TABLE OF CONTENTS
1........... PURPOSE
2........... SCOPE
3........... REFERENCES
4........... RESPONSIBILITIES
5........... MANPOWER AND EQUIPMENTS
6........... SAFETY
7........... GROUTING MATERIALS
8........... APPLICATION AND LIMITATIONS
9........... INSTALLATION
PROCEDURE (NON-SHRINK CEMENTITIOUS / EPOXY GROUT)
10......... FINAL INSPECTION & ACCEPTANCE
11......... ATTACHMENT
PURPOSE
The purpose of this method statement is to
estabilish and control all activities
involved for the installation of
mechanical equipments in accordance with good working practice as per Client
Standard Operation Instructor.
SCOPE
This method statement describes about the grouting
work shall be carried out the under various contexts in accordance with the
Saudi Aramco Requirements for the Luberef
Yanbu Refinery Expansion Project.
The method and operations committed hereunder will be
adhered to carrying out the works coming under its purview. This method
statement covers grouting works using cement based non-shrink grout and non-shrink
epoxy grout and dry pack grout.
REFERENCES
Saudi Aramco Specifications
1) SAES-Q-010
: Cement based, Non-Shrink Grout
for Structural and
Equipment
Grouting
2)
SAES-Q-011 :
Epoxy Grout for Machinery Support
3) SATIP-Q-010-01 :
Cement-Based Non-Shrink Grouting
Review of Compressive Strength Test Report
Formwork Inspection
Inspection
4) SATIP-Q-011-01 :
Epoxy Grout for Machinery Support
Strength Test Report
5) General
Instructions (GI)
Facilities
6) SG2419-HSE-PLN-002 : Loss Prevention Program
7) SG2419-QUA-PLN-001 : Project QA/QC Plan
Abbreviations
·
IFC :
Issued for Construction
·
Company :
Saudi Arabian Oil Company( Saudi Aramco)
·
Contractor :
SAMSUNG Engineering Co Ltd (SECL)
·
Sub-Contractor : Firms that has a
contract to do part of job
·
HSE : Health Safety Environment
·
JSA : Job Safety Analysis
·
SATIP : Saudi Aramco Typical Inspection Plan
·
SAIC : Saudi Aramco Inspection Check List
·
SATR : Saudi Aramco Test Report
·
RFI : Request for Inspection
·
QA/QC : Quality Assurance and Quality Control
·
FMC : Field Material Control
RESPONSIBILITIES
Equipment Engineer / Mechanical Superintendent
·
Shall report to
Construction Manager
·
Review the grouting
procedure of rotating and static equipment, erection drawing and responsible for over-all
direction, monitoring, coordination and control of all construction activities
related to the equipment installation and grouting works.
·
Prepare technical
deviation, concession request, if required.
·
Arrange as built
drawings whenever required in accordance with site condition.
Equipment Supervisor
·
Shall report to
Equipment Engineer/Mechanical Superintendent.
·
Coordinate with QA/QC
inspector while performing inspection as per Saudi Aramco Specification.
·
If any technical
deviation or discrepancy is observed during the execution, he shall raise site
technical query.
·
Shall ensure the installation
(dimensions, leveling and alignment) are as per vendor’s drawing and
specification.
Foreman
·
Shall be responsible
to arrange the required work permit prior to start any type of preparation
works.
·
Shall be responsible
for the direct execution of work involved in the equipment installation works
according to the plan and shall direct control and give instruction to the
labor.
·
Shall also ensure that
work is performed with proper tools, equipment, PPE and good housekeeping
around working area .
·
Shall ensure the
installation (dimensions, leveling and alignment) are as per vendor’s drawing
and specification.
QC Manager
·
Shall report to Site
Manager .
·
Shall have
responsibilities for the quality control of the equipment installation at site .
·
Shall be responsible
to the inspection or monitoring for preservation conditions in accordance with “Specification
for Preservation”.
QC Inspector
·
Shall report to QC
Manager.
·
Shall inspect the
incoming materials (receiving inspection) as per design general specification
and PO requirement.
·
Shall prepare the
inspection tools and measuring equipment for installation works.
·
Shall monitor and
inspect QC activities against Saudi Aramco specification and drawings.
·
Shall liaise with
Company Inspector during inspection, prepare and maintain inspection documents.
·
Shall ensure that
materials are handled, inspected and certified by concern authority.
Safety Officer
·
Shall report to Safety
Manager .
·
Shall review the work
permit before start of the work.
·
Shall ensure that all
equipment, tools and tackles are periodically inspected and color coding
procedure is followed.
·
Shall ensure that the
person involved in rigging are experienced and qualified as per Aramco
requirements.
·
Shall inspect whether
safety requirements are implemented and tool box meeting are conducted every
day.
·
Shall verify that the
personnel involving equipment installation and have undergone safety induction
program .
·
Shall verify that the
equipments (including lifting equipments) are in good and safe Working
condition.
·
Ensure that safety
requirements are implemented and adequate safety measure are undertaken to
prevent may damage to the work group, public, environment as well as
properties.
·
Shall monitor the safe
work plan, safety task assignment and job safety analysis conducted for the
job.
MANPOWER AND
EQUIPMENTS
Manpower
·
Supervisor
·
Helpers
·
Carpenters
·
Safety Crews
Tools and Equipment
·
Mixing Paddler
·
Electric Generator
·
Water Basket (Calibration Cup)
·
Mixing Bucket
·
Survey and leveling equipment such as
theodolite spirit level etc.
·
Air compressor
·
Safety equipments (PPE etc.)
SAFETY
·
Contractor’s safety supervisor shall carry
out the safety site inspections to ensure that the safety requirements laid out
in the HSE work plan are followed throughout all installation work.
·
Contractor’s manager/supervisor shall review
job safety assessment and work permit prior to the start of work, JSA will be
followed.
·
Pre-job instruction, toolbox meeting,
training for the labors for working at height, fall protection shall be
conducted by supervisor/foreman prior to the start of works.
·
Full body harness with double lanyard shall
be worn and properly hooked by everyone working at height of 1.8m and more, and
be hooked just above ones shoulder height.
·
Where provision to hook full body harness
does not exist, temporary lifelines shall be provided and harness shall be
hooked onto it.
·
Barricading of lifting area of equipment
shall be checked prior to the commencement of work and sufficient sign boards
shall be replaced.
·
All the lifting tackles shall be inspected
and color coded certified by HSE.
·
The work area shall be barricaded and no one
shall be allowed to work or move below the lifting activity or suspended load.
·
PPE implementation shall be monitored,
violation shall be recorded.
Working
at height of 1.8m and more, and be hooked just above ones shoulder height.
·
Scaffolds shall be thoroughly inspected
before green tag and use.
·
All equipment, tools safety accessories shall
be inspected on regular basis and shall be color coded as per safety
standard.
·
Trained fire watchman shall depute for all
hot work.
·
Slag and burrs due to welding, grinding or
cutting at heights shall be secured by enclosing the area with fire blankets.
·
Sufficient numbers of fire extinguishers
shall be provided near working places.
·
During working at height, tools shall be
secured with lanyard.
GROUTING MATERIALS
General
·
The material data
sheet for Non-shrink cementitious and epoxy grout shall be submitted to Company/Contractor
for approval prior to start grouting works. The approved material only
shall be used for steel structure and equipment grouting.
·
All grouts shall be
non-corrosive, non-staining and resistant to efforts to moisture.
Compressive strength of grout shall
meet or exceed the strength of foundation concrete.
Delivery, Storage & Handling
·
Non-shrink
cementitious grout shall be delivered to the site as dry mix in pre-measured waterproof
bags. Only water is to be measured at the site in the amount indicated on the
bag as per manufacture recommendation.
·
Non-shrink epoxy shall
be delivered to the site as a complete system in pre-measured packages to
facilitate accurate field mixing and instruction shall be followed as per
manufacture.
·
Grout shall be stored
in a dry & weather proof area within the temperature range recommended by
manufacturer . It is preferred to store in a dry warehouse. If the grout
material wants to keep outside, it shall be placed on pallets off the ground
surface and completely covered with durable plastic sheeting.
·
Any materials, which
found becomes damp or defective shall be removed from the site. Time of storage for non-shrink
grout shall not exceed manufacturer’s recommendation .
APPLICATION AND
LIMITATIONS
General
·
Non-shrink grout shall
be used for all mechanical equipment as per specifications and standards.
·
Grouting of equipments
supports shall be in accordance with equipment manufacturer’s recommendations
and Aramco Standards.
·
The details for
grouting & form work for equipment foundation shall be as per approved GA
drawing.
Non-Shrink Cementitious Grout
·
Non-shrink
cementitious grout shall be used as per approved drawings, specifications and
standards.
·
This type of grout
shall also be used for grouting of structural column base plates having shear
keys seated in companion keys formed in foundation piers and for sleeved anchor
bolts designed to resist high shear forces.
·
Non-shrink
Cementitious grout shall be Grade C combination Volume-Adjusting in accordance
with ASTM C1107.
·
Plastic volume change:
Grout shall show no shrinkage( 0.0%) and a maximum of four (4) percent expansion
at any time before initial set when tested in accordance with ASTM C827.
·
Hardened volume
change: Grout shall show no shrinkage( 0.0%) and a maximum 0.2 percent expansion
in the hardened state when tested in accordance with ASTM C1107.
·
Compressive strength:
Grout shall have a minimum compressive strength at 28 days of 350kg/㎠ when tested in accordance with ASTM C109.
·
Initial set time:
Grout shall achieve initial set in not less than 45minutes when tested in
accordance with ASTM C191.
·
Soundness: Grout shall
contain no staining substances, no aluminum powder, no
more than 0.1 percent chloride ions by weight of cement, or other materials
known to increase drying shrinkage and/or compromise durability.
·
The non-shrink or
expanding grout shall be cementitious . Metallic fillers shall not be acceptable
as non-shrink or expansion additive. Grout containing calcium chloride additive
is not acceptable.
Epoxy Grout
·
Epoxy grout shall be
used as per approved drawings, specifications and standards.
·
The epoxy grout shall
be nonmetallic one hundred percent solids system and formulated with
thermosetting resins and inert fillers. The cured grout shall be unaffected by
oils, synthetic lubricants, water, or chemicals.
·
The mixed consistency
shall be pour able and self-leveling to ensure simple, accurate placement.
The manufacturer shall determine volume change during curing by laboratory tests in accordance with ASTM
C827.
·
Volume change: Epoxy
grout shall exhibit no shrinkage (0.0%) and a maximum of two (2) percent
expansion when testes in accordance with ASTM C579, modified to use an
indicator ball with a specific gravity between 0.9 and 1.1
·
Compressive strength:
Epoxy grout shall have a minimum compressive strength at 7 days of 845 kg/cm² or 12,000 psi (SAIC-Q-1054 Item A4)
when tested in accordance with ASTM C579.
·
Heat Development: The
peak exothermic of a 50mm diameter by 100mm high cylinder of grout shall not
exceed 35℃
when tested at 24℃ material and laboratory temperature.
·
The peak exothermic
temperature rise from ambient at maximum recommended pour depth shall not
exceed 49℃. The direct-contact
temperatures limit of grout to be used shall exceed the calculated
temperatures of machinery by at least 10 percent.
·
Thermal expansion:
Maximum coefficient of thermal
expansion (ASTM C531): 54 x 10-6 mm /mm/℃
·
Linear Shrinkage: Maximum linear shrinkage
(ASTM C 531): 0.080 percent.
·
Irritants: The use of
epoxy grout that gives off noxious fumes or volatile shall be prohibited.
·
Creep resistance: The
compressive creep shall be within 3.0±0.5 x 10-3 mm /mm when tested in
accordance with ASTMC1181 under a 28kg/cm2 constant pressure at 60℃.
·
Effective bearing area
shall be a minimum of 95%.
Installation of Equipment
8.4.1 After the final grouting, once the compressive strength
is achieved according to the requirements, the equipment shall be released for
further activity.
8.4.2 The drivers and driven equipment shall be
released for installation after the grout has cured for a minimum of 24 hours.
INSTALLATION PROCEDURE
(NON-SHRINK CEMENTITIOUS / EPOXY GROUT)
General
Grouting steps shall be based on manufacturer’s procedure,
approved drawings & Specifications, and this Method Statement.
Surface Preparation
9.2.1 Concrete on which grout bear has reached the
curing period up until the compressive strength has reached 70% of the
specified strength, but not less than 7 days after placement. (SAIC-M-2006:
Inspection of
Support Foundation Prior to Structural or Equipment Installation)
9.2.2 Concrete shall be sound and surfaces to be
in contact with grout shall be free of oil, grease, paint, laitance and other
coatings. Surface shall be roughened by chipping, abrasive blasting or other
mechanical means in order to expose coarse aggregate and
to create irregular surface to which the grout will bond. Prepared surface
shall be cleaned of all dust and loose particles. Raking and brooming of
neither the concrete before hardening to achieve rough surface is not suitable
nor a substitute for chipping or abrasive blasting.
9.2.3 After cleaning, foundation surface shall be tightly
covered to keep it free of dust and oil.
9.2.4 Before grouting, equipment bases and base
plates shall be leveled and aligned in accordance with design drawings and
equipment manufacturer’s recommendations. Vent holes may be necessary in the
base plate to eliminate air pockets.
9.2.5 Unless otherwise specified or shown on
drawings, the entire foundation surface under the base plate shall be grouted.
Areas not to be grouted, such as oil pans or air circulation spaces, must be
sealed off before the equipment is lowered into place.
This may be accomplished with oakum
or hemp rope, expendable fabric hose (such as canvas fire hose), rigid
polyurethane foam, Styrofoam or other soft compressible material.
9.2.6 When using a canvas fire hose, the hose
shall be pressurized to a maximum of approximately 0.34 kg/cm2 to avoid moving the equipment and
affecting its alignment. Also for epoxy grout the fire hose shall be wrapped
with polyurethane tape and coated with a heavy paste wax for ease or removal.
9.2.7 When using rigid polyurethane foam or Styrofoam
(do not use Styrofoam for epoxy grout), allow 6mm per 25mm of height for crush.
The foam shall be installed prior to setting the equipment to ensure a
leak-proof joint, apply a bead of caulking compound on the mating surfaces of
the concrete to the foam, and of the rigid foam to the bed plate.
9.2.8 Expansion joint in epoxy grout shall be
spaced at a maximum of 1.4 meters or 48 inches unless otherwise specified in
the approved drawing. Joint filler shall be compatible material and sealed with
silicon sealant.
(Note: As per Saudi ARAMCO Engineering Standards, only
Cement-Based Non-Shrink and Epoxy Grout are acceptable for Structural and
Equipment base)
9.2.9 When using non-shrink cementitious grout,
the roughened concrete surface shall be presoaked with clear, portable water in
accordance with manufacturer’s recommendation.
9.2.10 When non-shrink epoxy grout is used, all
surfaces must be kept completely dry before grouting, unless otherwise
specified by grout manufacturer.
Forms, Equipment and Tools
9.3.1 When forms are required they shall be
designed for rapid, continuous and complete filling of the space to be grouted,
Forms shall be of adequate strength to withstand the forces produced during
placement of the grout.
9.3.2 Forms shall be caulked or sealed with tape
to provide watertight seal.
9.3.3 For
non-shrink cementitious grouting, the foam shall be made according to the
grouting height with chamber to avoid grinding in the foundation corners after
grouting.
9.3.4 For non-shrink epoxy grouting, on the open
side ( Just opposite to pouring side), the
form shall extend a minimum of 25mm above the bottom of the base plate being
grouted and shall be placed no closer than 45mm~65mm from the edge of the base
plate.
9.3.5 On the pouring side, the form shall extend
at least 75mm above the bottom of the base plate and shall be place 45mm~65mm
from the edge of the base plate or manufacturer’s recommendation.
9.3.6 Form for cementitious grout (normal or
non-shrink) shall be coated with approved release agent to prevent grout
adherence and absorption.
9.3.7 All chamfered edges required in grouts shall
be incorporated into the forms.
9.3.8 The following tools and equipment shall be
used for grouting works,
Mixing and Placing of Grouting Material
9.4.1 Manufacturer’s instructions shall be
strictly followed for non-shrink grout preparation, proportions, mixing,
forming and depth of pour , pouring, curing and protection.
9.4.2 Grouting
shall be preferably be accomplished when ambient and mix temperature are
between 5℃
and 32℃ for
cementitious grouts and between 12℃ and 31℃ for
epoxy grouts. For non-shrink cementitious and epoxy grouts, manufacturer’s
recommendation shall be followed.
9.4.3 Sufficient
manpower and equipments shall be available for rapid and continuous mixing and
placing of grout. Grout shall be mixed in quantities no greater than can be
placed in the manufacturer’s specified working time for the temperature at which
the grout is being placed. Working time specified shall be considered a maximum
value and any grout remaining after the specified working time has elapsed
shall be discarded. Do not remix or re-temper stiffening grout.
9.4.4 Any grout that shows evidence of initial set
or entrapped air shall be discarded.
Once grout is mixed, it shall be
placed continuously and rapidly, preferably from one side only, to avoid cold
joints and minimize the change of air entrapment.
9.4.5 The grout level shall not drop below the
equipment base. The grout fill location shall be removed only after the grout
has filled past the new fill location. Expansion joint dividers shall be used
to section off the maximum areas to be poured and worked at one time. Expansion
joints shall be installed in accordance with the manufacturer’s instructions
for epoxy grout placements of long length or large area.
9.4.6 For flat base plates, grout shall be placed
across the small dimension of the equipment base from one long edge to the other,
in one direction only. The use of a head box with an inclined plane to direct
the grout across the compartment is recommended.
9.4.7 For inverted “U” shaped base plates, such as
pump base plates, the base shall contain a sufficient number of relief holes
(one 3mm minimum diameter hole per corner) or grout shall be poured from a
100mm hole in the center of each compartment.
9.4.8 Use of a vibrator is not permitted. Also
grout shall not be placed when vibrations are being transmitted by the
operation of other equipment. Such equipment must be shutdown while grouting
and kept idle until grout has set sufficiently.
9.4.9 Cementitious grout may be tampered or rotted
to eliminate voids. Care shall be exercise however , so that air is not
introduced into the grout.
9.4.10 In making deep pours , epoxy grout shall
generally be poured in thickness of 50mm to 100mm per layer. Minimum
depth of pour is 50mm or manufacturer recommendation .
9.4.11 Depth
of pour is dependent on the product selected and on ambient temperatures.
Deeper or shallower pours may be
made if permitted by the manufacturer’s standards.
9.4.12 The final layer, which is to
the adhere to the machine base shall be limited to between 25mm and 50mm in
thickness, measured from bottom of the machine base or manufacturers
recommendation. Epoxy grout shall not be rotted .
Surface Finishing
9.5.1 Exposed surface of grout shall slope away
from base plates.
9.5.2 Cementitious grouts shall be trimmed back to
the lower edge of the base plate and tapered to the existing
concrete once the grout has reached an initial set. Protruding edges shall also
be cut back.
9.5.3 Epoxy
grout cannot be trimmed after initial set. Top surfaces shall be finished to
proper slope before initial set.
9.5.4 Forms shall remain in place for 24hrs or
manufacturer’s recommendation.
9.5.5 The final layer, which is to the adhere to
the machine base shall be limited to between 25mm and 50mm in thickness,
measured from bottom of the machine base or manufacturers recommendation. Epoxy
grout shall not be rotted .
Curing & Protection of Grout
9.6.1 Non-Shrink Grout shall be cured in
accordance with the manufacturer’s recommendations or when reached up to 70% of
the specified strength but not less than 7 days whichever is more stringent.
9.6.2 The temperature of the base plate,
supporting concrete foundation and grout shall be maintained during
curing as per manufacturer’s recommendations.
9.6.3 After
placement, cementitious grout shall be protected from premature drying,
excessively hot or cold temperatures and mechanical injury. Curing of
non-shrink cementitious grout shall be in accordance with manufacturer’s
instructions.
9.6.4 Since water interferes with proper curing of
epoxy grouts, moist curing shall not be used.
9.6.5 Curing for epoxy grout shall be in
accordance with manufacturer’s instructions.
9.6.6 Unless stated otherwise by the manufacturer,
epoxy grouts shall be protected from sudden temperature change for 48hrs.
Fixing and Removed of Shim, Wedge & Pad Plate
9.7.1 Padding shall be done at four sides as
minimum or more if required, by using non-shrink cementitious grout for
maintain the level of base frame prior to anchor box grouting for pump
foundation.
9.7.2 If leveling screws are used to level
equipment, the screws shall be coated and backed off after the grout
has hardened (after 48hrs) so that machine loads are transmitted only through
the grout.
9.7.3 After
removing the jack bolt the jack bolt holes shall be filled with epoxy material.
While removing the jack screws, dial
indicator shall be placed on the base frame / plate and coupling to indicate
any movement is occurred .
9.7.4 Leveling shall be ensured within 0.2mm/m by
jack bolt. If required, shims shall be used as minimum .
9.7.5 Metallic shims for all equipment and
structural steel shall be blocked off and removed once the grout has hardened,
unless specifically requested otherwise by the rotating equipment
manufacturers. The space left by the removal of the shims shall be epoxy
grouted if required.
9.7.6 Where ever jack bolt is not available in the
base frame, the new jack bolt will be welded with base frame for
alignment.
9.7.7 For
other static equipment the sufficient pads shall be given between the anchor
bolts to maintain the base level prior to grouting.
9.7.8 The thickness of the pad plate shall be
minimum 10mm
Anchor Bolt / Box & Pipe Sleeves (Pump Foundation)
9.8.1 Except where the use of epoxy grout is
identified on drawing, all anchor bolt sleeves shall be filled with the
non-shrink cementitious grout after the equipment is in place. (Refer to IFC
Drawings)
9.8.2 Once the grouting is completed in the anchor
box, the epoxy grouting shall be done to the bottom of pump base
frame . (Refer to IFC Drawings)
9.8.3 After that, inside the base frame will be
filled with non-shrink cementitious grout. (Refer to IFC Drawings)
9.8.4 All surfaces shall be free of oil, grease
and foreign substances.
9.8.5 Where epoxy grout is used, anchor bolts
shall be protected from the grout by means of PVC pipe, rubber hose or polyurethane
wrapped in several layers around the bolt threaded portion. Annular space
within anchor bolt sleeves shall be plugged with a sleeve seal to prevent epoxy
grout entering the sleeved space.
Very informative post.
ReplyDeleteFor more information on grouting chemicals: http://roff.in/grouting-solutions/roff-rainbow-tile-mate-rtm/
Nice and more reachable blog chennai review. Kindly update about some modular kitchen cabinets chennai
ReplyDeleteI saw some beautful kitchen reviews is more helpful to us.
ReplyDelete