METHOD STATEMENT FOR A/G HOT PIPING INSULATION WORK


TABLE OF CONTENTS



1.0             SCOPE………………………………………………………………………….3        
3.0             DEFINITION…..………………………………………………………………...3       
4.0             REFERENCES……………………………………………………………….…3      
5.0             RESPONSIBILITIES…………………………………………………………...4      
6.0             MATERIAL REQUISITION……………………….……………….………......4       
7.0             INSULATION JACKETTING PROCEDURE….…………………………….5
8.0             REMOVABLE VALVE & FLANGE BOX ...................................................7
9.0             RESOURCES…………………………………………………………….….....8
10.0          HSE REQUIREMENT……………………………………………………........8
11.0          QC REQUIREMENTS……………………………………….…………….…..9
12.0                ATTACHMENT.…………………………………………….………….…..11-12     




1.0         SCOPE
The Scope of work shall be summarized below: -

      I.        To supply and install of basic insulation, cladding and other ancillary’s/fastening material for hot, personnel protection, steam tracing & electrical tracing on Piping where ever insulation is specified as per project specification.

    II.        Sub-Contractor shall provide all scaffolding where required as per work scope suited insulation installation work.

2.0         PURPOSE
The purpose of this Method Statement is to define responsibility, requirements and the execution procedure for the hot insulation on Hot Piping for Refinery Expansion Project.

3.0         DEFINITION
         For the purpose of this specification, the following definitions shall apply:
         Client                :  
         Contractor        :   
                     Sub-Contractor:   
                     Project              :   .
         Location            :                


4.0         REFERENCE

   The materials of insulation shall generally meet the requirement of ASTM code, ARAMCO Standards, and PIP. Those not covered in ASTM code shall be conformed to applicable codes, and submitted for Client’s approval. Insulation Specification for Refinery Expansion Project,
   Document. No: LEP-O0-GS-0001

      I.        SAUDI ARAMCO ENGINEERING PROCEDURE(SAEP)
    II.        SAUDI ARAMCO ENGINEERING STANDARD (SAES)
   III.        SAUDI ARAMCO STANDARD DRAWINGS
  IV.        PROCESS INDUSTRY PRACTICES
   V.        ASTM SPECIFICATIONS
  VI.        DESIGN CODES & STANDARDS
 VII.        Insulation Details for Hot Piping – AA-036911-001- Rev 06.
 VII.    Insulation Details for Hot vessels – AA-036912-001- Rev 02.
5.0         RESPONSIBILTIES
   The responsibilities of the various personnel on the project site are as defined below:-

  1. Management has responsibilities to ensure that insulation work adheres to the recognized standard or code of practice with respect to the project specification, safety, quantity and other requirements.          
           
    II.        Site Manager shall be responsible to the Management and for the overall implementation of this method statement for all construction activities carried out.

  1. QC Operative/QC Inspector shall be responsible for all the inspection and testing works as per approved ITP (SATIP- Rev 5), the preparation of documents and for maintaining all record.


  1. Site Operatives/ supervisor shall be responsible for achieving the stage acceptance of the Inspection & Test Plan.
 
   V.        Applicator for direct work shall ensure that they perform the insulation application as per project specification and in accordance with project safety procedure.
  VI.        HSE/Safety Supervisor shall monitor regular safety checks and ensure that the work is carried out in accordance to project safety norms.

6.0         MATERIAL REQUISITION
It shall be the responsibility of the Supervisor to authorize the requisition of the materials required for the relevant items to be insulated using Material Request Issue Form which may consist of:

6.1 Insulation Material

Insulation Material Code as per LEP-OO-GS-0001 with properties meeting to SAEP & SAES.


6.2   Jacketing Material – All Insulation design.
Jacket Material Code as per LEP-OO-GS-0001 with properties meeting to SAEP & SAES


6.1         Ancillary/Fastening Materials:

6.1.1  Insulation fastening Material for hot Piping – SS304 - 1.6 mm thick Tie Wire for < 4’’Ø and interlayer at 250mm spacing.
6.1.2  Insulation fastening Material for hot Piping – SS304 as per A 167 Strap1/2 inch x 0.5mm thick for 4’’Ø to 34’’Ø and ¾ inch x 0.5mm for 36’’Ø and above  at 250mm spacing.
6.1.3  Jacketing fastening Material for hot Piping - SS304 as per A 167 Strap 1/2 inch x 0.5mm thick up to 34’’Ø  and ¾ inch x 0.5mm thick for 36’’Ø all metal jackets at 305mm spacing.
6.1.4  Screws shall be self drilling No.8 by ½ inch (13mm) stainless steel, with elastomeric washer. Screw head shall be hex, Phillips recessed round, round, hex-slotted or Pan type.
6.1.5  Metal sealant shall be RTV Silicone, aluminium or grey color, suitable for continuous service to 204° C and intermittent service to 260° C.
6.1.6  Insulation support on vertical Piping can be either a ring or expanded metal lath with support studs, Maximum support ring spacing shall be 5 meter for piping with temperature below 315°c and 3.65 meter above 315°c.



7.0   INSULATION & JACKETING PROCEDURE

7.1       Scope of work & Explanation of Procedure
   The total process consists of surface cleaning, fixing of insulation & cladding material and its securement. This procedure covers stage wise activities including quality control checks for insulation work.
  
7.2       Release Note
   All the areas prior to start of insulation will be officially released to Insulation Sub-contractor. No other activities shall be allowed in the area released for insulation without information to Insulation Sub-contractor. Proper release note has to be provided duly signed by the Contractor concerned engineer / authorized person. The release note receipt should be signed by KAEFER QC or Site-in Charge after physically confirming the readiness of area for insulation.

7.3         Application Of Insulation & Jacketing

7.3.1 General        
·         Insulation shall be applied per all applicable engineering specifications and standard insulation details.
·         It shall be the responsibility of the Supervisor to ensure the insulation and jacket materials are applied correctly including the correct order of layering, and with correct securement / fastening and sealants.
·         Ensure the Piping mechanical work completed prior to release for insulation by the Contractor’s Representative has all previous work including hydrostatic or other testing and touch of painting completed and is in a fit state to insulate.
·         Piping surface shall be clean, dry and the surrounding area is free of obstacles and debris as per specification.
·         When weep or aeration holes in jacket are required, it will be provided.
·         Thickness selection shall be made from Thickness Tables in the insulation specifications specified for the job.


7.3.2  Insulation Application:
I)         Hot Insulation
·        The surfaces to be insulated shall be dry and reasonably clean prior to the application of the insulation.
·        Check the insulation sections are of correct type, size and thickness including thickness orientation for application as per the project specification.
·        Single layer of insulation shall be applied with longitudinal joints staggered. In multiple layer application all joints of adjacent layers shall be staggered.
·        Insulation of single or multiple layers shall be secured properly with stainless steel 304 Tie wire or Strap as specified fastening material in project specification.

II)    Steam Tracing & Electrical Tracing Insulation

·       Steam tracing & Electric tracing pipe insulation shall be oversized.

III)   Personal Protection 

·      Piping & equipment  operating above 60° C shall be provided with insulation for
            Personal Protection where accessible
     
·      Personal Protection shall be provided to 7 ft (2.13 m) above grade or platforms and
            3ft (0.91 m) horizontally from the periphery of platforms, walkways or ladders.

·      For Hydrogen service or where heat conservation insulation is not required for
            flanges a sheet metal shroud should be installed over flanges for personnel protection.

7.3.3      Jacketing Application

·        Insulated surface shall be weatherproofed by applying fabricated flat metal jackets.
·         Check the material issued is the correct thickness as specified in specification.
·        Jacketing shall be fitted in such a manner as to provide a close fitting assembly without gaps.
·        After the installation of the Jacketing, sufficient clearance to be maintained from nearby spools with or without Jacketing.
·        Jacketing for Insulation on electric tracing & Steam tracing piping shall be installed with bands only.

7.3.4      Insulation Excluding Welding Joint

·        Weld joint exclusion is only applicable in combination with PMT/C/PID written approval on the exclusion of the particular weld joint in view of delayed hydro testing.


·        For the welding joint near the valve & Flange, clearance will be Bolt length plus 25mm as per specification

8.0         Removable Valve & Flange Box
·        Valve and flange box shall be removable type
·        Secure Insulation to metal cover with clips
·        Valve & Flange cover shall be secured with quick release toggle clips (1” & 2” )
·        Box shall have 50mm overlap & top sloped to drain water
·        Sealant shall be used to weather proof openings


9.0         RESOURCES

Machinery Lists
Sl No
Description
No. Required
1
Material storage shed
As required
2
Metal fabrication shed
As required
3
Sheet Metal fabrication machineries such as cutting, rolling, swaging, folding, lock-form etc
As required
4
Electric tools – battery drill, shear cutter etc
As required
5
Hand tools- saw, band tighter etc
As required
6
Pulley- Manual lifting by rope
As required

10.0      HSE REQUIREMENTS
             
·         Comply with all Requirements of LUBREF EHS Standards procedure.
·         Task Risk Assessment shall be carried for all critical activities. Risk Assessment to address all the hazards and how to reduce them.
·         Toolbox talks shall be conducted on daily basis prior to commencement of the work.
·         All personnel shall adhere to all relevant procedures set out in the KAEFER/SAMSUNG/LUBREF HSE plan.
·         Flexible hoses shall be armoured type, and shall be protected against external damage.
·         Work crews and supervisors will attend weekly HSE meetings.
·         All Machinery for the fabrication work should be well-maintained and safe to use.
·         All mandatory PPE (Helmet, Safety Gloves and Shoes) shall be provided all the time.
·         Materials used on this project contain no asbestos and causes no known health hazards either during or after installation. During application, however, the following precautions will be taken.
·         Follow the safety instruction given in material safety data sheet.
·         Protect skin from irritation by wearing loose clothing; wash work clothing separately from other garments.
·         Protect eyes and respiratory tract from airborne product by wearing dust masks and goggles/safety glasses or eye shields.
·         All waste to be disposed-off in safe manner.
·         Unauthorized person not allowed to entire work area.
·         MSDS to be made available.
·         Workers at height 100% tie off and suitable working platforms (Scaffolding).




11.0      QC REQUIREMENTS

·               KAEFER will issue RFI to Contractor wherever applicable as per approved Inspection and Test Plan (ITP) requirement.
·               Upon final acceptance of the installation of the insulation and metal cladding, the QC department shall issue an insulation installation and completion report as per project approved form. 
·               All required documentation will be maintained by QC department.

12.0       ATTACHMENTS

·         Attachment I  SATIP-N-001-02

·         Attachment II JSA for Insulation work

No.
Activity
Potential Hazards
Preventive Measures
1
Manpower/Personnel transportation to and from site
Ø  Incompetent vehicle driver
Ø  Over speeding of driver
Ø  Personnel injury and manage to asset
Ø  H2S gas leakage
Ø  Hydrogen gas leakage
Ø  Conduct tool box meeting.
Ø  Competent driver to drive,
Ø  Speed limit and safety signs posted on the road and strictly followed.
Ø  All vehicles to be used on site are CONTRACTOR inspected and approved for used.
Ø  Speed limit is 30 km / hour and safety sign board posted on the road.
Ø  Gas test shall be carried out.
Ø  Use proper gas monitor
2
Tools and  materials handling and transportation
Ø  Improper arrangement
Ø  Overloading
Ø  Personnel injury
Ø  Damage to asset
Ø  Proper stacking and arrangement of materials on the transport vehicle.
Ø  During transportation all materials shall be secured by using nylon rope.
Ø  Do not over speed follow speed limit.

3
Materials loading and unloading
Ø  Sharp edges of materials
Ø  Ergonomics
Ø  Slits, trips and falls
Ø  Falling of materials, tools and equipment during lifting
Ø  Personnel injury and damage to asset




Ø  Tool box meeting shall be carried out and all hazard associated with the job shall be discussed.
Ø  Ensure all workers involve are issued with correct type of PPE and wearing is strictly enforced.
Ø  All equipment and machinery that will be used unloading heavy load shall be in good condition, free of defects, CONTRACTOR inspected.
Ø  Tag line shall be provided for proper control of the load when lifting by crane.
Ø  Barricading and warning signs shall be posted around the work location.

4
Working inside the trench excavation more than 1.2meters deep
Ø  Oxygen deficiency
Ø  Collapse of soil
Ø  Improper/unsafe access
Ø  Personnel injury
Ø  Cave-in
Ø  Fall

Ø  Tool box meeting shall be carried out
Ø  If the trench excavation is more than 1.2 meters deep, confined space entry permit shall be ensured and all confined space entry procedures shall be complied.
Ø  Ensure all worker assigned are confined space entry trained. Log sheet of personnel entering and exiting the excavation shall be maintained.
Ø  Frequent gas and oxygen monitoring shall be ensured.
Ø  Ensure the both the edges of trench excavation are properly sloped to allowed entry personnel inside.
Ø  Ensure sufficient safe access and egress ladder shall be provided and maintained properly.
Ø  Daily excavation checklist shall be ensured and maintained at all times.
Ø  Supervisor must be there.
5
Equipment to be used Mobile crane, hiab, trailers, air compressor, cold cutting machine, welding machine.
Ø  Equipment operated by unauthorized by person.
Ø  Improper vehicle movement.
Ø  Over speeding of diesel engine whipping of hoses due to improper hose coupling
Ø  Untrained person
Ø  Working platform
Ø  Cut metal chips
Ø  Fire
Ø  Uninspected welding machine
Ø  Relevant work permits to be obtained from the authority concerned.
Ø  Operator must be assigned to the equipment to operate.
Ø  Use approved equipments with regular maintenance and inspection of equipments.
Ø  Movement should be controlled by authorized banks man.
Ø  Arrestor to be fixed for engine exhaust pipe.
Ø  Fire extinguisher.
Ø  Use proper PPE.
Ø  Good housekeeping.
Ø  Blanket must be placed below the cut pipe to collect all metal chips.
Ø  Welding machine should be inspected by CONTRACTOR.
6
Scaffolding/temporary working platform erection and dismantling
Ø Slips, trips and falls.
Ø Tools and materials falling from height.
Ø Personnel injury and damage to asset.
Ø High wind velocity.
Ø Tool box meeting shall be carried out daily.
Ø All workers must be issued with the correct type of PPE.
Ø Full body harness with two lanyards must be issued to all workers working on 1.8 meters above and 100% tied off shall be strictly enforced whilst on height.
Ø All area should be barricaded.
Ø Housekeeping
Ø Only competent and certified workers shall be carried out the works.

7
Working at heights
Ø Tools and materials falling from at heights
Ø Personnel injury and damage to asset.
Ø Equipments falling from heights
Ø High wind velocity
Ø Slips, trips and falls
Ø Can tip over
Ø Fire
Ø explosion
Ø Full body harness with two lanyards must be issued to all workers working on 1.8 meters above and 100% tied off shall be strictly implemented.
Ø Samsung work at height training must be completed by the involve workers prior to mobilization to the site.
Ø Tools and materials must be secured and tied properly when using and lifting on heights respectively.
Ø Working area should be barricaded.
Ø Scaffolding material shall be free of defects, inspected and approved by Samsung.
Ø Mobile elevated working platform must be good running condition, free of defects and with valid third party inspection certification.
Ø Barricading and warning signs must be posted around the working area.
Ø All working platform should be inspected and tagged.

8





Insulation works








Ø Permit inadequate.

Ø Poor safety attitudes of workers.
Ø Minor injuries to finger/hand.


Ø Operating the machineries by unauthorized personnel.
Ø Bits/scraps falling on eyes.
Ø Exposure to sunlight/wind/mixing with soil or sand.
Ø Electrical fault.




Ø Fire source.



Ø Physical contact with eye /skin.


Ø Inhalation of insulation dust/dirt.




Ø Sheet metal cut pieces/scraps left over.





Ø Ensure company is processed and authorized and competent persons.
Ø Safety audits and unsafe act auditing.

Ø Conduct daily tool box meeting for safe handling of sheet metal.
Ø Make sure that personnel are wearing hand gloves while handling the sheet metal.
Ø Make sure that only authorized /trained personnel are operating the machines.


Ø Check that all the personnel are using eye protection safety glasses at all times.
Ø All material will be stored on pallet and properly covered.

Ø Check that all the electrical connection are properly protected.
Ø All tools and equipments must be color coded and inspected by CONTRACTOR.

Ø Ensure all insulation packaging materials are correctly removed prior to installation.
Ø Provide fire extinguisher.

Ø All PPE such as helmet, safety glass, dust mask, coverall, hand gloves and safety shoes must be worn at all times.

Ø Particle must be worn at all times.

Ø Use of garbage bag to collect bits and pieces of insulation material to avoid dust/dirt arising from it.

Ø All waste and left over materials must be collected on daily basis and disposed as per MSDS and project waste disposal procedure.

Ø Provide MSDS.
                 

Thursday, 23 November 2017

Leadership in Energy and Environmental Design (LEED) Certification !!

igbcapWhy learn about LEED?
Owners and developers are demanding green buildings to save money while protecting the environment and occupant’s health. LEED ® has already been adopted by USA, Canada, Mexico, and India and the Emirates GBC.



Who should attend?
Industry professionals who wish to become a LEED ® accredited professional
  • Facility Managers
  • Building Owners
  • Developers
  • Client Representatives
  • Architects
  • Engineers
  • Consultants
  • Sustainability Managers
What's covered?
LEED ® Green Associate V4 (2 days)
  • Green Building and the LEED process
  • Project Site Factors / Water Management
  • Project Systems and Energy Impact / Acquisition, installation and management of project materials
  • Improvements to the Indoor Environment / Stakeholder Involvement in Innovation / Project Surroundings and Public Outreach
LEED ® AP Building Design and Construction V4 (2 days)
  • Recognise the unique aspects of the BD & C and the differences between each rating system
  • Identify the minimum programme requirements for BD & C
  • Describe the goal, intent & requirements
  • Identify synergy between BD & C credits
  • Plan for key considerations and requirements for the LEED Certification process

LEED ® AP Building Operations and MaintenanceV4 (2 Days)
  • Materials In
  • Material Out
  • Administration
  • Green Cleaning
  • Site Management
  • Occupant Health
  • Energy Metrics
  • Operational Effectiveness
You may request Special sessions on LEED AP V4 for the below mentioned:
  • LEED® for Neighborhood Development
  • LEED® for Interior Design and Construction
  • LEED® for Homes.

The Benefits of LEED Certification

Leave the Competition Behind. Whether you are a freelance designer, or head of a multi-million dollar corporation, it is important to stay on top of the cutting edge trends in your industry. In this economy, you can't risk losing out on bids and potential business because you aren't in the know. Having an Accredited Professional on staff can be a highly marketable asset. For example, did you know that all GBCI registered projects that have an Accredited Professional on the job receive an extra point towards the project certification? This easy, single point can be the difference between the project being awarded a Gold versus Silver status. This is just one of many examples of why having an Accredited Professional on staff can give you an edge over your competition.
Signify Your Green Building Expertise. You've worked hard to become educated on green building concepts and strategies. Turn this knowledge into a tangible credential, developed and backed by the U.S. Green Building Council. The Green Associate and Accredited Professional credentials have gained national and global notoriety as the Leadership in Energy and Environmental Design rating system becomes one of the most widely used standards for green building and design. Having these credentials after your name and on your resume will help you become a more attractive candidate for green jobs, consulting gigs, and other opportunities in the green building field.
New Directions, New Business. Capitalize on the Green Collar economy. Whether you are looking to start a new career path, or develop new business for your company, accreditation can be a stepping-stone to new contacts and new opportunities for success in the green building and design fields.
Make a Difference in How We Design & Build. Many current methods used in the building industry can be harmful to our planet, our communities, and even our health. Take action towards improving this system, by learning and implementing more sustainable, eco-friendly, and energy-efficient practices. Whether it's developing improved waste management strategies, or spearheading the installation of a green roof, individuals of all skills and backgrounds can play an integral role in promoting and implementing this change.

The Importance and Advantages of LEED Certification

Acquiring LEED certification will introduce you to the following benefits:
  • Recover higher costs as green building offers a lot of alternatives that can downsize the structural, electrical and mechanical system.
  • Designs are cost-effective since building saves from 20% to 50% energies compared to common construction.
  • Care for the future
  • Enhance health and well-being of tenants
  • Get introduced to large number of equipment which can help you save more energy and be environment friendly.
LEED Certification are given to organizations likes Construction, Commercial Interiors, Existing Buildings, New Buildings, Core and Shell, Schools, Homes, Hotels, Retail, Healthcare and Neighborhood Development. This orients the company on how to contribute in taking care of our environment.

Standards of LEED Certification

To get the LEED Certification, you must secure the following:
  • Prevention of pollution within the construction site
  • Reduce water use
  • Minimum energy performance as per ASHRAE 90.1
  • Building energy systemsn
  • Refrigeratioin management
  • Collecting and storing recyclables
  • Smoke-free environment

LEED exam in India and qualifying for the LEED Green Associate

There are three ways to qualify for the LEED Green Associate exam:
1) You must be or have been employed in a sustainable field of work OR
2) You must be or have been involved in a LEED certified project within the last three years OR
3) You must show involvement in an education program that addresses green building principles
It is possible that your work as a senior engineer in HVAC planning would qualify as a “sustainable field of work.” To learn more, check out our previous article to learn what we believe qualifies as a sustainable field of work.
However, the Green Building Certification Institute (GBCI) will give the official ruling on this matter, so if you are unsure of whether your work as an HVAC engineer will count, contact GBCI at gbci.org or by calling 1-800-795-1746.

LEED Experience and Green Building Education

If your field of work does not qualify you, Green-Buildings.com offers the tools you need to become eligible for the exam.
First, Green-Buildings.com offers the LEED Project Experience Program, which will make you eligible for the Green Associate exam. It will satisfy the second option for eligibility, which is involvement in a LEED project.
This program allows you to work on a live LEED project, 100% online. Since many project teams want someone who is already a LEED AP to work on their LEED project, this is a good option for aspiring LEED APs.
Additionally, Green-Buildings.com offers Green Associate exam prep courses that will provide you a certificate of completion. This certificate of completion can be used to satisfy third option for eligibility, which is involvement in a green building education program.

LEED Green Associate Exam Costs

GBCI charges a $50 application fee for the LEED Green Associate exam. Additionally, the exam (per exam appointment) costs $150 for full-time students and members, or $200 for all others.
Once you earn your Green Associate credential, you must pay $50 every two years to maintain your credential through the Credential Maintenance Program (CMP). If you choose not to maintain the credential through CMP, you can either retest or lose your credential.

LEED Green Associate Exam Prep Courses

Learn all about LEED certification and jumpstart your career in green building by earning the LEED Green Associate credential! LEED Green Associate is the introductory-level professional credential under the Leadership in Energy & Environmental Design (LEED) program, and demonstrates a general understanding of all the LEED green building rating systems.
Our LEED Green Associate classes provide an introduction to green building and sustainable design principles, specifically as they relate to USGBC's LEED green building rating system. This course prepares individuals to pass the LEED Green Associate exam on the first try, and is the first step in becoming a LEED professional. This course is fully updated for the new LEED v4 rating system!


About

Our in-person LEED Exam Prep comes with access to our on-demand materials as well. Our instructors combine real-world LEED Project expertise with best practices to deliver material in a way that ensures students pass their LEED exams the very FIRST time! GBRI's Exam Prep will familiarize you with ALL the required information to pass the LEED Green Associate and BD+C Exam. You don't need to purchase anything else besides what's already included in your package.
Prepared by 7+LEED Professionals, GBRI’s LEED v4 Exam Prep Package contains everything you need to prepare for the LEED Green Associate Exam - self-paced modules, a road map, study guide, 200+ practice questions, memory charts, flash cards, audio files, and 2 mock exams. Taught in the context of a real LEED v4 project, GBRI’s exam prep addresses LEED project experience questions apart from analyzing knowledge and task domains.
• Earn your USGBC LEED AP credential in as little as 4 weeks
• Practice exams: 300+ practice test questions with explanations for each question to help you review and solidify your understanding
• Mock Exams : 2 Simulated Mock Exams
• Self-Paced Modules
• Study Guide, Flash Cards and Memory Charts(printable)
• Competitive pricing:


Objectives

  1. Prepare for the LEED Green Associate exam
  2. Identify and learn intent, requirements, reference standards, implementation strategies and exemplary options for all the credits under the BD+C rating system
  3. Analyze the required task and knowledge domains presented on the LEED Green Associate Exam
  4. Learn how to prepare for the LEED Green Associate professional role by working on a real-life LEED registered project
  5. Review 200+ practice test questions with explanations


Wednesday, 22 November 2017

சித்தூர் ராணி பத்மினியின் கதையா இந்த பத்மாவதி !! ஒரு சிறப்பு பார்வை..


Image result for queen padmavati


சித்தூர் ராணி பத்மினி என்ற தமிழ் படம் நியாபகம் உள்ளதா ?

பேரழகி சித்தூர் ராணி பத்மினியின் அவள் நூறு கிளியோபாட்ராவின் அழகுக்குச் சமமானவள்! இதோ அந்தக் கதை:--

14-ம் நூற்றாண்டில் (ஏறத்தாழ 700 வருடங்களுக்கு முன்), அலாவுதீன் கில்ஜி, டில்லியிலிருந்து அரசோச்சிய காலத்தில் ரஜபுதனத்திலுள்ள (ராஜஸ்தான் ) சித்தூரை ராஜபுத்திர பேரரசரான ரத்தன்சிங் என்பவன் ஆண்டுவந்தான். ராணி பத்மினி மிகப் பெரிய பேரழகி. இவரிடம் ஹிரா மணி என்ற பேசும் கிளி இருந்திருக்கிறது. அந்த கிளி சித்தூர் அரசன் ராணா ரத்தன் சிங் என்ற ராஜாவிடம் சென்று எங்களது ராணி பேரழகி என்று கூறியிருக்கிறது.. உடனே அவரும் ராணியை திருமணம் செய்ய சுயம்வரத்திற்கு வந்திருக்கிறார். சுயம்வரத்தில் பத்மினி யையும் திருமணம் செய்து கொள்கிறார்.

பத்மினி தாமரை போன்ற அழகிய முகம் வாய்ந்தவள். தைரியசாலி, நல்ல புத்தி சாதுர்யமிக்கவள். அவளுடைய அழகு பற்றிய செய்தி வட இந்தியா முழுதும் பரவியிருந்தது.


அலாவுதீன் கில்ஜிக்கு, எல்லா முஸ்லீம் மன்னர்களுக்கும் இருந்தது போல பல மனைவியர் இருந்தனர். அவன், சித்தூர் ராணி பத்மினியையும் அபகரிக்க விரும்பினான். ஆகவே பெரும்படையுடன் புறப்பட்டு ராஜஸ்தானுக்கு வந்து சித்தூரை முற்றுகையிட்டான். “நான் சித்தூரை வெல்ல வரவில்லை என்றும், பத்மினியின் அழகை ஒரே ஒரு முறை பார்த்துச் செல்லவே வந்ததாகவும்” ரத்தன் சிங்கனுக்குச் செய்தி அனுப்பினான்.


ரத்தன்சிங் அவன் வார்த்தையை நம்பி, ஓரிரு வீரர் துணையுடன் கோட்டைக்குள் வரலாமென்றும், ரஜபுத்ரப் பத்தினிப் பெண்கள் வேறு ஆடவரைப் பார்க்கக் கூடாதாகையால் நிலைக் கண்ணாடியில் மட்டும் அவள் உருவத்தைப் பார்க்கலாம் என்றும் நிபந்தனை போட்டான். உடனே அலாவுதீனும் இரண்டொரு வீரருடன் வந்து கண்ணாடியில், பேரழகி பத்மினியைப் பார்த்தான். ஏதேனும் சதி செய்து அவளைக் கவரவேண்டும் என்று எண்ணி,மனதில் சதித்திட்டம் தீட்டினான்.

“நான் உன்னை நம்பி, உன் கோட்டைக்குள், தனியே வந்தேனே. நீயும் என்னை நம்பி என் கூட வந்து வழியனுப்பக்கூடாதா?” என்று ரத்தன்சிங்கிடம் அலாவுதீன் சொன்னான். ரஜபுத்ர இந்துக்கள், அலாவுதீனை நம்பி அவன் கூட குதிரையில் செல்லுகையில், அலாவுதீன் உத்தரவிட்டவுடன் ஆப்கானியப் படைகள், ரத்தன்சிங்ச் சூழ்ந்து கொண்டன. அவனைக் கைது செய்து டில்லிக்குக் கொண்டு சென்றான் அலாவுதீன்.

“உன் மனைவியை என்னிடம் ஒப்புவித்தால் நான், உன்னை விடுவித்து, மீண்டும் சித்தூரின் மன்னனாக்குவேன்” என்று அலாவுதீன் சொன்னான். ஆனால் ரத்தன்சிங் இணங்கவில்லை. இந்தச் செய்தி சித்தூர் வரை சென்றது.


ரத்தன்சிங்னின் மனிவியான பத்மினி மஹா புத்திசாலி;வைரத்தை வைரத்தால் அறுக்க வேண்டும், முள்ளை முள்ளால் எடுக்க வேண்டும்; வஞ்சனையை வஞ்சனையால்தான் வெல்ல வேண்டும் என்று கருதி,அலாவுதீன் கில்ஜிக்குச் செய்தி அனுப்பினாள். என் கணவனை நீ விடுவிப்பாயானால், நான் உன்னிடம் வரத்தயார். ஆயினும் ரஜபுதனப் பெண்கள், எல்லோரும் காணும்படி வெளியே உலவ மாட்டார்கள். ஆகவே என் பரிவாரம் புடை சூழ மூடிய பல்லக்குகளில் வருவோம்” என்றாள். அலாவுதீனும் ஆவலுடன் காத்திருந்தான்.



சித்தூர் கோட்டையிலிருந்து 70 மூடு பல்லக்குகள் புறப்பட்டன. ஒன்றில் கூட பெண்கள் கிடையாது. அத்தனையிலும், தேர்ச்சிபெற்ற 70 வீரர்கள் மறைந்திருந்தனர். ஆறு பல்லக்குத் தூக்கிகள், ஒவ்வொரு பல்லக்கையும் சுமந்தனர். அவர்கள் அனைவரும் வீரர்கள். பல்லக்குகளில் ஆயுதங்களை மறைத்து வைத்தனர். பாந்தால் என்பவன் அவர்களை டில்லியை நோக்கி அழைத்துச் சென்றான். அவன், “ பத்மாவதி, கடைசியாக ஒரு முறை கணவனைப் பார்த்துவிட்டு உன்னிடம் வருவாள்” என்று அலாவுதீனிடம் சொன்னவுடன் “ பத்மாவதியின் பல்லக்கை” கூடாரத்துக்குள் அனுப்பினான். அதிலிருந்த வீரன் வெளியே குதித்து ரத்தன்சிங் குதிரையின் மேல் வைத்து தப்பிக்கச் செய்தாள் . உடனே பெரும் சண்டை நிகழ்ந்தது. இரு தரப்பும் வீரர்களை இழந்தன.

ஓரிரு ஆண்டுகள் உருண்டோடின. அலாவுதீனின் வெறி அடங்கவில்லை. எப்படியும் பத்மினியை அடைந்தே தீருவதென்று முடிவு செய்து, மீண்டும் படையெடுத்து சித்தூரை முற்றுகையிட்டான்.


இப்பொழுது ரத்தன்சிங் பலவீனமான நிலையில் இருந்தான்; ஏனெனில் முந்தைய போர்களில் முக்கியப் படைத் தலைவர்களை இழந்துவிட்டான். ஒரு கட்டத்தில் தோல்வி நிச்சயம் என்று தெரிந்தது. தன் மகனை அருகாமையிலுள்ள ரஜபுதன ராஜ்யத்துக்கு அனுப்பி பாதுகாப்பாக இருக்கும்படி சொல்லிவிட்டு வீரதீரப் போரில் ஈடுபட்டு உயிர்துறந்தான் ரத்தன்சிங் . யா  இந்த 


ரஜபுதனப் பெண்கள் வீராங்கனைகள்; அரண்மனையின் அந்தப் புரத்தில் மாபெரும் தீ வளர்த்தனர். அதில் முகமதியரிடமிருந்து தங்கள் கற்பைக் காக்க அன்று 74,500 பெண்கள் அந்தத் தீயில் வீழ்ந்ததாகக் கூறப்படுகிறது., பேரழகி பத்மினியுடன் குதித்து சாம்பலாயினர். வெற்றிக் களிப்புடன் கோட்டைக்குள் நுழைந்த அலாவுதீனுக்கு, வீரர்களின் பிணங்களும்,வீரத்தாய்மார்களின் சாம்பலுமே கிடைத்தது!

ராணி பத்மினி மன்னர் உமாயுனைச் சகோதரனாக உதவி கோரி, ராக்கி கயிறு அனுப்பியதாகவும், உமாயுன் வரும் முன்பே கில்ஜியின் முற்றுகை முற்றி, பத்மினி இறந்ததாகவும் கூறப்பெறுகிறது. பத்மினி அனுப்பிய ராக்கி கயிறே பின்நாளில் ரக்சா பந்தன் என்ற விழாவாக வட இந்தியாவில் கொண்டாடப் பெறுகிறது. 

இதனால் ராணி பத்மாவதியை ராஜஸ்தானில் உள்ள ஒரு பிரிவினர் தெய்வமாக வழிபடுகிறார்கள். பாரத நாடு உள்ள வரை, பத்மினியின் புகழும் நீடிக்கும்! ரஜபுதனக் கோட்டை கொத்தளங்களும், பாலைவன மணல் துகள்களும் இன்றும் கூட பத்மினியின் புகழைப் பாடிக்கொண்டிருக்கின்றன!!


தமிழில் பத்மினி திரைப்படம்.. 

சித்தூர் ராணி பத்மினி 1963 ஆம் ஆண்டு வெளிவந்த தமிழ்த் திரைப்படமாகும். சி. எச். நாராயணமூர்த்திஇயக்கத்தில் வெளிவந்த இத்திரைப்படத்தில் சிவாஜி கணேசன் , வைஜெயந்திமாலா ராணி பத்மாவதியாக நடித்திருந்தனர்.
இந்தியில் ‘பத்மாவதி 
திரைப்படம் !!

சித்தூர் ராணி பத்மினியின் கதை இந்தியில் ‘பத்மாவதி’ என்ற பெயரில் சினிமாவாக தயாரிக்கப்பட்டுள்ளது. நடிகை தீபிகா படுகோனே ராணி பத்மினியாக நடித்துள்ளார். பிரபல இயக்குனர் சஞ்சய் லீலா பன்சால் என்பவர் திரைக்கதை வசனம் எழுதி இயக்கி உள்ளார். கவிஞர் மாரிக் முகமது ஜெயாசி எழுதிய கவிதையை அடிப்படையாக கொண்டு இந்தப் படம் தயாரிக்கப்பட்டுள்ளது. நடிகர் ஷாகித் கபூர் ராணி பத்மினியின் கணவர் ராவல் ரத்தன் சிங்காகவும் டெல்லியை ஆண்ட சுல்தான் அலாவுதீன் கில்ஜியாக ரன்வீர் சிங்கும் நடித்துள்ளனர். வருகிற டிசம்பர் பத்மாவதி படம் திரைக்கு வருகிறது. படத்தில் சித்தூர் ராணி பத்மாவதியின் வரலாறு தவறாக சித்தரிக்கப்பட்டு உள்ளதாக ராஜஸ்தான், குஜராத் மற்றும் மராட்டிய மாநிலத்தில் வசிக்கும் ராஜ புத்திர வம்சத்தினர் எதிர்ப்பு தெரிவித்து போராட்டத்தில் ஈடுபட்டு வருகிறார்கள்.படத்தை தடைசெய்யும்படி சுப்ரீம் கோர்ட்டில் தொடரப்பட்ட வழக்கு தள்ளுபடி செய்யப்பட்டு விட்டது.

டெல்லி சுல்தான் அலாவுதீன் கில்ஜியிடம் இருந்து மானத்தை காப்பாற்ற பல  ஆயிரம் பெண்களுடன் தீயில் இறங்கி உயிர் நீத்தவர் ராணி பத்மினி.ஆனால் பத்மாவதி படத்தில் அலாவுதீன் கில்ஜியை ராணி பத்மினி காதலிப்பதுபோல் தவறாக காட்சிபடுத்தி உள்ளனர் என்று அவர்கள் குற்றம் சாட்டி உள்ளனர். இதற்கிடையே பத்மாவதி படத்துக்கு ரஜபுத்தர மன்னர்களின் வம்சத்தினர் எதிர்ப்பு தெரிவித்துள்ளனர். 




பத்மாவதி பட சர்ச்சை என்னை அலாவுதீன் கில்ஜியின் வரலாறை அறிய
முற்படுத்தியது. தவறான சித்தரிப்புகளுக்கு முன்னால் நாம் அவரைப்பற்றி தெரிந்து கொள்வோம். நீங்களும்..


அலாவுதீன் கில்ஜியின் வரலாற்றின் சிறு குறிப்பு.



அலாவுதீன் கில்ஜி கி.பி 1295 முதல் 1316 வரை டெல்லியில் அரசனாக ஆட்சி செய்தவர்.

1298ல் குஜராத் மீது படையெடுத்து வெற்றி கொண்டவர்.

1299ம் ஆண்டு டெல்லியை கைப்பற்ற வந்த மங்கோலியர்களை விரட்டி அடித்த இரண்டாம் அலெக்சாண்டர் (கில்ஜி)

1310ல் கில்ஜி,மாலிக்காபூர் படை தேவ்கீர் மீது படையெடுத்து கர்நாடக,மலபார், கனாரா பகுதிகளை பிடித்து கொரமண்டல் பகுதி முழுவதும் தன் வசப்படுத்தினார்.(எனவே காஷ்மீர் முதல் கன்னியாகுமரி வரை பெரும்பகுதியை ஆட்சி செய்த மன்னர்)

இந்தியாவில் மதுவை ஒழிக்க முதன்முதலாக சட்டம் கொண்டு வந்த சுல்தான், மதுவை தயாரிப்பதையும்,விற்பதையும்,அருந்துவதையும் பெரும் தண்டனை குற்றமாக அறிவித்தவர். அலாவுதீன் கில்ஜி

வியாபாரிகள், பிரயாணிகள் பாதுகாப்பாகவும்,தொல்லையில்லாமல் பயணிக்க நெடுஞ்சாலைகள் போட்டார்.

விலைவாசிகளை கட்டுப்படுத்த மக்களின் அத்தியாவசிய பொருட்களுக்கு மன்னரே விலை நிர்ணயம் செய்தார்.அதுவே இன்றைய state Trading Corporation of India என்னும் கொள்கைக்கு முன்னோடி.

1296ல் அலாவுதீன் கில்ஜி 70ஏக்கர் நிலத்தில் மிகப்பெரிய நீர் நிலையை உருவாக்கினார். இதிலிருந்து மக்களுக்கு பாதுகாக்கப்பட்ட குடிநீர் வழங்கினார்.

வழிப்போக்கர்கள் தங்குவதற்கு சாவடிகளும், சத்திரங்களும் கட்டினார் மேலும் இலவச உணவும் அளிக்கப்பட்டது.

கி.பி.1316ல் ஜனவரி 2ம் தேதி அலாவுதீன் கில்ஜி மரணமடைந்தார்


இந்த சித்தூர் ராணி பத்மினி சரித்திரத்தில் எனக்குள் எழும் கேள்விகள் ?

1, அலாவுதீன் கில்ஜி கெட்டவன் என்று வைத்துக்கொள்ளவோம். இவன் படையுடன் சித்தூரில் முகாமிட்டுள்ளான். ஏன் அவனுக்கு பத்மாவதியை காட்ட வேண்டும். இதில் எதோ உடன்பாடு முரண்பட்டதால் அவன் ரத்தன்சிங்கை டெல்லிக்கி கூடி சென்றான். அவன் நினைத்தால் பத்மாவதியை சித்தூரிலே அடைந்திருக்கலாமே ?

2, ஆயுதங்கள் மறைத்து 70 பல்லக்குடன் வந்து ரத்தன் சிங் தப்பித்தார் என சரித்திரம் கூருகிறது. டெல்லியை ஆண்ட அலாவுதீன் கில்ஜி  முட்டாளாக இருக்க முடியாது. அப்படி இருந்தால்  நாட்டை எப்படி  காப்பாற்ற முடியும் ?

3, அரண்மனையின் அந்தப் புரத்தில் அணைத்து பெண்களுடன்  ராணி பத்மினி  ஏன் தீ குளிக்க வேண்டும். ( அலாவுதீன் கில்ஜி அடைய நினைத்தது பத்மினி ராணியை மட்டுமே ). 


4,ஒரு வேலை இந்தியில் ‘பத்மாவதி’ என்ற பெயரில் சினிமாவாக தயாரிக்கப்பட்டுள்ள கதையில் உள்ளது போல் அலாவுதீனிக்கும், பத்மாவதிக்கும் காதல் மலர்ந்து , அதை மறைக்க, ராஜ புத்திர வம்சத்தின் பெருமையை காக்க அவர்களே பெண்களை தீ குண்டத்தில் கொளித்தீர்களாம் அல்லவா ?

5, மாலிக் முகமது ஜாயசி என்பவர் 1540ல் எழுதிய கவிதை தான் ராணி பத்மினியின் முதல் வரலாறு குறிப்பு என அறியப்படுகிறது. அதனால் அலாவுதீன் கில்ஜியை நாம் கெட்டவன் என  நினைத்துள்ளோம்.  இஸ்லாமிய  அடிப்படையில் போரில்  பெண்கள் மற்றும் குழந்தைகளை  கொல்லக்கூடாது. மேலும் பிறர்  மனைவியை  தப்பான கண்ணோட்டத்துடன்  பார்ப்பதும்  தடை செய்யப்பட்டுள்ளது. ஆகவே சித்தூர் ராணி பத்மினி  ஒரு  கதையாக  இருக்கலாம் என்பதே  எனது கருத்து ..


ஆக்கம்  மற்றும் தொகுப்பு : மு.அஜ்மல் கான்.


Sunday, 19 November 2017

World's largest umbrellas ( 4 Ea) installation Job started in Holy Mecca's Grand Mosque !!


The work starts to install the world's largest folding umbrella started last month on the northern courtyard of Mecca's Grand Mosque. It will be the first of eight high-tech giant umbrellas. As many as 54 smaller umbrellas are to be installed in the Grand Mosque during the upcoming six months


Image result for mecca umbrellaThe giant umbrellas were made in Germany. The shades will come complete with clocks, guiding screens, air conditioners and surveillance cameras. Each umbrella will be 45 meters high and 16 tons heavy. Once all open, the umbrellas will protect people from the sun on the territory of 2,400 square meters, gulfinthemedia.com reports.

More than 25 engineers, technicians and security specialists from Germany will supervise the installation process, as well as the operating electronic mechanism.Fifty-four smaller shades will be installed in the northern courtyard on the territory totaling ​​19,200 square meters. When the project is complete, as many as 400,000 worshipers will be able to hide from the sun in the shaded area.

More Details..
http://lifeinsaudiarabia.net/blog/2016/03/14/12-interesting-facts-about-worlds/

 Collection By Ajmal Khan