed
8.
Valve flange face condition
thnks bhai
ReplyDeletethenks, sir jajakallah kheir for this one blog wrighting
ReplyDeleteThanks
ReplyDeleteupdate more quistion answer about ndt,welding,fittings,structure.
ReplyDeleteThanks sir
ReplyDelete