METHOD OF STATEMENT
FOR ADHESIVE BONDED JOINTS and BUTT and WRAP
LAMINATION JOINT OF REINFORCE THERMOSETTING RESIN...
1.0 PURPOSE
This method statement utilize to ensure that the
assembly & installation of RTR (Fiberglass) piping work will be carried out
safely, efficiently and in accordance with good working practice and as per
Project specification. The instruction is intended to give general application
guidance and establish controls during the preparation, fabrication,
installation, testing and final acceptance of RTR (Fiberglass) piping work.
2.0 SCOPE OF WORK
The scope of this method statement is applicable to
Non-Metallic U/G piping installation activities for RTR (Fiberglass) pipes which includes materials
storage, handling, transportation, pipe laying & installation, pipe
jointing such as Lamination, Taper/Taper adhesive bonded and Key-Lock type,
inspection, testing and back filling procedure that to be installed on the
Yanbu Export Refinery Project (YERP) EPC-3, Yanbu, KSA.
3.0
REFERENCE, STANDARD AND SPECIFICATION
3.1
Project Engineering Standards & Procedures
SPECIFICATION NO
|
DOCUMENT TITLE
|
SAES – A - 004
|
General Requirements for Pressure Testing
|
SAES – A - 007
|
Hydrostatic Testing Fluids and Lay-up Procedures
|
SAES – B - 017
|
Fire Water System Design
|
SAES – B - 067
|
Safety Identification and Safety Colours
|
SAES – L - 105
|
Piping Material Specification
|
SPECIFICATION NO
|
DOCUMENT TITLE
|
SAES – L - 610
|
Non Metallic Piping
|
SAES – L - 350
|
Construction of Plant Piping
|
SAES – L - 460
|
Pipeline Crossings Under Roads and Railroads
|
SAES – S - 070
|
Installation of Utility Piping Systems
|
3.2 Industry Standards &Codes
ASME B 31.3 Chemical
Plants and Petroleum Refinery Piping
ASTM D 2855 Underground Installation of Fiber Glass (RTRP)
AWWA C 950 Fiber Glass Pressure Pipe
3.3Manufacturer Standards
& Procedures
111-EP3-PU-G9L-9336 Bondstrand Installation, Operation & Maintenance
Manual
111-EP3-PU-G9L-9350 Bandstand RTR (Fiberglass) Piping Field Hydro Test
Procedure
3.4Piping Material Specification
PIPING CLASS
|
LINE SERVICE
|
BASIC MATERIAL
|
12FE0U2
|
FIRE WATER (FW)
|
RTR (Fiberglass)
|
12FE0U4
|
FRESH COOLING WATER (CW)
|
RTR (Fiberglass)
|
12FE0U6
|
OILY WATER SEWER (OWS)
|
RTR (Fiberglass)
|
12FE0U6
|
POTENTIALLY CONTAMINATED STORM WATER (PCS)
|
RTR (Fiberglass)
|
4.0MANPOWER, TOOLS AND
EQUIPMENTS
4.1Manpower
Project Manager Piping
Superintendent / Supervisor
Piping Engineer Civil
Supervisor
QC Manager / Supervisor QC
Inspector
Safety Officer / Supervisor Piping Foreman
Surveyor Pipe
Fitter
Crane Operator Qualified
Laminator
Rigger Watchman
/ Helper
Scaffold Erector Truck
Driver
Bonder Grinder
4.2 Tools and Equipments
Abrasive Cutting Disc Air Blower
Air compressor PPEs (Safety
helmet, hand gloves, Protective
clothing, goggles, dust masks, safety shoes,
respirator, SCBA)
Air Relief Roller Band clamp
with puller rings
Drilling Machine Exhaust fans
Engine Welding Machine Flapper-Wheel Sanders (Grit-60)
Grinder Hydrostatic
Test Pump / Filling Pump
Hacksaw Paint
Brush (4"wide) / Paint Roller
Hammer or Mallet Laminators Tool
Set
Slings Chain
Block
Measuring
Tape Power
Generator
Mechanical
Pullers Tenting
(Subject to weather conditions)
Mobile
Crane Rubber
Scraper Plate
Non-Metallic
Rope, Tag Line Resin Mixer
Pipe
Shaving Tools Heating
Blanket
Pipe
Support Grinding
Wheels
Pipe
vice Shackles
Power
Drive Lights
(with posts)
Pumps
& Motors Infra-Red
Burner or Hot Air Gun
Trailer
Truck Knife,
File Abrasive Paper
Ventilation
Equipments Wrap-Around
White
Marker Winch
5.0TERMS
PMT Project
Management Team
Contractor SAMSUNG
Engineering Company Ltd.
Subcontractor Raymond
Saudi Arabia Ltd.
6.0 RESPONSIBILITIES
6.1 Project Manger
Project Manager has the overall responsibility for
this Method of Statement and is responsible for supporting it and for ensuring
all entitles at the worksite actively participate. He is implementing,
administer and provide oversight for the project Safe Work Plan Process.
6.2 Project Supervisor
Ensure the full implementation of this Method of
Statement and identifies the requirements and add on resources for the
effective accomplishment of the installation of underground piping. Ensure that
hazard risk and mitigation measures determined during the project scheduling
process are provided to the respective craft supervisory personnel responsible
for safely performing the work.
6.3 Piping
Superintendent/Supervisor
Ensure full compliance of all piping foreman, pipe
fitters and labours regarding the execution of work in accordance with manufacturer’srecommendations
and YERP requirements. Secure all necessary work permits. As a responsible
Supervisor prior to assigning the work task performers, review any hazard, risk
and mitigation and
measures determined during the scheduling process,
visit task location, plan the work, analyze the work for any hazards and
consider potential safeguards.
6.4 Piping Engineer
Provide technical support to site operation section,
provide IFC drawings, specifications, piping test packages, standard and
technical specifications. Responsible for PMT review of drawings and data and
the resolution of technical work execution problems. Routinely review Safe Work
Plan documentation submitted daily by respective Responsible Supervisor(s). Take
an active leadership role in Safe Work Plan Process by verifying Responsible
Supervisor(s) are properly conducting Safe Work Plan discussion meetings,
routinely observe the Safe work Plan discussion meetings, routinely observe the
Safe Work Plan Process in the field, activelyparticipate
in the Safe Work Plan Process and regularly follow-up with observations of the
actual work activity.
6.5 Safety Supervisor/Officer
Check the
work area for any unsafe condition. Ensure that all safety requirements have
been adequately addressed and the work is carried out safely in accordance with
approved YERP Health Safety Environment (HSE) Safety Manual and Procedures.
Ensure that material safety data sheets are available at site.
6.6 QC Manager / QC Supervisor
QC Manager is responsible for the implementation of
all required quality controlled activities such as test and inspection for this
particular job. QCSupervisor is responsible for coordination, carrying out of
the inspection and testing details respective to this procedure. QC manager
monitors the QC Personnel in their daily functions and conducts reviews of
documentation and inspection/verification activities. Ensures adequately
qualified and experienced QC Personnel are assigned to inspection duties.
Identifies task related hazards and recommends to the Responsible Supervisor
the work processes that could be used to ensure safe operation.
6.7 QC Inspector
Monitors
daily piping activities and conducts inspections in accordance with the
approved Project Quality Control Procedure, associated procedures and
specifications. Prepares quality records and final acceptance documentation
where required. Maintains close working relationship with
PMT/Contractor/Subcontractor/Manufacturer Representative. Identifies task
related hazards and recommends to the Responsible Supervisor the work processes
that could be used to ensure safe operation.
7.0 SAFETY REQUIREMENTS
7.1 General
7.1.1 The main
early preparation and any work shall be completely complied with respect to
safety, Job Safety Analysis prior to execution of this particular job.
7.1.2 Necessary
permits for all related activities within the construction site shall be
obtained prior to the commencement of the job. Confined space permit shall be
utilized prior to start of any U/G work activities. The confined space work
shall be in accordance with the Confined Space Entry, Project Procedure - 833,
and an approved Confined Space Procedure.
7.1.3 Unusual and
unexpected acute hazard may be encountered while working inside the pipe, it is
therefore required that all personnel who will be involved in this activity
shall be oriented with nature of job and the hazards that might be countered. A
confined space procedure shall be established as per approved safety plan as
briefly outlined in this procedure.
7.1.4 Chemical
waste such as resin, catalyst and styrene shall be disposed separately from
other waste to prevent contamination of the surroundings as per the Project
Procedure - 816, Waste Management and an approved Chemical Disposal Plan.
7.2 Safety Precautions
The chemical
components required for butt & wrap joints present certain safety and
health hazards if not handled well. Following are the recommendation:
7.2.1 Hazards
7.2.1.1
Resin: Liquid resin contains styrene
which is flammable. Its vapours may cause irritation of the eyes, nose and
throat. Excessive inhalation may cause dizziness, drowsiness or loss of
consciousness.
7.2.1.2
Catalyst: Methyl ethyl ketone per oxide is a strong oxidizing
agent and is a fire and explosion hazard. It is irritant to eyes, skin and
mucous membranes, and is known as sensitizer. It shall always be stored in
original containers & only small quantity shall be taken to the work place
as per site activities/ requirement.
7.2.1.3
Solvent: (AP-62 or Methylene chloride) - The principal hazard
is a loss of consciousness in case of excessive in halation of vapours.
Exposure to high vapour concentration may cause cardiac irregularities.
7.2.2 Precautionary Measures:
7.2.2.1
Internal lamination shall be conducted in adequate
ventilation. Workers shall wear dust / vapour mask while mainly working inside
the pipe. All crew members shall use protective clothing (Long sleeved shirts,
long pants), safety glasses and rubber gloves.
7.2.2.2
Ventilation is a necessity when lamination in confined
areas because solvents tend to be heavier than air and migrate to lower levels.
The fresh air inlet of the ventilation system shall be located near the top of
the confined space, and the discharge should be located near the bottom,
positioned to eliminate the dead air spaces.
7.2.2.3
Exhaust fans shall be used for ventilation. Suction
side of the exhaust fan shall be kept on the top of the RTR (Fiberglas) branch
tops and the discharge should be in the bottom portion of the pipe. Refer
Figure - 1 at Safe Work Plan. Supplementary fans may be necessary to ensure
good air circulation.
7.2.2.4
Tools should be correctly selected for the purpose,
and also operated and maintained according to the manufacturer's instructions.
7.2.2.5
Suitable respirators shall be used if contaminant levels exceed
Permissible Exposure Limits. Air-Purifying or Air-Fed respirators complying
with an approved standard shall be used if a risk assessment indicates this is
necessary. Respirator selection shall be based on the known or anticipated
exposure levels, the hazards of the product and the safe working limits of the
selected respirator.
7.2.2.6
Extreme care should be used if tools have the ability
to create sparks in the presence of flammable vapours. "NO SMOKING" signs in all lamination
material storage and working area shall be displayed.
7.2.2.7
Goggles and face shield shall be worn, while grinding
to guard against flying particles and where necessary, hearing protection shall
be provided to prevent long term hearing loss.
7.2.2.8
Solvent cements for RTR are made from flammable liquids. These materials
shall keep away from all source of ignition. Adequate ventilation shall be
provided to reduce fire hazard and to minimize breathing of solvent vapours.
Proper PPE shall be used to avoid contact of cement with skin and eyes.
7.3 Waste Disposal
7.3.1
To achieve and maintain environmentally sound
practices for sanitation and for conservation of the environment, the
Contractor has to monitor waste accumulation and to ensure prompt and correct
disposal of the waste materials.
7.3.2
Non-hazardous wastes, hazardous waste and inert
construction wastes at project site shall be segregated separately. The
Contractor and Subcontractor HSE Personnel shall maintain a waste inventory to
keep a record of the types and quantities of waste present at the job sites.
7.3.3
At any case theresin, hardener, solvent or any other
chemical shall not be drained onto the ground or buried. Chemicals spills to
the ground are to be remediated immediately. Thecontaminated soil along with
the chemical spill waste shall be collected in a bin or container in the
working area.
7.3.4
Waste materials shall be segregated at source by
providing coloured and marked (with universal symbol and signage in Arabic and
English) bins / containers the waste as follows:
7.3.4.1
Red :
Hazardous Wastes
7.3.4.2
Green : Refuse
7.3.4.3
Brown : Plastics
7.3.4.4
Blue : Glass
7.3.5
Sufficient quantities of bins / containers shall be
placed for each type of waste at waste collections points, depending on the
variety and quality of the wastes expected
from the location. There shall be effective and timely replacement of the segregated bins and containers to the waste
disposal area. Each bin / container shall
have a tight sealing lid.
7.3.6 All waste
generated on site shall be removed promptly to the central waste collection area, which shall be
established by the Contractor and approved by LUBEREF.
8.0
MATERIALS
8.1
Provision
All RTR(Fiberglass) materials and components such as
pipe, fittings, spool assemblies, lamination kits, resin catalyst and chemicals
shall be supplied by Contractor in accordance with the specification AWWA C950,
SAES-L-610, SAES-L-105 and manufacturer's recommendation.
8.2 Handling
8.2.1
Upon receipt of the RTR (Fiberglass) and other
non-metallic materials shall be subjected to visual inspection for any damage
during the transport and if there is any defect found, the same should be
reported to the Contractor.
8.2.2
If load has shifted or indicates rough treatment,
carefully inspection each pipe section for damage. Generally an exterior
inspection will be sufficient to detect any damage.
8.2.3
Working tools, scaffolding or any other objects shall
be prevented from striking or being dropped on or inside the pipe, fittings or
spool assemblies.
8.2.4
Pipes, fittings and spool assemblies shall be lifted
and positioned using proper rigging and hoisting practices. Lifting sling angle
shall not be more than 45° from vertical.
8.2.5
Lifting sling that will be in direct contact with the
pipe, spool assemblies and components shall be made from woven nylon or canvass
and shall have minimum of 150 mm (6 inch) wide.
8.2.6
Lifting sling shall not be attached, or allowed to
come into contact with nozzles, flanges, gussets or other fittings.
8.2.7
Pipes, fittings and spool assemblies shall be
supported for storage on level ground in the original shipping or equivalent.
8.2.8
Loose RTR (Fiberglass) pipe shall be handled by hand
or, if the pipe is too heavy, used nylon or cotton spreader slings.
8.2.9
Secure pipes and spool assemblies to prevent damage
from wind and other contaminants.
8.2.10
In the storage area of RTR (Fiberglass)
pipes and its components shall be visibly marked and barricaded to avoid
accidents. Safety precautions must be ensured.
8.3 Storage
8.3.1
It is generally advantageous to store pipes on flat
timber to facilitate placing and removal of lifting slings around the pipe.
8.3.2
Racks shall conform to factory shipping packages for
each pipe size. Shelves shall be provided for continuous support of the pipe.
8.3.3
If loose pipes are stacked on each other, the stack
height shall not exceed 1.5m adequate side support shall be provided to prevent
slipping or rolling.
8.3.4
If pipe is stored on racks or bearing boards, the
support shall be at least 75mm wide. Supports shall be spaced on 3 meter
centers maximum with the first supports 1.5 meter from the end of the pipe.
8.3.5
All supporting surfaces shall be free of sharp
objects.
8.3.6
Thermoplastic pipe tubing and fittings shall be stored under cover to
avoid unnecessary dirt accumulation and long term exposure to sun light.
8.3.7
Thermoplastic pipe and fitting shall be stored with
continuous support in straight, uncrossed bundles. Care should be taken in
handling to ensure that unnecessary abuse such as abrasion on concrete or
crushing is avoided.
8.3.8
Thermoplastic fittings shall be stored in their
original containers. Fittings shall be stored in a building or under a cover
that allows free air circulation.
8.3.9
Solvent cement and primer for thermoplastic piping
shall be stored in an air-conditioned building with a maximum temperature of
26.7°C.
8.3.10
Gaskets, “O”-rings and locking keys shall be stored
flat on racks below 38°Cand out of direct sunlight.
8.3.11
Adhesive for RTR (Fiberglass) piping shall be stored
in an enclosure where temperature does not exceed 38°C.
8.3.12
Pipes and fittings shall properly protect from impact,
especially on their ends. They shall not throw, bumped, hit or dragged and
pushed over abrasive surfaces.
8.3.13
If the pipes are stacked in layers, inverted cradles
or its equivalent shall be used on top of the pipe and the support cradles of
various layers shall be aligned vertically. Stacking shall follow the
requirements of pipe manufacturer.
8.3.14
Adhesive and solvent cement containers shall be
tightly closed when not in use and shall be returned to the storage facilities
to minimize exposure to excessive temperatures.
8.3.15
Solvent cement and primer for RTR (Fiberglass) piping
shall not be stored if no expiration date is clearly marked on the container.
8.3.16
Lamination joint kits, resin, catalyst and chemicals
shall be stored in the original packing in a dry place and within temperature
and humidity limits recommended by material manufacturer.(Catalyst shall be
stored in a cool maintained room(20-25C). Resin & Styrene shall be stored
in a shelter/ stored area.)
8.3.17
Lamination joint kit shall be protected from dust,
fog, water and other contaminants.
Materials that are damaged, expired, wetand in non-conformance with the
material manufacturer and project standards shall not be used.
8.3.18
Resin, catalyst
and chemicals shall be stored in the area approved by the safety department. It
must be stored outside the working area and firefighting equipment shall be
available within its vicinity. "NO SMOKING" or "FLAMABLE"
signboards shall be visibly placed in that area.
8.3.19
RTR (Fiberglass) pipes shall have continuous support
along its entire length when being transported by either truck or pipe trailer.
All sharp edges that could touch the pipe shall be padded with sacks, rubber
strips, or other suitable material.
8.3.20
Bearing boards at least 75 mm wide shall be used to protect
RTR (Fiberglass) pipe from sharp objects on the truck beds. Rubber tire
sections or other suitable material shall be attached to the bearing boards.
Support spacing and height limits shall follow Para 10.3.1 to Para 10.3.5. Except that the end of support
shall not be 1m
from the
ends of the pipe.
8.3.21
RTR (Fiberglass) pipe shall be secured with cotton or
nylon strap.
8.3.22 Solvent
cement primer and adhesive containers shall be protected from direct sunlight.
9.0
ASSEMBLY AND INSTALLATION
9.1
General
9.1.1
Checking drawings (IFC) as per latest revision.
9.1.2
Make sure that all RTR (Fiberglass)pipes, fittings and
spool assemblies are free from defects prior to installation.
9.1.3
All safety permits required are obtained and
precaution must be established.
9.1.4
The pipe installation shall be in the sequence of CW,
PCS, OWS, FW and DW lines respectively.
9.1.5
The RTR (Fiberglass) pipe shall be kept near and
parallel to the excavated trench within the minimum safe distance from the top
edge of it.
9.1.6
Initially dewatering of the trench shall be done by
the civil subcontractor, during installation of RTR (Fiberglass) pipes the
dewatering shall be done by the mechanical subcontractor if necessary.
9.1.7
Before installing the pipes in the trench, the
bedding's compaction and its testing shall be done.
9.1.8
Pipes shall be lifted by crane using 2 flexible nylon
web slings at equal space. The lifting space shall be minimum 150 mm wide.
9.1.9
The elevation of pipe bedding has to be check as per
IFC drawing prior to lying down of pipes.
9.1.10
Survey instrument shall be used to make sure that the
laid pipes do not deviate from the established line. Pipe elevation shall be
maintained in accordance to IFC plan and isometric drawings.
9.1.11
All reference points have to be certified and
established for verification.
9.1.12
Pipe line shall be in a straight line both horizontal
and perpendicular plane.
9.1.13
Pipes shall properly align and fit up as perfectly as
possible. Best effort shall exert to eliminate the lateral offset. The maximum
permissible lateral offset is 10 mm.
9.1.14
The curve of each pipe shall be within 10 mm of its
theoretical position for line and level at each end.
9.1.15
Installation of scaffolding if necessary shall be done
as an access to the joint preparation for fit up and external lamination, or
for adhesive bonding of big diameter pipe.
9.1.16
Request and notice for closing of
roads if necessary during RTR (Fiberglass) materials lay down and piping
installation shall be done by subcontractor and approved by contractor safety
department. The routing plan shall be made by the contractor safety department.
9.2 Pipe
Laying Preparation and Installation
9.2.1
Ensure that all relevant documents
and material have been approved by LUBEREF prior to commencement of the work,
and that the latest revisions of IFC drawings, specifications including
approved procedure are disseminated to concerned personnel who carry out the
work.
9.2.2
Prior to commencing the installation
work, any damage such as exterior scratch mark, impact mark, bulges,
projections, blisters, indentation, delamination and/or abrupt curvature of pipes, coupling and
flanges shall be inspected visually.
9.2.3
Internal inspection shall also be
performed to check for damage of inside surface, such as scratch or impact
marks, and to verify drainage of water and removal of foreign materials.
9.2.4
Qualification for RTR (Fiberglass)
piping installation personnel shall be trained and qualified in accordance with RTR (Fiberglass) manufacturer's
requirements.
9.2.5
All RTR (Fiberglass) fittings and
spool assemblies shall be transferred to the working area nearer to the trench.
9.2.6
All RTR (Fiberglass) materials shall
be handled in accordance with the manufacturer's recommendation.
9.2.7
Storage of RTR (Fiberglass) materials
near the working area shall also be
considered to avoid being contacted with contaminants.
9.2.8
Damage components shall be marked and
segregated and should not be brought in the vicinity of the working area.
9.2.9
Trench excavation and bedding details
and procedure shall be in accordance withSAES-S-070 Para21 as follows.
9.2.9.1
The depth of the trench shall be dug
deep enough to provide a minimum round cover above the top of the pipe, as required
in Table 2 ofthis procedure, and a ground bedof at least 150mm in depth below
the bottom of the pipe. The width of the trench should be wide enough to allow
room for jointing, but in any case not less than shown in Table 1 of this
procedure. Piping under road crossing shall be in accordance with the Project
ProcedureSAES- L-460, Para 12.
9.2.9.2
The trench bottom shall be
continuous, smooth, free of rocks, and to the line and grade shown on the installation
drawings. The pipe shall have essentially continuous support and not rest on
the joint. For RTR
(Fiberglass) piping, the trench
contour shall not cause the joint angular deflection or the pipe bending radius
to exceed the manufacture's limit.
9.2.9.3
The minimum trench width from the
bottom to 300mm above the top of the pipe shall be as shown in Table 1.
TYPE OF PIPE
|
NOMINAL PIPE SIZE (mm)
|
MIN. WIDTH OF TRENCH (mm)
|
RTR (Fiberglass)
|
250 and under
|
O.D. + 300
|
RTR (Fiberglass)
|
300-600
|
2 x O.D.
|
RTR (Fiberglass)
|
Over 600
|
O.D. + 600
|
TABLE 1- TRENCH WIDTH
TYPE OF PIPE
|
NOMINAL PIPE SIZE AND
SERVICE
|
MINIMUM COVER
(mm)
|
RTR (Fiberglass)
|
Under 150mm size
|
600
|
RTR (Fiberglass)
|
150mm and larger
|
900
|
Thermoplastic
(CPVC)
|
Pressure pipe
above 100mm
|
900
|
TABLE – MINIMUM COVER OVER THE TOP OF PIPE
9.3 Installation
Activities
9.3.1
After lying the spools, place the sandbags beside of
pipes to support from any movement.
9.3.2
These spool assemblies shall be the reference points
in the installation of the underground cooling water supply and return lines.
9.3.3
After completing the laying of the initial spools, a
dimensional check on the trench shall be done to ensure that the pipe length's
measurement is correct including its fitting's location and that no
interference from the pipe rack foundation existed.
9.3.4
After the dimensional checking and corrections was
made, (if there is any) excavation on the pipe's joint portion shall be made
prior to pipe laying works.
9.3.5
This excavated portion on the trench will be the
working area of the laminators during jointing of big diameter pipe lamination
or adhesive-bonding activity.
9.3.6
A 50-ton crane shall be used in these pipe laying
activities in the working place. Therefore the pipes can be lowered only on the
vacant or open area.
9.3.7
In this situation, rollers or carts shall be used to
facilitate the laying down of the pipes in their respective locations.
9.3.8
Place the rollers or carts on the trench. Make sure
that the vertical centre of the pipe and the roller/cart is identical. After
checking the position of the rollers/carts, gently place the pipe on it.
9.3.9
Pull the pipe with the use of a chain block or lever
block until it reaches the location.
9.3.10
With the use of chain block attached to the steel
structure and to the nearest portion of pipe to be lifted, lift the affix
portion of the pipe to remove the roller/cart. Use inspected "A"
frame, if steel structure is not available.
10.0
ASSEMBLY INSTRUCTION AND PROCEDURE
10.1
Butt-and-Wrap Joint
10.1.1 Ensure that
the gap between the two pipes to be laminated is within the allowable limit shown
below:
10.1.1.1
2mm for diameter up to 300mm
10.1.1.2
3mm for diameter above 300 mm to
600mm
10.1.1.3
10mm for diameter above 600mm
10.1.2
Grinding the pipe surfaces (internal &external).
10.1.3
Prior to start of lamination work, check the temperature
of materials and laminate surface. Temperature shall be within the range of
12°C to 38°C and minimum of 12°C above dew point.
10.1.4 Thoroughly clean the pipe ends
that to be jointed.
10.1.5
Mark the plies width to be applied on the pipe joint
(total bond width). This marked area to be grinded. Use rotary disc
grinder/sander to grind the area. This procedure shall remove the shiny surface
of pipe.
10.1.6
An internal lamination shall include groove at the
lamination ends. This grooving shall absorb the laminating ply edges into it.
These grooving facilitate the product flow without reducing the flow momentum.
10.1.7
The grinding procedure shall be repeated if the
prepared surface area is contaminated prior to start of lamination work. Wipe
the grind areas with clean solvent/cloth to remove the collected dust and any
surface moisture. The solvent must be allowed to evaporate completely.
10.1.8
Align the pipe section as perfectly as possible. In
case the gap cannot be avoided it shall be filled with "glass putty"
cabosil powder mixed with catalyzed resin as per manufacturer's recommendation.
The gap shall be no exceeding 10mm in width all around.
10.1.9
For the diameter 600mm and above, internal lamination
is also required.
10.1.10
Each supplied joint kit contains the required number
of plies chopped mat and woven roving
according to the manufacturer's specification.
10.1.11
Each layer consists of one or more sections to make up
the complete around the pipe
circumference. These sections are pre-cut to a specific length that can be handled easily. Re-check the applicable
layers configuration from the process sheet provided.
10.1.12
The total number of plies is divided into layers with
the same number of plies and that
each layer begins and ends with chopped mat plies.
10.1.13
Prepare enough resin for approximately 20 to 30
minutes gel time by adding proper amount of catalyst in the one gallon half cut
plastic pot. Mixed the catalyzed resin through mixing tongue to make it
homogeneous.
10.1.14
Cover the table with heavy craft paper and spread a
thin layer of mixed resin on the paper
over an area large enough to include the largest piece of chopped mat. Lay a
piece of chopped mat on the applied layer of resin on the table.
10.1.15
Dip the paint woolly roller into the resin (not very
deeply) and apply it in the layer mat
smoothly all over the surface to wet-out well. Lay out a piece of woven roving
over the wet mat and apply the paint roller over to it completewet out. (It is
noted that the mat plies are always longer than woven roving so short of length
in woven roving shall be distributed
equally over the mat.)
10.1.16
Continue building up by alternate mat and roving plies
& wetting out each one before
applying the next one. Too many plies may not allow dissipation when the resin
is under curing process and could cause blistering.
10.1.17
Apply a coating of catalyzed resin directly on the
pipe joint ends through the same paint roller used for wet-out.
10.1.18
Lifts the resin impregnated plies through mixing stick
from any corner & place them at
the pipe joint which is already grinded and well cleaned. Make sure that the
wet plies are placed centred&
equally distributed on the pipe ends & the first chopped strand mat lies directly on the pipe.
10.1.19
Roll out the paint roller over the plies to release
big air cavities and any excessive resin.
Use steel grooved roller slightly pressed to remove out the air bubbles. The
angle of groove roller shall be change time to time in order to remove the air
bubbles in all directions. Make sure all bubbles have been taken out prior to
start the plies to become hard.
10.1.20
Stop rolling as soon as the resin starts gel. Continue
this procedure until all the sections
of the first layer been applied. Make sure that each section overlaps with the
other by minimum 5cm.
10.1.21
Allow this
lay-up round to cure & cool (until it is comfortable to touch with the barehands)
prior to apply of another plies.
10.1.22
Complete the supplied number of plies application with
the same procedure.
10.1.23
There could be another alternative to prepare the
lay-up in place of on-work below:
10.1.23.1 It is to wet out the plies
directly on the pipe joint itself one by one.
10.1.23.2 Spread a thin layer of resin
directly on the pipe joint surface.
10.1.23.3 Pleased the chopped mat layer
on the pipe joint with equal length both sides.
10.1.23.4 Wet out the layer through
point roller.
10.1.23.5 Continue in the same manner as
described earlier.
10.1.23.6 When working on the top section internally, a faster
curing time is advisable. Increase slight amount of catalyst with a limit so
that the bubble out process may end before gelling start.
10.1.24
For internal lamination, the edges
shall be penetrated into the previously made grooves at both side of the lay-up
width to maintain smooth flow of the product during operation.
10.1.25
Approved Bonding Procedure
Specification (BPS) shall be provided by QC section asper manufacturer qualification
record.Manufacturer's standard procedure for all type of joints.
10.2
Cautions
10.2.1
Do not use resin if it is near gel.
10.2.2
Never allow solvent to run on uncured
resin.
10.2.3 Each section of the pipe shall
be laminated (at least partially) before another
length of pipe is added. This is to avoid excessive deformation internally with laminated
materials.
10.2.4 Provide sunshade to lower the
ambient temperature in the joint area. If the
ambient temperature is still above the required range, the work shall be temporarily stopped.
10.2.5 Lamination works shall not be
allowed during sand storms and high percent
of humidity.
10.2.6 Resin shall be tested for gel
time and peak exothermic temperature to determine
and establish its curing characteristics.
10.2.7 Abraded area that is not
covered with the overlay shall be coated with waxed
resin after completion of joint overlays.
10.2.8 In case the lay-up joint is
not completed by the end of the day, or the lamination
process will be continued after several hours, following shall be taken.
1.
The shiny surface of the lay-up by minor grinding.
2.
Wipe the grinded area with clean
solvent to remove the collected dust&allow the solvent to evaporate.
3.
If top layer of mat removed through
grinding, an addition piece of mat shall be placed.
4.
Quality Control Inspection: The
applied lamination standard shall be verified through QC Inspection
10.3
Butt-and-Wrap Joint
10.3.1 Dampness: The lay-up
joints must be
conducted in dry
Conditions.
Any moisture/dampness on the
pipe surface or on the lay-up table may lead to a poor bonding of joints.
Therefore, precautions must be taken during humid/wet weather. A portable
shelter that will cover the pipe jointing area solves the purpose. A portable
heat source (high volt bulb) may also require if weather is continuously humid
or wet.
10.3.2Hot Weather: The gel time decreases as the atmospheric temperature
increases and the gel time becomes very short. It is recommended to maintain
the shelter over the pipe with adequate ventilation.
10.3.3 Cold Weather:lf the temperature at site is too
cold which may increase the curing time of the applied layers, it is
recommended to use the heated shelter. High voltage lamp/hot blowers could be
used in the surrounding area, but not directly on the work place.
10.4 Taper/Taper Adhesive Bonded Joint
10.4.1
Only Qualified pipe assemblers shall carry out the
work. Bonders shall be certified by the manufacturer, installation of piping as
per approved bonding procedurespecification.
10.4.2
Contaminated pipe surfaces shall be clean prior to machining
the pipe ends.
10.4.3
When holding pipe in a vice, use rubber padding or
similar material to protect it from damages. Scribe the pipe using a pipe
fitter's wrap-around.
10.4.4
Use a hacksaw or an abrasive wheel to cut the pipes.
10.4.5
The pipes ends squareness shall remain within the
tolerance. These tolerances can be checked by using the arbor of the pipe
shaver which is inserted into the pipe base flush with the cut end of the pipe.
10.4.6
The pipe shall be adequately supported to prevent
damage before fitting the arbor inside the pipe. Refer Figure-3. Fix the arbor
to the inside of the pipe by turning the central tensioning bolt clockwise.
10.4.7
Adjust the shaver to the required pipe size. Be sure
to use the correct Tapper angle.
(Various types of shavers are available for shaving the pipe ends, subject to
the pipe size. Use the correct one.)
10.4.8
Shave the taper spigot. Maximum shaving depth / feed
is 2mm. Repeat the shaving action until the required spigot diameter / spigot
nose thickness is achieved.
10.4.9
Due to possible tolerance spreading the manufacturer
recommends to use a nominal sized dummy bell end. This may avoid too long or
too short assembly lengths. If the insertion depth in the dummy is too small,
the spigot end to be shaved and to be adjusted.
10.4.10 Preparation of the surfaces to
be bonded shall be within two (2) hours from assembly and if it lapses, the
surface should be re-sanded.
10.4.11 The surface to be sanded shall
be clean and dry prior to sanding.
10.4.12 Use 10-12 mm drill motor,
1700-2000 rpm and flapper type sander with 40-60 grit aluminum oxides abrasive.
10.4.13 The surface must have a dull,
fresh finish and not a polished look after sanding.
10.4.14 The edges of the spigot shall
slightly abrade.
10.4.15 Insertion depth of the spigot
in the bell or coupling shall be marked on the pipe.
10.4.16 This marked shall be made to
ensure proper alignment and full insertion of the bell and spigot.
10.4.17 Make sure that before mixing
the adhesive, all preparations have been done and all parts to be bonded are
ready for assembly, because mixed adhesive has a limited pot life subject to
the ambient temperature.
10.4.18 Adhesive components shall be
mixed until the mixture has a uniform colour and consistency.
10.4.19 Do not use adhesive mixture
that begins to produce heat or lumps or gelled masses.
10.4.20 Adhesive shall not extrude
into the bore of the pipe to the extent that a significant blockage is created.
Extruded adhesive shall not exceed the lesser of 10mm or 5% of the pipe
diameter.
10.4.21 If adhesive is not within 21
°C and 38°C range, which will need to warm or
cool it before mixing. The adhesive will not mix and spread well below 21°Cand
will set up too fast above 38°C.
10.4.22 Bonding surface temperature
shall be kept between 15°C and 40°C. Use shield or cover if the temperature is
above 40°C.
10.4.23 All surfaces to be bonded
(sanded area) must be completely covered with adhesive, approximately 0.5mm in
the bell and 1mm on the spigot. Sufficient adhesive has to be applied on the
cylindrical end of the spigot that will be covered by the bell.
10.4.24 When inserting the spigot in
the bell pay attention to the marks and position and keep the joint together.
Letting the spigot slip back or turning the spigot after complete insertion may
result in a bad joint.
10.4.25 The bonded joint shall not be
moved, vibrated or otherwise disturbed during curing time. Install the bond
clamps on both components keeping sufficient space for the pullers (or winches)
when pulling the joint together.
10.4.26 Pipe shall be assembled using
mechanical pullers; care shall be taken to prevent the connections from being
damaged during this operation. Theapplied tension using mechanical pullers
shall be equal at both sides and in sequence to have proper alignment.
10.4.27 During the application of
tension, it shall be ensured that there shall be no metal contacts with the RTR
(Fiberglass) Pipe. Where required, rubber padding shall be provided as shown in
Figure-2. It shall be necessary to set a bridge (piece of wood between puller
cables and pipe outside) to simplify placing of the heating blanket.
10.4.28 After completion of bonding,
the joint is allowed for ambient curing. Heat assisted curing is required for
epoxy adhesive bonded connections, which shall be performed immediately after
the adhesive mix is hardened. For the purpose of curing, the heating blanket
shall be used.
10.4.29 Open end pipes shall be closed
during curing to avoid of cooling down of inside surface of joint by draught.
Also wind breaker shall be used when there is high velocity wind.
10.4.30 Only the required size of the
heating blanket shall be used in the curing of the adhesive. Do not remove the
pullers until the adhesive has fully cured.
10.4.31 If the temperature is below
10°C or the wind has a cooling effect, insulation material shall cover the
heating blanket.
10.4.32 Insulation material should
overlap the sides of the blanket with at least 100mm and should match to the
pipe.
10.4.33 Functioning of the heating
blanket shall be checked regularly. Temperature shall always meet the
manufacturer's recommendation.
10.4.34 Time (start and end) shall be
marked on the pipe to ensure complete curing.
10.4.35 During curing time, the joint shall
not be moved, vibrated or otherwise disturbed.
10.4.36 Ends of pipe shall be covered
completely to prevent ingress of foreign debris and contaminants.
10.4.37 In special cases, wherever the
shaving and bonding a joint is highly difficult, there Butt-and-Wrap lamination
type joint shall be considered as per the manufacturer standard.
ReplyDeleteIt is a great post for every blog and for me. Obviously I want to say that this is very important post for learn. Thanks....
FRP Products Manufacturers in Chennai
Very Nice information for gel based cable jointing kits for the electrical cable joints get long life.
ReplyDelete