Wednesday 13 June 2018

ARAMCO SCAFFOLD CERTIFICATION TEST MODEL QUESTIONS/ ANSWERS

1 After installing one pair of post which component of scaffold should be install
 A/    Runer         B/   Brace    C/  Ties   D/    Guys A
2 Prior to install scaffold a scaffold supervisor must look 
 A/  Height of scaffold  B/ Width of scaffold  C/ Length of scaffold D/ Load rating Scf
3 Who will install red tag 
  A/ Scaffold supervisor  B/ Scaffold inspector C/ Permit receiver D/ Permit issuer A
4 What type of rope used to lift scaffold material ( drawing )
A/  Rolling hitch B/ Reaf knot   C/ Timber hitch   D/ Drum hitch 
5 Scaffold plan required if scaffold height increase more then
             mtr
 A/ 4.0 mtr    B/ 38.0 mtr    C/  3.0 mtr    D/ 12.2 mtr  D
6 If yellow tag installed on the scaffold what is to be worn
 A/ Safety belt   B/ Life lice   C/  Full body harness anchored  D/ Full body harness C
7 Ladder 1st rung height from the ground 
 A/ 600mm/ 2ft    B/ 300mm/1ft    C/ 1200mm/ 4ft     D/ 1800mm / 6ft  A
8 Scaffold plat form slope
 A/ 1;3    B / 1;1    C / 1;4    D / 1;2  C
9 Tread depth of stairway at least
A / 220mm     B / 150mm     C / 300mm       D / 400mm  A
10 Mediume duty scaffold underhung maximum longitudinal post spacing 
 A / 1.2     B / 1.8      C / 1.5       D / 3.2   C
11 OSHA 1926.450 Tank builders bracket scaffold space atleast  
 A / 1.5    B / 3.2     C / 1.2    D / 2.4  B
12  Check coupler shall be install 
 A/ Bellow the runer  B/ Bellow the transom C/On the beam D/Top&Bottom H/ tube  D
13 If yellow tag is install Fullbody harness shall be anchored to 
 A /Conduit     B / Steel stucture        C / Runner          D / Transom  B
14 Above the platform headroom height atleast 
 A / 2.0 M       B / 1.5M         C / 2.5M         D / 1.8M  D
15 An installed power line 60kv scaffold clearance atleast 
 A / 4.0mtr      B / 1.0mtr       C / 3.0mtr      D / 1.2mtr  A
16 Bracket scaffold plank shall be overlaped 
  Plank shall be overlape in one direction only and minimum overlape 230mm ( 9'' )
17 Medimum duty mobile scaffold caster wheel dia 
 A / 5''     B / 7''      C /4''       D /  3''   B
18  Mobile tower scaffold caster wheel must have 
 A / Pin       B / Base plat       C / Wheel lock       D / Screw jack  C
19  Landing platform wide atleast 
 A /27''      B / 20''       C / 15''      D / 21''  A
20 1!/2 thick plank span length increase 1.5 mtr how many board bearer atleast 
 A / Two     B / Foure     C / One      D / Three  C
21 A light duty scaffold has 8 planked level howmany working platform shall be consider
 A / One      B / Zero    C / Two       D / Three 
22  Base plat shall be used all place except 
 A /Mobile scaffold  B/ Light duty scaffold   C/ Tower scaffold  D/ Heavy duty scaffold
23 Soft ground required
 A / Sill board    B / Screw jack    C / Base plat      D / Level the ground  A
24 All scaffold tubing must have marked 
 A / Bs-1139     B / 10219       C / ASTM-500        D / ASTM-123  D
25 Load rating of fabricated tubeler scaffold platform 
 A / Light duty     B / Special duty     C / Medium duty    D /All purpus  A
26 SGB type material birdcage scaffold transverse side 1.8mtr longitudinal direction must
 A/ 1.5     B / 1.8      C / 2.5      D / 2.4    C
27 When pair of post in position which componet install first 
 A / Outrigger      B / Raker      C / Tie       D / Ledger  D
28 Duration of Reinspection of tag 
 A / 3 Weeks     B / 2 Weeks     C / 1 Weeks      D / 4 Weeks  B
29 What kind of rope use lowering material during dismantle scaffold 
 A / Steel rope     B / Knock roll      C / Timber Hitch     D / Nilon rope  D
30 As per SSH Sole plat (Sill board) not required 
 A / Loose sand ground   B/ Concrete ground  C/ Asphalt ground    D/ Sand Surface  B
31 Where Use Base plate 
 A/ Concrete ground   B/ All over except mobile   C/ Asphalt ground   D/Sand surface B
32 What type of scaffold is consider as Special scaffold 
A / 120kg/m2    B / 290kg/m2       C / 240kg/m2          D / 175kg/m2    B
33 Which type of Scaffold required for piping Equipment work 
A / Light duty     B / Special duty        C / Medium duty          D / General  B
34 From which height guardrail system required when person protect from fall 
 A / 2.0mtr     B / 1.6mtr       C / 1.2mtr        D / 1.8mtr  D
35 Toprail of guardrail system is inbetween 
A/ 0.95mtr(38'')-1.15mtr(45'')           B/ 0.8mtr(32'')-0.9mtr(35'')
 C/ 1.0mtr(40'')- 1.20mtr(48'')           D/ 0.7mtr(28'')- 0.95mtr(38'') A
36 Distance from face of wall or steel stucture must not exceed 
A/ 360mm (14'')    B/ 250mm(10'')     C/ 300mm(12'')      d/ 230mm(9'')  A
37 Minimum clear Headroom for scaffolding platform 
 A/ 1.8mtr(6')    B/ 3.0mtr(10')      C/ 2.0mtr(6.6')       D/ 2.5mtr (8') A
38 Temprary stairways tread depths atleast 
 A/ 220mm(9'')    B/ 280mm (11'')    C/ 215mm (8'')      D/ 150mm(6'')  A
39 The distance between bottom rung of ladder to base at least 
A/ 600mm(2ft)    b/ 1200mm(4ft)    C/ 300mm(1ft)    d/ 1500mm(5ft) 
40 What type of stamps to be applied on the scaffold tubes 
 A/ BS - 1139     B/ ASTM - 123     C/ BS- 2482       D/ ASTM - 125  A
41 What is required end of planks more then 25(1'') splited
 A/ Baded                 B/ no banding                 C/ Nailed              C/ Tie with wire  A
42 All type connection shall be made by
A/ Double coupler        B/ Putlog coupler      C/ Siwval coupler      D/ putlog&siwval A
43 Tie must connected with always 
A/ Close node point  B/ With outrigger   C/ Bracing    D/ With min 2 ledgers or posts D
44 Bracing connection made 
degree
A/ 35 dg to 55dg B/ 45dg to 55dg        C/ 30dg to40 dg D/ 40dg to 45 dg  A
45 The slope of scaffolding platform not exceed
A/ 1 vertical to 4 horizontal         B/ 4 horizontal to 1 vertical A
C/ 2 vertical to 1 horizontal  D/ 3 horizontal to 2 vertical 
46 Wate is the procedure dismantle scaffold 
A/ Top runner     B/ Lift by lift         C/ Tie & Transom         D/ Any where  B
47 What is the minimum distance from scaffold to 60 kv power line 
A/ 3 mtr        B/ 3.5 mtr       C/ 4 mtr          D/ 4.5 mtr  C
48 What is the minimum distance of runner joint to the post 
A/ 300 mm        B/ 200 mm         C/ 280 mm           D/ 350 mm
49 Unless Otherwise specified in manufactured  instructions of system scaffold braced 
full height of each 
A/ 10 mtr(33')      B/ 15 mtr(45')          C/ 8 mtr(8')          D/ 6 mtr (21') A
50 Distance from base to foot tie must be 
160 mm(6'') min     B/ 200 mm(8'') min     C/ 160 mm(6'') max   D/ 250 mm(10'') max  A
51 When bearer& runner joints must be far from the post maximum 
A/ 12'' (300mm)    B/ 16''(400mm)        C/ 6''(150mm)        D/ 18''(450mm) A
52 Scaffolding with one working platform&Eight additional PLF which type of scaffold it is
A/ Heavy duty        B/ medium duty      C/ Light duty       D/ Special duty  C
53 SGB Cuplock type Birdcage scaffold transom side 1.8mtr what is the longitudinal side
A/ 2.5 mtr         B/ 1.8 mtr        C/ 1.2 mtr        D/ 1.0 mtr  A
54 Heigher then which height of scaffold reviewed by Loss Prevention
A/ 6.0 mtr (21ft) B/ 38 mtr(133ft)        C/ 12.2 mtr(40ft)           D/ 10 mtr(30ft) B
55 Tube&coupler Medium duty scaffold transverse post spacing 1.2 m what is longitudinal
A/ 1.8 mtr      B/ 2.4 mtr       C/ 1.2 mtr        D/ 2.0 mtr  A
56 Medium duty Mobile scaffold Caster wheel dia at least
A/ 120 mm (5'')        B/ 170 mm (7'')         B
57 What device to install on mobile scaffold caster wheel 
A/ Wheel lock       B/ Screw jack         C/ jack plate          D/ Base plate  A
58 50 mm thick OSHA certified planks used on tank bracket scaffold what is the 
circumferential distance of bracket strap centre 
A/ 1.5 mtr       B/ 3.2 mtr        C/ 2.4 mtr          D/ 1.8 mtr  C
59 What is the maximum load rating of fabricated tubler frame scaffold 
A/ 120 kg/m2      B/ 170kg/m2           C/ 240kg/m2          D/ 290kg/m2  A
60 Bracket scaffold planks overlap minimum
A/ In one direction with minimun overlap 230 mm (9'' )
B/ In both direction with minimun overlap 230 mm (9'' ) 
C/ in both direction with minimun overlap 300 mm (12'') 
D/ in one direction with minimum overlap 300mm (12'' ) A
61 Check coupler shall be installed 
A/ Top of hunger tube&Bottom of Trapaze tube 
 B/ Under of hunger tube & Top of Trapaze tube 
C/ Under&top of the Beam A
62 What is the height of first platform in system scaffold 
 A/ 1.5 mtr       B/ 2.0 mtr         C/ 1.8 mtr         D/ 2.5 mtr  B
63 Scaffolding landing &Walkway shall be at least 
A/ 675 mm(27'')3 planks     B/ 600 mm(24'')     C/ 760 mm(30'')      D/ 1200 mm(47'') A
64 Under hung scaffold longitudinal side hanger tube spacing more then 1.5 mtr atleast..
A/ one board bearer   B/ 3 board bearer      C/ 2 board bearer      D / not required  C
65 Yellow tag is applied what type of PPE will worn
A/Full body harness&anchored B/ Life line   C/ Safety belt&anchored    D/Safety belt  A 
66 Load required for safw anchore point at least
A/ 2400 kg(5291lbs)    B/ 2000kg(4409lbs)   C/ 2260kg(5000lbs)   D/ 2600kg(5732lbs A
67 What is the purpose of use bracing on scaffold  
A/For rigidity of scaffold B/For inspection C/For looking good  D/For contractor Scaffold / A
68 Where are use plan bracing
A/ Tower &mobile scaffold     B/ Long scaffold     C/ Run scaffold     D/ Any where  A
69 Which type of scaffold used caster ?
A/ Tower scaffold      B/ Mobile scaffold     C/ System scaffold      D/ Any scaffold  B
70 Which type of lanyards suitable to use for scaffold 
A/ Locking type snaphooks     B/ D ring type    C/ Only one lock type    D/ Any type  A
71 What is the load rating for light duty scaffold 
A/ 240kg/m2(2.4kn/m2)  B/ 120kg/m2(1.2kn/m2)   C/250kg/m2(2.5kn/m2)  D/270kg/m2  B
72 What type of scaffold for abrasive blasting and cleaning 
A/ Light duty       B/ Special duty       C/ medium duty        D/ Any type scaffold  C
73 What is the purpose of special duty scaffold 
A/ To load greater then 240kg/m2   B/Any load     C/ To load less then 240kg/m2  A
74 Where install ledger on the scaffold 
A/ Lenth side    B/ Width side      C/ For bracing          D/ Any where  A
75 What is the purpose of using screw jack on scaffold 
A/ Compesate variation of ground   B/ For load rating      C/ For scaffold stability A
76 Cantlivered more then 3.0 mtr out side the stucture what type of scaffold 
A/ Medium duty     B/ Light duty      C/ Special duty      D/ None of above  C
77 Where use spigot 
A/ System scaffold    B/ Tower scaffold     C/ Mobile scaffold     D/ Any type scaffold  A
78 What is the length of trapaze tube 
A/ 450mm-600mm    B/ 500mm-700mm      C/ 200mm-400mm     D/ 150mm-300mm A
79 Guard rail system shall be able to with stand with out failure a force at least 
A/ 80kg (200pounds)    B/ 100kg(220pounds)     C/ 110kg(242pounds)     D/ 90kg D
80 What is the length of lanyards 
A/ 6 Feet(1.8mtr)        B/ 6.5Feet(2.0mtr)     C/ 8Feet(2.4mtr)       D/ 10Feet(3.0mtr) A
81 Why use snaphooks and D ring in personnel fall arrest systm 
A/ To prevent rool out       B/ To prevent body     C/ To hang       D/ Any purpose A
82 Horizontal &Vertical life lines made by 
A/ 10mm(3/8'') minimum diameter steel rope    B/ 11mm minimun diameter mild wire rope
C/12mm minimum diameter nylon rope  D/8mm minimun diameter polypropelene rope /A
83 Horizontal an unload sag at the center not greater then ?
A/ 300mm(12'')       B/ 250mm(10'')      C/ 200mm(8'')      D/ 400mm(16'') A
84 Toeboard minimum vertical height &thickness at least 
A/ 200mm(8'')-40mm(1.5'')    B/ 150mm(6'')-50mm(2'')     C/100mm(4'')-25mm(1'')
D/ 120mm(5'')-50mm(2'') C
85 Toeboard shall be capable load at least ?
A/ 23kg(50pounds)       B/ 25kg(55pounds)        C/ 30kg(66pounds)     D/ 20kg(44po)    A
86 Where tools material equipment are piled to a point heigher then the top eadge of toe
board what kind of protective screen to be used to prevent falling &protect striking worker  
A/ 18 guage wire with a maximum 13mm mesh 
B/ 20 guage wire with a maximum 20mm mesh 
C/ 24 guage wire with a maximum 16 mm mesh 
D/ 16 guage wire with a maximum 18 mm mesh  A
87 Asafe means of entry and exit shall be provided 
A/Above or bellow 2ft B/ Above or bellow 4ft  C Above or bellow 6ft D/Above or bellow3ft  A
88 What is width and lenth of temporary stairway landing 
A/ 560mm(22'') wide--760mm(30'')long        B/ 760mm(30'')wide--560mm(22'') long 
C/ 580mm(23'')wide--600mm(24'') long        C/ 630mm(25'')wide--760mm(30'') long  A
89 What is the vertical height of temporary stairway 
A/ 3.7mtr(12ft)   B/ 4 mtr(13ft)       C/ 4.5 mtr(14ft)        D/ 3.5 mtr (11.5ft) A
90 Temporary stairway shall be installed which degree ?
A/ 30- 50 degree     B/ 35- 40 degree      C/ 40- 50 degree       D/ 30- 40 degree  A
91 Temporary stairway riser height at least and maximum how much 
A/ 6''(150mm)-8''(215mm)               B/ 9''(220mm) 11''(280mm) 
C/ 4''( 100mm)-8'' (215mm)             D/ 8''(215mm)- 6'' (150mm)  A
92 Temporary stairway tread depth how much at least and maximum ?
A/ 9''-220mm 11''-280mm                       B/ 6''-150mm 8''-220mm
C/ 11''-280mm 8''-220mm                       D/ 8''-220mm 6''-150mm A
93 Temporary stairway handrail height shall be ?
A/ 940mm 37''-860mm 34''                      B/ 950mm 38'' -1150mm 45''
C/ 940mm 37'' -950mm 38''                     D/ 860mm 34'' -1150mm 45'' A
94 Temporary stairway minimum clearance in between hand rail& wall shall be ?
A/ 80mm      B/ 50mm       C/ 100mm      D/ 150mm A
95 Temporary ram and walk way slope not more then 
A/ 1 V 3 H     B/ 1 V 4 H      C/ 1 V 1 H       D/ 1 V 2 H  A
96 Post spacing is Depend on what 
A Length of Scaffolding 
B Width of Scaffolding
C Height of Scaffolding
D Load rating of Scaffolding D
97
 IF THE LADDER RUNG OR SIDE IS DAMAGE WHAT YOU HAVE TO DO

A       Repair&Used B REMOVED FROM S/ARAMCO
C CAN USE IF SAMALL DAMAGE D NONE OF ABOVE
98 WHAT IS THE DISTANCE BETWEEN THE LEDGER AND TRAPEZE TUBES
A 3 FT B 2 FT
C 1 FT D 4 FT
99 WHAT IS THE DISTANCE BETWEEN THE TOEBOARD AND WORKING SURFACE 
A 8 MM B 5 MM
C 6 MM D 4 MM
100 WHAT IS THE MIN HEIGHT OF TOP RAIL 
102 A 1.15 M (45 INCH) B 0.95 M(38 INCH)
C 0.80 M(32 INCH) D 0.90 M (36 INCH)
103 SUPERVISOR CAN SIGN LESS THEN WHAT HEIGHT 
A 8 M B 12.2 M
C 6 M D 10 M
104          WHO WILL INSTAL THE RED TAGE
A SCAFFOLD INSPECTOR B SCAFFOLD SUPERVISOR
C LPD D PERMIT RECIVER
105 MED/DUTY TUBE&COUPLER SCAFFOLD IF PLANKS LEVEL 2 HOW MANY WILL BE WORKING PLF
A 3 B 5
C 1 D 2
106  PLAN BRACING IN MOBILE&TOWER SCAFFOLD SHALL BE INSTALL
A AT THE BASE B AT THE TOP
C EVERY LIFT D BASE &TOPE AND EVERY THIRD LIFT
107 IN HANGER TUBE HOW MANY CLAMP FIX AT LEAST 
A 3 B 4
C 2 TO BE CHECK D 5
108 IF THE PLANKS THICKNESS IS 50 MM THE MAXIMUM CIRCUMFERENTIAL DISTANCE BETWEEN
A 3.2 M B 1.5 M
C 2.7 M D 2.4 M
109 RAMP OR WALKWAY SHALL HAVE CLEATTS IF THAT IS
A 1 V- 3 H B 1 V- 4 H
C 1 V-2 H D 1 V-1 H
110 RAMP OR WALKWAY ABOVE THE HORIZONTAL DEGREES 
A 35 D B 15 D
C 25 D D 20 D
111 TIES OR GUYS SHALL BE INSTALLED CLOSED TO THE HEIGHT OF
A 3 TIMES THE MINI BASE DIMENSION  B 2 TIMES
C 4 TIMES D NON ABOVE
112 IF THE GAPE BETWEEN PLANKS 25 MM WHAT TO DO( USE SSH)
A        COVER WITH PLANKS  B USE PLY WOOD
C NO NEED TO COVER D NON ABOVE
113 IF SCAFFOLDING IS NOT PASSED OR ALETRING WICH TYPE OF TAG WILL BE USED
A RED TAG B       GREEN TAG
C YELLOW TAG D              ANY TAG
114  FOR BIRDCAGE SCAFFOLDING INTERIOR LONGITUDINAL ZIG ZAG BRACING IN WICH DEGREES 
A 30-35 DG B 35-45 DG
C 35-55 D 30-50 DG
115 TEMPORARY RAMP AND WALK WAY SLOPE NOT MORE THEN
A ONE VERTICAL UNIT THREE HORIZANTAL UNITS A
B ONE VERTICAL UNIT FOUR HORIZANTAL UNITS
C ONE VERTICAL UNIT ONE HORIZANTAL UNIT
D ONE VERTICAL UNIT TWO HORIZANTAL UNITS
116 WHAT IS THE NECESSARY WHEN ROOF WORK BEAR THE LOAD
A
A REINFORCED B PROVIDE SCREWJACK
C PROVIDE SOLE BOARD
D PROVIDE BASE PLATE
117 DURING NIGHT TIME AN ELEVATED WORK AREA WHAT TYPE OF LIGHT TO BE USED
A ADEQUATE LIGHT ACCORDING TO SAES-P-123
B ADEQUATE LIGHT ACCORDING TO BS-1139
C ADEQUATE LIGHT ACCORDING TO BS-5973
ADEQUATE LIGHT ACCORDING TO EN-10219-2
118 WHAT IS THE SUSTAIED WINDS SPEED ALLOWED TO WORK AN ELEVATED WORK AREA A
A 65 KPH(40MPH) B 70 KPH(50MPH)
C 50 KPH(30MPH) D 80KPH(70MPH)
119 FLOATATION RING SHALL BE PROVIDED AT INTERVELS NOT MORE THEN  A
A 15 MTR(50 FT) B 20MTR(65 FT)
C 10 MTR (33 FT) D 5 MTR (15 FT)
120
WHAT PRECAUTION SHALL BE TAKEN TO PREVENT WORKERS TO HOT SURFACE
A
A BEARIER ,STAND BY MAN WARNING SIGN
B LADDER SIGN BOARD
C COVER THE PIPE
D ANY OF ABOVE

No comments: