1 |
After installing one pair
of post which component of scaffold should be install |
|
|
A/
Runer B/ Brace
C/ Ties D/
Guys |
|
|
A |
2 |
Prior to install scaffold
a scaffold supervisor must look |
|
|
|
A/
Height of scaffold B/ Width of
scaffold C/ Length of scaffold D/ Load
rating Scf |
D |
3 |
Who will install red
tag |
|
|
|
|
|
|
A/ Scaffold supervisor B/
Scaffold inspector C/ Permit receiver D/ Permit issuer |
A |
4 |
What type of rope used to lift scaffold material ( drawing ) |
|
|
A/ Rolling hitch B/ Reaf knot C/ Timber hitch D/ Drum hitch |
|
|
5 |
Scaffold plan required |
if scaffold height
increase more then |
|
mtr |
|
|
A/ 4.0 mtr |
B/ 38.0 mtr C/ 3.0 mtr
D/ 12.2 mtr |
|
|
D |
6 |
If yellow tag installed
on the scaffold what is to be worn |
|
|
|
A/ Safety belt B/ Life lice C/
Full body harness anchored D/
Full body harness |
C |
7 |
Ladder 1st rung height
from the ground |
|
|
|
|
|
A/ 600mm/ 2ft B/ 300mm/1ft C/ 1200mm/ 4ft D/ 1800mm / 6ft |
|
A |
8 |
Scaffold plat form slope |
|
|
|
|
|
|
A/ 1;3
B / 1;1 C / 1;4 D / 1;2 |
|
|
|
C |
9 |
Tread depth of stairway
at least |
|
|
|
|
|
A / 220mm B / 150mm C / 300mm D / 400mm |
|
A |
|
|
|
|
|
|
|
|
|
10 |
Mediume duty scaffold
underhung maximum longitudinal post spacing |
|
|
A / 1.2
B / 1.8 C / 1.5 D / 3.2 |
|
|
|
C |
11 |
OSHA 1926.450 Tank
builders bracket scaffold space atleast |
|
|
|
A / 1.5
B / 3.2 C / 1.2 D / 2.4 |
|
|
|
B |
12 |
Check coupler shall be install |
|
|
|
|
|
|
A/ Bellow the runer B/ Bellow the transom C/On the beam
D/Top&Bottom H/ tube |
D |
13 |
If yellow tag is install
Fullbody harness shall be anchored to |
|
|
|
A /Conduit B / Steel stucture C / Runner D / Transom |
B |
14 |
Above the platform
headroom height atleast |
|
|
|
|
A / 2.0 M B / 1.5M C / 2.5M D / 1.8M |
|
|
D |
15 |
An installed power line
60kv scaffold clearance atleast |
|
|
|
A / 4.0mtr B / 1.0mtr C / 3.0mtr D / 1.2mtr |
|
|
A |
16 |
Bracket scaffold plank
shall be overlaped |
|
|
|
|
Plank shall be overlape in one direction only and minimum overlape
230mm ( 9'' ) |
|
17 |
Medimum duty mobile
scaffold caster wheel dia |
|
|
|
|
A / 5''
B / 7'' C /4'' D /
3'' |
|
|
|
B |
18 |
Mobile tower scaffold caster wheel must
have |
|
|
|
|
A / Pin
B / Base plat C / Wheel
lock D / Screw jack |
|
C |
19 |
Landing platform wide atleast |
|
|
|
|
|
|
A /27''
B / 20'' C / 15'' D / 21'' |
|
|
|
A |
20 |
1!/2 thick plank span
length increase 1.5 mtr how many board bearer atleast |
|
|
A / Two
B / Foure C / One D / Three |
|
|
C |
21 |
A light duty scaffold has
8 planked level howmany working platform shall be consider |
|
|
A / One
B / Zero C / Two D / Three |
|
|
A |
22 |
Base plat shall be used all place
except |
|
|
|
|
|
A /Mobile scaffold B/ Light duty scaffold C/ Tower scaffold D/ Heavy duty scaffold |
A |
23 |
Soft ground required |
|
|
|
|
|
|
A / Sill board B / Screw jack C / Base plat D / Level the ground |
A |
24 |
All scaffold tubing must
have marked |
|
|
|
|
|
A / Bs-1139 B / 10219 C / ASTM-500 D / ASTM-123 |
|
D |
25 |
Load rating of fabricated
tubeler scaffold platform |
|
|
|
|
A / Light duty B / Special duty C / Medium duty D /All purpus |
A |
26 |
SGB type material
birdcage scaffold transverse side 1.8mtr longitudinal direction must |
|
|
A/ 1.5
B / 1.8 C / 2.5 D / 2.4 |
|
|
|
C |
27 |
When pair of post in
position which componet install first |
|
|
|
A / Outrigger B / Raker C / Tie D / Ledger |
|
|
D |
28 |
Duration of Reinspection
of tag |
|
|
|
|
|
A / 3 Weeks B / 2 Weeks C / 1 Weeks D / 4 Weeks |
|
B |
29 |
What kind of rope use
lowering material during dismantle scaffold |
|
|
A / Steel rope B / Knock roll C / Timber Hitch D / Nilon rope |
D |
30 |
As per SSH Sole plat
(Sill board) not required |
|
|
|
|
A / Loose sand ground B/ Concrete ground C/ Asphalt ground D/ Sand Surface |
B |
31 |
Where Use Base plate |
|
|
|
|
|
|
A/ Concrete ground B/ All over except mobile C/ Asphalt ground D/Sand surface |
B |
32 |
What type of scaffold is
consider as Special scaffold |
|
|
|
A / 120kg/m2 |
B / 290kg/m2 C / 240kg/m2 D / 175kg/m2 |
|
B |
33 |
Which type of Scaffold
required for piping Equipment work |
|
|
|
A / Light duty B / Special duty C / Medium duty D / General |
B |
34 |
From which height
guardrail system required when person protect from fall |
|
|
A / 2.0mtr B / 1.6mtr C / 1.2mtr D / 1.8mtr |
|
|
D |
35 |
Toprail of guardrail
system is inbetween |
|
|
|
|
|
A/ 0.95mtr(38'')-1.15mtr(45'') B/ 0.8mtr(32'')-0.9mtr(35'') |
|
|
|
C/ 1.0mtr(40'')- 1.20mtr(48'') D/ 0.7mtr(28'')- 0.95mtr(38'') |
|
A |
36 |
Distance from face of
wall or steel stucture must not exceed |
|
|
|
A/ 360mm (14'') B/ 250mm(10'') C/ 300mm(12'') d/ 230mm(9'') |
A |
37 |
Minimum clear Headroom
for scaffolding platform |
|
|
|
|
A/ 1.8mtr(6') B/ 3.0mtr(10') C/ 2.0mtr(6.6') D/ 2.5mtr (8') |
|
A |
38 |
Temprary stairways tread
depths atleast |
|
|
|
|
A/ 220mm(9'') B/ 280mm (11'') C/ 215mm (8'') D/ 150mm(6'') |
A |
39 |
The distance between
bottom rung of ladder to base at least |
|
|
|
A/ 600mm(2ft) b/ 1200mm(4ft) C/ 300mm(1ft) d/ 1500mm(5ft) |
|
|
40 |
What type of stamps to be
applied on the scaffold tubes |
|
|
|
A/ BS - 1139 B/ ASTM - 123 C/ BS- 2482 D/ ASTM - 125 |
A |
41 |
What is required end of
planks more then 25(1'') splited |
|
|
|
A/ Baded B/ no banding C/ Nailed C/ Tie with wire |
A |
42 |
All type connection shall
be made by |
|
|
|
|
|
A/ Double coupler B/ Putlog coupler C/ Siwval coupler D/ putlog&siwval |
A |
43 |
Tie must connected with
always |
|
|
|
|
|
A/ Close node point B/ With outrigger C/ Bracing D/ With min 2 ledgers or posts |
D |
44 |
Bracing connection
made |
|
degree |
|
|
|
A/ 35 dg to 55dg |
B/ 45dg to 55dg C/ 30dg to40 dg |
D/ 40dg to 45 dg |
A |
45 |
The slope of scaffolding
platform not exceed |
|
|
|
|
A/ 1 vertical to 4 horizontal |
|
B/ 4 horizontal to 1 vertical |
A |
|
C/ 2 vertical to 1
horizontal |
|
D/ 3 horizontal to 2
vertical |
|
46 |
Wate is the procedure
dismantle scaffold |
|
|
|
|
A/ Top runner B/ Lift by lift C/ Tie & Transom D/ Any where |
B |
47 |
What is the minimum
distance from scaffold to 60 kv power line |
|
|
A/ 3 mtr B/ 3.5 mtr C/ 4 mtr D/ 4.5 mtr |
|
|
C |
48 |
What is the minimum
distance of runner joint to the post |
|
|
|
A/ 300 mm B/ 200 mm C/ 280 mm D/ 350 mm |
|
A |
49 |
Unless Otherwise
specified in manufactured instructions
of system scaffold braced |
|
|
full height of each |
|
|
|
|
|
A/ 10 mtr(33') B/ 15 mtr(45') C/ 8 mtr(8') D/ 6 mtr (21') |
A |
50 |
Distance from base to
foot tie must be |
|
|
|
|
|
160 mm(6'') min B/ 200 mm(8'') min C/ 160 mm(6'') max D/ 250 mm(10'') max |
A |
51 |
When bearer& runner
joints must be far from the post maximum |
|
|
A/ 12'' (300mm) B/ 16''(400mm) C/ 6''(150mm) D/ 18''(450mm) |
A |
52 |
Scaffolding with one
working platform&Eight additional PLF which type of scaffold it is |
|
|
A/ Heavy duty B/ medium duty C/ Light duty D/ Special duty |
C |
53 |
SGB Cuplock type Birdcage
scaffold transom side 1.8mtr what is the longitudinal side |
|
|
A/ 2.5 mtr B/ 1.8 mtr C/ 1.2 mtr D/ 1.0 mtr |
|
A |
54 |
Heigher then which height
of scaffold reviewed by Loss Prevention |
|
|
A/ 6.0 mtr (21ft) |
B/ 38 mtr(133ft) C/ 12.2 mtr(40ft) D/ 10 mtr(30ft) |
B |
55 |
Tube&coupler Medium
duty scaffold transverse post spacing 1.2 m what is longitudinal |
|
|
A/ 1.8 mtr B/ 2.4 mtr C/ 1.2 mtr D/ 2.0 mtr |
|
|
A |
56 |
Medium duty Mobile
scaffold Caster wheel dia at least |
|
|
|
A/ 120 mm (5'') B/ 170 mm (7'') |
|
|
|
B |
57 |
What device to install on
mobile scaffold caster wheel |
|
|
|
A/ Wheel lock B/ Screw jack C/ jack plate D/ Base plate |
A |
58 |
50 mm thick OSHA
certified planks used on tank bracket scaffold what is the |
|
|
circumferential distance of bracket
strap centre |
|
|
|
|
A/ 1.5 mtr B/ 3.2 mtr C/ 2.4 mtr D/ 1.8 mtr |
|
C |
59 |
What is the maximum load
rating of fabricated tubler frame scaffold |
|
|
A/ 120 kg/m2 B/ 170kg/m2 C/ 240kg/m2 D/ 290kg/m2 |
A |
60 |
Bracket scaffold planks
overlap minimum |
|
|
|
|
|
A/ In one direction with minimun
overlap 230 mm (9'' ) |
|
|
|
|
B/ In both direction with minimun
overlap 230 mm (9'' ) |
|
|
|
|
C/ in both direction with minimun
overlap 300 mm (12'') |
|
|
|
|
D/ in one direction with
minimum overlap 300mm (12'' ) |
|
|
A |
61 |
Check coupler shall be
installed |
|
|
|
|
|
A/ Top of hunger tube&Bottom of
Trapaze tube |
|
|
|
|
B/ Under of hunger tube & Top of Trapaze
tube |
|
|
|
|
C/ Under&top of the
Beam |
|
|
|
|
A |
62 |
What is the height of
first platform in system scaffold |
|
|
|
A/ 1.5 mtr B/ 2.0 mtr C/ 1.8 mtr D/ 2.5 mtr |
|
B |
63 |
Scaffolding landing
&Walkway shall be at least |
|
|
|
|
A/ 675 mm(27'')3
planks B/ 600 mm(24'') C/ 760 mm(30'') D/ 1200 mm(47'') |
A |
64 |
Under hung scaffold
longitudinal side hanger tube spacing more then 1.5 mtr atleast.. |
|
|
A/ one board bearer B/ 3 board bearer C/ 2 board bearer D |
/ not required |
C |
65 |
Yellow tag is applied
what type of PPE will worn |
|
|
|
|
A/Full body
harness&anchored |
B/ Life line C/ Safety belt&anchored D/Safety belt A |
|
66 |
Load required for safw
anchore point at least |
|
|
|
|
A/ 2400 kg(5291lbs) B/ 2000kg(4409lbs) C/ 2260kg(5000lbs) D/ 2600kg(5732lbs |
A |
67 |
What is the purpose of
use bracing on scaffold |
|
|
|
|
A/For rigidity of
scaffold B/For inspection C/For looking good
D/For contractor Scaffold / A |
|
68 |
Where are use plan
bracing |
|
|
|
|
|
|
A/ Tower &mobile
scaffold B/ Long scaffold C/ Run scaffold D/ Any where |
A |
69 |
Which type of scaffold
used caster ? |
|
|
|
|
|
A/ Tower scaffold B/ Mobile scaffold C/ System scaffold D/ Any scaffold |
B |
70 |
Which type of lanyards
suitable to use for scaffold |
|
|
|
|
A/ Locking type
snaphooks B/ D ring type C/ Only one lock type D/ Any type |
A |
71 |
What is the load rating
for light duty scaffold |
|
|
|
|
A/
240kg/m2(2.4kn/m2) B/
120kg/m2(1.2kn/m2)
C/250kg/m2(2.5kn/m2)
D/270kg/m2 B |
|
72 |
What type of scaffold for
abrasive blasting and cleaning |
|
|
|
A/ Light duty B/ Special duty C/ medium duty D/ Any type scaffold |
C |
73 |
What is the purpose of
special duty scaffold |
|
|
|
|
A/ To load greater then
240kg/m2 B/Any load C/ To load less then 240kg/m2 |
A |
74 |
Where install ledger on
the scaffold |
|
|
|
|
|
A/ Lenth side B/ Width side C/ For bracing D/ Any where |
A |
75 |
What is the purpose of
using screw jack on scaffold |
|
|
|
A/ Compesate variation of
ground B/ For load rating C/ For scaffold stability |
A |
76 |
Cantlivered more then
3.0 mtr out side the stucture what type of scaffold |
|
|
A/ Medium duty B/ Light duty C/ Special duty D/ None of above |
C |
77 |
Where use spigot |
|
|
|
|
|
|
|
A/ System scaffold B/ Tower scaffold C/ Mobile scaffold D/ Any type scaffold |
A |
78 |
What is the length of
trapaze tube |
|
|
|
|
|
A/ 450mm-600mm B/ 500mm-700mm C/ 200mm-400mm D/ 150mm-300mm |
A |
79 |
Guard rail system shall
be able to with stand with out failure a force at least |
|
|
A/ 80kg (200pounds) B/ 100kg(220pounds) C/ 110kg(242pounds) D/ 90kg |
D |
80 |
What is the length of
lanyards |
|
|
|
|
|
|
A/ 6 Feet(1.8mtr) B/ 6.5Feet(2.0mtr) C/ 8Feet(2.4mtr) D/ 10Feet(3.0mtr) |
A |
81 |
Why use snaphooks and D
ring in personnel fall arrest systm |
|
|
|
A/ To prevent rool
out B/ To prevent body C/ To hang D/ Any purpose |
A |
82 |
Horizontal &Vertical
life lines made by |
|
|
|
|
|
A/ 10mm(3/8'') minimum diameter
steel rope B/ 11mm minimun diameter
mild wire rope |
|
|
C/12mm minimum diameter
nylon rope D/8mm minimun diameter
polypropelene rope /A |
|
83 |
Horizontal an unload sag
at the center not greater then ? |
|
|
|
A/ 300mm(12'') B/ 250mm(10'') C/ 200mm(8'') D/ 400mm(16'') |
A |
84 |
Toeboard minimum vertical
height &thickness at least |
|
|
|
A/ 200mm(8'')-40mm(1.5'') B/ 150mm(6'')-50mm(2'') C/100mm(4'')-25mm(1'') |
|
|
D/ 120mm(5'')-50mm(2'') |
|
|
|
|
C |
85 |
Toeboard shall be capable
load at least ? |
|
|
|
|
A/ 23kg(50pounds) B/ 25kg(55pounds) C/ 30kg(66pounds) D/ 20kg(44po) A |
|
86 |
Where tools material
equipment are piled to a point heigher then the top eadge of toe |
|
|
board what kind of protective screen
to be used to prevent falling &protect striking worker |
|
|
A/ 18 guage wire with a maximum 13mm
mesh |
|
|
|
|
B/ 20 guage wire with a maximum 20mm
mesh |
|
|
|
|
C/ 24 guage wire with a maximum 16
mm mesh |
|
|
|
|
D/ 16 guage wire with a
maximum 18 mm mesh |
|
|
A |
87 |
Asafe means of entry and
exit shall be provided |
|
|
|
|
A/Above
or bellow 2ft B/ Above or bellow 4ft C
Above or bellow 6ft D/Above or bellow3ft |
A |
88 |
What is width and lenth
of temporary stairway landing |
|
|
|
A/ 560mm(22'')
wide--760mm(30'')long B/
760mm(30'')wide--560mm(22'') long |
|
|
C/
580mm(23'')wide--600mm(24'') long
C/ 630mm(25'')wide--760mm(30'') long |
A |
89 |
What is the vertical
height of temporary stairway |
|
|
|
|
A/ 3.7mtr(12ft) B/ 4 mtr(13ft) C/ 4.5 mtr(14ft) D/ 3.5 mtr (11.5ft) |
A |
90 |
Temporary stairway shall
be installed which degree ? |
|
|
|
A/ 30- 50 degree B/ 35- 40 degree C/ 40- 50 degree D/ 30- 40 degree |
A |
91 |
Temporary stairway riser
height at least and maximum how much |
|
|
A/ 6''(150mm)-8''(215mm) B/ 9''(220mm) 11''(280mm) |
|
|
|
C/ 4''( 100mm)-8''
(215mm) D/ 8''(215mm)- 6''
(150mm) |
|
A |
92 |
Temporary stairway tread
depth how much at least and maximum ? |
|
|
A/ 9''-220mm 11''-280mm B/ 6''-150mm 8''-220mm |
|
|
|
C/ 11''-280mm
8''-220mm D/
8''-220mm 6''-150mm |
|
A |
93 |
Temporary stairway
handrail height shall be ? |
|
|
|
|
A/ 940mm 37''-860mm 34'' B/ 950mm 38'' -1150mm
45'' |
|
|
C/ 940mm 37'' -950mm
38'' D/ 860mm 34''
-1150mm 45'' |
A |
94 |
Temporary stairway
minimum clearance in between hand rail& wall shall be ? |
|
|
A/ 80mm B/ 50mm C/ 100mm D/ 150mm |
|
|
A |
95 |
Temporary ram and walk
way slope not more then |
|
|
|
|
A/ 1 V 3 H B/ 1 V 4 H C/ 1 V 1 H D/ 1 V 2 H |
|
|
A |
96 |
Post spacing is Depend on
what |
|
|
|
|
|
A |
Length of
Scaffolding |
|
|
|
|
|
|
B |
Width of Scaffolding |
|
|
|
|
|
|
C |
Height of Scaffolding |
|
|
|
|
|
|
D |
Load rating of
Scaffolding |
|
|
|
D |
97 |
IF THE LADDER RUNG OR
SIDE IS DAMAGE WHAT YOU HAVE TO DO |
|
|
|
A Repair&Used |
B |
REMOVED FROM S/ARAMCO |
|
|
|
C |
CAN USE IF SAMALL DAMAGE |
D |
NONE OF ABOVE |
|
|
|
98 |
WHAT IS THE DISTANCE
BETWEEN THE LEDGER AND TRAPEZE TUBES |
|
|
A |
3 FT |
B |
2 FT |
|
|
|
|
|
C |
1 FT |
D |
4 FT |
|
|
|
|
99 |
WHAT IS THE DISTANCE
BETWEEN THE TOEBOARD AND WORKING SURFACE |
|
|
A |
8 MM |
B |
5 MM |
|
|
|
|
|
C |
6 MM |
D |
4 MM |
|
|
|
|
100 |
WHAT IS THE MIN HEIGHT OF
TOP RAIL |
|
|
|
|
102 |
A |
1.15 M (45 INCH) |
B |
0.95 M(38 INCH) |
|
|
|
|
|
C |
0.80 M(32 INCH) |
D |
0.90 M (36 INCH) |
|
|
|
103 |
SUPERVISOR CAN SIGN LESS
THEN WHAT HEIGHT |
|
|
|
A |
8 M |
B |
12.2 M |
|
|
|
|
|
C |
6 M |
D |
10 M |
|
|
|
|
104 |
WHO WILL INSTAL THE RED TAGE |
|
|
|
|
|
A |
SCAFFOLD INSPECTOR |
B |
SCAFFOLD SUPERVISOR |
|
|
|
|
C |
LPD |
D |
PERMIT RECIVER |
|
|
|
105 |
MED/DUTY TUBE&COUPLER
SCAFFOLD IF PLANKS LEVEL 2 HOW MANY WILL BE WORKING PLF |
|
|
A |
3 |
B |
5 |
|
|
|
|
|
C |
1 |
D |
2 |
|
|
|
|
106 |
PLAN BRACING IN MOBILE&TOWER SCAFFOLD
SHALL BE INSTALL |
|
|
A |
AT THE BASE |
B |
AT THE TOP |
|
|
|
|
C |
EVERY LIFT |
D |
BASE &TOPE AND EVERY
THIRD LIFT |
|
|
107 |
IN HANGER TUBE HOW MANY
CLAMP FIX AT LEAST |
|
|
|
A |
3 |
B |
4 |
|
|
|
|
|
C |
2 TO BE CHECK |
D |
5 |
|
|
|
|
108 |
IF THE PLANKS THICKNESS
IS 50 MM THE MAXIMUM CIRCUMFERENTIAL DISTANCE BETWEEN |
|
|
A |
3.2 M |
B |
1.5 M |
|
|
|
|
|
C |
2.7 M |
D |
2.4 M |
|
|
|
|
109 |
RAMP OR WALKWAY SHALL
HAVE CLEATTS IF THAT IS |
|
|
|
A |
1 V- 3 H |
B |
1 V- 4 H |
|
|
|
|
|
C |
1 V-2 H |
D |
1 V-1 H |
|
|
|
|
110 |
RAMP OR WALKWAY ABOVE THE
HORIZONTAL DEGREES |
|
|
|
A |
35 D |
B |
15 D |
|
|
|
|
|
C |
25 D |
D |
20 D |
|
|
|
|
111 |
TIES OR GUYS SHALL BE
INSTALLED CLOSED TO THE HEIGHT OF |
|
|
A |
3 TIMES THE MINI BASE DIMENSION |
B |
2 TIMES |
|
|
|
|
|
C |
4 TIMES |
D |
NON ABOVE |
|
|
|
112 |
IF THE GAPE BETWEEN
PLANKS 25 MM WHAT TO DO( USE SSH) |
|
|
A COVER WITH PLANKS |
B |
USE PLY WOOD |
|
|
|
C |
NO NEED TO COVER |
|
D |
NON ABOVE |
|
|
113 |
IF SCAFFOLDING IS NOT
PASSED OR ALETRING WICH TYPE OF TAG WILL BE USED |
|
|
|
A |
RED TAG |
|
B GREEN
TAG |
|
|
|
|
C |
YELLOW TAG |
D
ANY TAG |
|
|
114 |
FOR BIRDCAGE SCAFFOLDING INTERIOR
LONGITUDINAL ZIG ZAG BRACING IN WICH DEGREES |
|
|
|
A |
30-35 DG |
B |
35-45 DG |
|
|
|
|
|
C |
35-55 |
D |
30-50 DG |
|
|
|
115 |
TEMPORARY
RAMP AND WALK WAY SLOPE NOT MORE THEN |
|
|
|
A |
ONE
VERTICAL UNIT THREE HORIZANTAL UNITS |
A |
|
|
B |
ONE VERTICAL UNIT FOUR
HORIZANTAL UNITS |
|
|
|
C |
ONE VERTICAL UNIT ONE
HORIZANTAL UNIT |
|
|
|
D |
ONE VERTICAL UNIT TWO
HORIZANTAL UNITS |
|
116 |
WHAT IS THE NECESSARY
WHEN ROOF WORK BEAR THE LOAD |
|
|
|
|
|
|
|
|
|
A |
|
|
A |
REINFORCED |
B |
PROVIDE SCREWJACK |
|
|
|
C |
PROVIDE SOLE BOARD |
|
|
|
|
|
D |
PROVIDE BASE PLATE |
|
|
|
|
|
|
|
|
|
|
|
|
117 |
|
DURING NIGHT TIME AN
ELEVATED WORK AREA WHAT TYPE OF LIGHT TO BE USED |
|
|
|
A |
ADEQUATE LIGHT ACCORDING
TO SAES-P-123 |
|
|
|
B |
ADEQUATE LIGHT ACCORDING
TO BS-1139 |
|
|
|
C |
ADEQUATE LIGHT ACCORDING
TO BS-5973 |
|
|
|
D |
ADEQUATE LIGHT ACCORDING
TO EN-10219-2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
118 |
WHAT IS THE SUSTAIED
WINDS SPEED ALLOWED TO WORK AN ELEVATED WORK AREA |
A |
|
|
A |
65 KPH(40MPH) |
B |
70 KPH(50MPH) |
|
|
|
C |
50 KPH(30MPH) |
D |
80KPH(70MPH) |
|
|
|
|
|
|
|
|
|
|
119 |
FLOATATION RING SHALL BE
PROVIDED AT INTERVELS NOT MORE THEN |
A |
|
|
A |
15 MTR(50 FT) |
B |
20MTR(65 FT) |
|
|
|
C |
10 MTR (33 FT) |
D |
5 MTR (15 FT) |
|
|
|
|
|
|
|
|
|
|
120 |
WHAT PRECAUTION SHALL BE
TAKEN TO PREVENT WORKERS TO HOT SURFACE |
A |
|
|
A |
BEARIER ,STAND BY MAN
WARNING SIGN |
|
|
|
B |
LADDER SIGN BOARD |
|
|
|
|
|
C |
COVER THE PIPE |
|
|
|
|
|
|
D |
ANY OF ABOVE |
|
|
|
|