Saturday, 28 November 2015

M&E Consultant Firm in Malaysia

As for reference to my post from here, i try to compile most of the m&e consultancy firm for job hunting purpose for fresh grads.

International Firm
- Meinhardt
- J Roger Preston (JRP)
- Sinclair Knight Merz (SKM)
- Norman, Disney and Young (NDY)

Local Firm
- Kumarasivam, Tan & Arrifin + Tenaga (KTAT)
- Eagles Consultants
- Petareka
- Sepakat Setia Peruding (SSP)
- Jurutera Peruding Valdun
- ARUP Perunding

almost more to list down, but i guess these are the majors one .... feel free to add more in the comments...
  1. AECOM PERUNDING SDN BHD Website: http://www.aecom.com/
  2. AFRIMA CONSULTING ENGINEER SDN BHD Website: http://www.afrimagroup.com/
  3. AKTIF FA KONSULT SDN BHD Website: Not Available
  4. ALAM JURUTERA PERUNDING SDN BHD Website: Not Available
  5. AMIR MADANI RUNDING SDN BHD  Website: Not Available
  6. ANGKASA CONSULTING SERVICES SDN BHD Website: http://www.acssb.com.my/
  7. ANTARA JURUTERA PERUNDING SDN BHDWebsite: Not Available
  8. ARUP JURURUNDING SDN BHD
  9. Website: http://www.arup.com.my/
  10. ATZ CONSULT SDN BHD 
  11. Website: Not Available
  12. BERAKAN JURUTERA PERUNDING SDN BHD
  13. Website: Not Available
  14. BW PERUNDING SDN BHD
  15. Website: http://www.bwp.com.my/
  16. C. H. Chuah Perunding
  17. Website: Not Available
  18. CORPORATED INTERNATIONAL CONSULTANTS
  19. Website: Not Available

  20. Delta Consult Ing Services
  21. Website: Not Available
  22. DH PERUNDING
  23. Website: Not Available
  24. DK Perunding
  25. Website: Not Available
  26. DPI Konsult Sdn Bhd
  27. Website: http://www.dpik.com.my/
  28. DR C C WONG JURUTERA PERUNDING
  29. Website: Not Available
  30. DR Y G TAN JURUTERA PERUNDING SDN BHD
  31. Website: http://www.drygtan.com/
  32. EDP CONSULTING GROUP SDN BHD
  33. Website: Not Available
  34. ENGINEERING & ENVIRONMENTAL CONSULTANTS SDN BHD
  35. Website: Not Available
  36. EPSILON JURUTERA PERUNDING (S) SDN BHD
  37. Website: Not Available
  38. ERINCO SDN BHD
  39. Website: http://www.erinco.com.my/

  40. ESA JURUTERA PERUNDING SDN BHD
  41. Website: Not Available
  42. FARID AHMAD CONSULTING ENGINEERS SDN BHD
  43. Website: Not Available
  44. FIVE-H ASSOCIATES SDN BHD
  45. Website: http://www.fiveh.com.my/
  46. G & P PROFESSIONALS SDN BHD
  47. Website: http://www.gnpgroup.com.my/
  48. GCU CONSULTANTS SDN BHD
  49. Website: www.gcu.com.my
  50. GR ASSOCIATES SDN BHD
  51. Website: Not Available
  52. GTP CONSULTANTS SDN BHD
  53. Website: Not Available
  54. H&T CONSULTING ENGINEERS SDN BHD
  55. Website: www.htasb.com
  56. HASS CONSULTING ENGINEERS SDN BHD
  57. Website: Not Available
  58. HLA ASSOCIATES SDN BHD
  59. Website: http://www.hla-group.com/
  60. HSS INTEGRATED SDN BHD
  61. Website: http://www.hssgroup.com.my/
  62. HSS MEKANIKAL & ELEKTRIKAL SDN BHD
  63. Website: http://www.hssgroup.com.my/
  64. HUSSEIN & K.H. CHONG JURUTERA PERUNDING (M)
  65. Website: Not Available
  66. IHSAN TEAM CONSULTANTS SDN BHD
  67. Website: http://www.ihsanteam.com/
  68. IKHLAS PERUNDING
  69. Website: Not Available
  70. IKTISAS INGENIEURS SDN BHD
  71. Website: http://www.iktisas.com/
  72. ILHAM CONSULT SDN BHD
  73. Website: http://www.ilhamconsult.com/
  74. INGENIEUR BERSEKUTU 
  75. Website: Not Available
  76. J & A ASSOCIATES SDN BHD
  77. Website: Not Available
  78. J BERAKAN JURUTERA PERUNDING
  79. Website: http://jbjp.blogspot.com/
  80. JOHAN JURUTERA PERUNDING
  81. Website: Not Available
  82. J.P.R. SDN BHD
  83. Website: http://www.jpr.com.my/
  84. J. ROGER PRESTON (MALAYSIA) SDN BHD
  85. Website: http://www.jrpl.com/
  86. JPSPEC SDN BHD
  87. Website: Not Available
  88. JTK CONSULT SDN BHD
  89. Website: http://www.jtkconsult.com.my/
  90. JUARACONSULT SDN BHD
  91. Website: Not Available
  92. JURUJATI KONSULTANT SDN BHD
  93. Website: Not Available
  94. JURURUNDING IMK SDN BHD
  95. Website: Not Available
  96. JURUNDING KBZ
  97. Website: http://kbz-group.com.my/
  98. JURUTERA ARTECON SDN BHD
  99. Website: Not Available
  100. JURUTERA CMP SDN BHD
  101. Website: http://www.jcmp2002.enetmyne.com/
  102. JURUTERA GCS SDN BHD
  103. Website: Not Available
  104. JURUTERA JASA (SARAWAK) SDN BHD
  105. Website: http://www.juruterajasa.com/
  106. JURUTERA KONSULT MAJU SDN BHD
  107. Website: http://www.jkm-engineers.com/
  108. JURUTERA M & E KONSULT (SARAWAK) SDN BHD
  109. Website: Not Available
  110. JURUTERA MINSAR KONSULT SDN BHD
  111. Website: http://www.minsar.com.my/
  112. JURUTERA PERUNDING BERSAMA SDN BHD
  113. Website: Not Available
  114. JURUTERA PERUNDING BUMIREKA
  115. Website: Not Available
  116. JURUTERA PERUNDING CKS
  117. Website: Not Available
  118. JURUTERA PERUNDING GEA (M) SDN BHD
  119. Website: http://www.gea.com.my/
  120. JURUTERA PERUNDING INTELEK SDN BHD
  121. Website: Not Available 
  122. JURUTERA PERUNDING KINAKOTA SDN BHD
  123. Website: Not Available
  124. JURUTERA PERUNDING LC SDN BHD
  125. Website: Not Available
  126. Jurutera Perunding M&E NTM (S) Sdn Bhd
  127. Website: Not Available
  128. JURUTERA PERUNDING MUSTAPA DAN RAKAN-RAKAN SDN BHD
  129. Website: Not Available
  130. JURUTERA PERUNDING PRIMA JAYA
  131. Website: Not Available
  132. JURUTERA PERUNDING SRI ARIF SDN BHD
  133. Website: Not Available
  134. JURUTERA PERUNDING TEKADMAJU SDN BHD
  135. Website: http://www.jptm.com.my/
  136. JURUTERA PERUNDING VALDUN SDN BHD
  137. Website: http://www.valdun.com/
  138. JURUTERA PERUNDING WAHBA SDN BHD
  139. Website: http://www.wahbaengineering.com/
  140. JURUTERA PERUNDING W D LEE
  141. Website: Not Available
  142. JURUTERA PERUNDING WTA SDN BHD
  143. Website: Not Available
  144. JURUTERA TCS SDN BHD
  145. Website: Not Available
  146. K.L. CONSULT ASSOCIATES SDN BHD
  147. Website: http://www.klconsult.com/
  148. KEMASEPAKAT SDN BHD
  149. Website: Not Available
  150. KHAIRI CONSULT SDN BHD
  151. Website: www.kc.com.my
  152. KL PRIMA CONSULT SDN BHD
  153. Website: www.klprima.com.my
  154. KN ASSOCIATES SDN BHD
  155. Website: Not Available
  156. KONSMAL SDN BHD 
  157. Website: Not Available
  158. KONSORTIUM BUMI CONSULTANTS AND SERVICES SDN BHD
  159. Website: http://www.konsortiumbumi.com/
  160. KONSORTIUM MALAYSIA
  161. Website: Not Available
  162. KONSULTANT KUMPULAN (MT) SDN BHD
  163. Website: Not Available
  164. KONSULTANT PROSES SDN BHD
  165. Website: http://www.konpro-group.com/
  166. KTA (SARAWAK) SDN BHD
  167. Website: http://www.ktas.com.my/
  168. KTA TENAGA SDN BHD
  169. Website: http://www.ktatenaga.com.my/
  170. LI-ZAINAL SDN BHD
  171. Website: http://www.li-zainal.com/
  172. LYS CONSULT SDN BHD
  173. Website: Not Available
  174. MAR & Associates Sdn Bhd
  175. Website: Not Available
  176. MEGAMAS KONSULT SDN BHD
  177. Website: Not Available
  178. MEG CONSULT SDN BHD
  179. www.meg.com.my Website: http://www.meg.com.my/
  180. MINCONSULT SDN BHD
  181. Website: http://www.minconsult.com/
  182. MKH RUNDING SDN BHD
  183. Website: Not Available
  184. MMSB CONSULT SDN BHD
  185. Website: http://www.mmsbconsult.com.my/
  186. MOHD ASBI & ASSOCIATES
  187. Website: http://www.asbi-associates.com.my
  188. MOTT MACDONALD (M) SDN BHD
  189. Website: http://www.mottmac.com/

  190. NEXUS ENGINEERING CONSULTANTS
  191. Website: www.nexusec.com
  192. O.B.E. CONSULTING SDN BHD
  193. Website: Not Available
  194. OMNI PROJECT CONSULTANCY SDN BHD
  195. Website: http://www.omniprojectconsultancy.com
  196. PAKATAN RUNDING YUSOFF SDN BHD
  197. Website: Not Available
  198. PCR SDN BHD
  199. Website: Not Available
  200. PERUNDING ASATEC
  201. Website: Not Available
  202. PERUNDING BAKTI SDN BHD
  203. Website: http://www.pbakti.com/
  204. PERUNDING BENA
  205. Website: Not Available
  206. PERUNDING BSK SDN BHD
  207. Website: Not Available
  208. PERUNDING C. F.
  209. Website: Not Available
  210. PERUNDING DELIMA SDN BHD
  211. Website: Not Available
  212. PERUNDING ERA DAYA SDN BHD
  213. Website: Not Available
  214. PERUNDING FAISAL, ABRAHAM DAN AUGUSTIN SDN BHD
  215. Website: http://www.faapeng.com/
  216. PERUNDING GEA (SABAH) SDN BHD
  217. Website: Not Available
  218. PERUNDING HASHIM & NEH SDN BHD
  219. Website: http://www.phneh.com/
  220. PERUNDING IRNOVA SDN BHD
  221. Website: Not Available
  222. PERUNDING ISKFIT
  223. Website: Not Available
  224. PERUNDING JANJE 
  225. Website: Not Available
  226. PERUNDING JAYAREKA SDN BHD 
  227. Website: Not Available
  228. PERUNDING JPC SDN BHD
  229. Website: Not Available
  230. PERUNDING JPNS SDN BHD
  231. Website: Not Available
  232. PERUNDING KCT SDN BHD
  233. Website: Not Available
  234. Perunding Megatro Sdn Bhd
  235. Website: Not Available
  236. PERUNDING MENARA SDN BHD
  237. Website: Not Available
  238. PERUNDING MSA SDN BHD
  239. Website: Not Available
  240. PERUNDING MUHANDIS SDN BHD
  241. Website: http://www.perundingmuhandis.com.my/
  242. PERUNDING PERTAMA
  243. Website: Not Available
  244. Perunding SCK
  245. Website: Not Available
  246. PERUNDING SHAHELMEY & RAKAN-RAKAN SDN BHD
  247. Website: Not Available
  248. PERUNDING SERI YAKIN
  249. Website: Not Available
  250. PERUNDING TEKNIK GLOKAL SDN BHD
  251. Website: Not Available
  252. Perunding Teknik Padu Sdn Bhd
  253. Website: Not Available
  254. Perunding Techno Awam Sdn Bhd
  255. Website: Not Available
  256. PERUNDING YGL
  257. Website: Not Available
  258. PERWIRA AL-SHURA CONSULTING ENGINEERS SDN BHD
  259. Website: http://www.pace.com.my/
  260. PETAREKA PERUNDING (M) SDN BHD
  261. Website: http://www.petareka.com.my/
  262. PJS CONSULTANTS SDN BHD
  263. Website: Not Available
  264. PJSI Consultants Sdn Bhd
  265. Website: http://www.pjsi.net/
  266. Plantmac Engineering Consultant
  267. Website: Not Available
  268. PME CONSULTING ENGINEERS SDN BHD
  269. Website: Not Available
  270. POWER PROJECT CONSULTANT SDN BHD
  271. Website: Not Available
  272. PRIMETECH ENGINEERS SDN BHD
  273. Website: Not Available
  274. PRODANA WAWASAN CONSULTING ENGINEERS SDN BHD
  275. Website: Not Available
  276. PRODUKTIF SEPAKAT CONSULTING ENGINEERS SDN BHD
  277. Website: Not Available
  278. PRO JURUTEK ASSOCIATES
  279. Website: Not Available
  280. PS KONSULTANT SDN BHD
  281. Website: Not Available
  282. PU ENGINEERING SDN BHD
  283. Website: Not Available
  284. PY KONSEP PERUNDING SDN BHD
  285. Website: Not Available
  286. RANHILL CONSULTING SDN BHD
  287. Website: Not Available
  288. RJA CONSULTANT
  289. Website: Not Available
  290. RJP SDN BHD
  291. Website: http://www.rjpsb.com/
  292. RPM ENGINEERS SDN BHD
  293. Website: http://www.rpm-engineers.com.my/
  294. SARAHILL CONSULTING SDN BHD
  295. Website: Not Available
  296. SEJATI KONSULT
  297. Website: Not Available
  298. SEPAKAT SETIA PERUNDING SDN BHD
  299. Website: http://www.sspsb.com.my/
  300. SILKBRIDGE CONSULT
  301. Website: Not Available
  302. SINCLAIR KNIGHT MERZ ENGINEERING SDN BHD
  303. Website: http://www.globalskm.com/
  304. SISTEM KONSULT SDN BHD
  305. Website: Not Available
  306. SKM PERUNDING MAHIR BERSATU SDN BHD
  307. Website: http://www.globalskm.com/
  308. SMEC (MALAYSIA) SDN BHD
  309. Website: http://www.smecmal.com.my/
  310. SMHB SDN BHD
  311. Website: http://www.smhb.com/
  312. SRS CONSULTING ENGINEER
  313. Website: Not Available
  314. SSP (E&M) Sdn Bhd
  315. Website: http://www.sspsb.com.my
  316. STRAITS CONSULTING ENGINEERS SDN BHD
  317. Website: http://www.straits-engineers.com/
  318. SYNERGY ALLIANCE CONSULTANTS (M) SDN BHD
  319. Website: http://www.sacsb.com/
  320. T & T KONSULT SDN BHD
  321. Website: http://www.ttkonsult.com.my/
  322. T. S. YEE & ASSOCIATES
  323. Website: Not Available
  324. TAHIR WONG SDN BHD
  325. Website: Not Available
  326. TEKUN PERUNDING SDN BHD
  327. Website: Not Available
  328. TENAGA Z-L SDN BHD
  329. Website: Not Available
  330. TOTAL PROJECT SOLUTION CONSULTANT SDN BHD
  331. Website: http://www.totalproject.com.my/
  332. TY LIN INTERNATIONAL SDN BHD
  333. Website: http://www.tylin.com.my/
  334. WAN HUSIN & ASSOCIATES SDN BHD
  335. Website: http://www.wanhusin.com.my/
  336. WAN MOHAMED & KHOO SDN BHD
  337. Website: http://www.wmksb.com.my/
  338. WNG JURUTERA PERUNDING SDN BHD
  339. Website: Not Available
  340. WONG YING & SAN CONSULTANTS SDN BHD
  341. Website: Not Available
  342. WTS KONSULTANT SDN BHD
  343. Website: Not Available
  344. ZAIDUN-LEENG SDN BHDSARAHILL CONSULTING SDN BHD
  345. Website: Not Available
  346. SEJATI KONSULT
  347. Website: Not Available
  348. SEPAKAT SETIA PERUNDING SDN BHD
  349. Website: http://www.sspsb.com.my/
  350. SILKBRIDGE CONSULT
  351. Website: Not Available
  352. SINCLAIR KNIGHT MERZ ENGINEERING SDN BHD
  353. Website: http://www.globalskm.com/
  354. SISTEM KONSULT SDN BHD
  355. Website: Not Available
  356. SKM PERUNDING MAHIR BERSATU SDN BHD
  357. Website: http://www.globalskm.com/
  358. SMEC (MALAYSIA) SDN BHD
  359. Website: http://www.smecmal.com.my/
  360. SMHB SDN BHD
  361. Website: http://www.smhb.com/
  362. SRS CONSULTING ENGINEER
  363. Website: Not Available
  364. SSP (E&M) Sdn Bhd
  365. Website: http://www.sspsb.com.my
  366. STRAITS CONSULTING ENGINEERS SDN BHD
  367. Website: http://www.straits-engineers.com/
  368. SYNERGY ALLIANCE CONSULTANTS (M) SDN BHD
  369. Website: http://www.sacsb.com/
  370. T & T KONSULT SDN BHD
  371. Website: http://www.ttkonsult.com.my/
  372. T. S. YEE & ASSOCIATES
  373. Website: Not Available
  374. TAHIR WONG SDN BHD
  375. Website: Not Available
  376. TEKUN PERUNDING SDN BHD
  377. Website: Not Available
  378. TENAGA Z-L SDN BHD
  379. Website: Not Available
  380. TOTAL PROJECT SOLUTION CONSULTANT SDN BHD
  381. Website: http://www.totalproject.com.my/
  382. TY LIN INTERNATIONAL SDN BHD
  383. Website: http://www.tylin.com.my/
  384. WAN HUSIN & ASSOCIATES SDN BHD
  385. Website: http://www.wanhusin.com.my/
  386. WAN MOHAMED & KHOO SDN BHD
  387. Website: http://www.wmksb.com.my/
  388. WNG JURUTERA PERUNDING SDN BHD
  389. Website: Not Available
  390. WONG YING & SAN CONSULTANTS SDN BHD
  391. Website: Not Available
  392. WTS KONSULTANT SDN BHD
  393. Website: Not Available
  394. ZAIDUN-LEENG SDN BHD
  395. Website: http://www.zaidun-leeng.com.my/




Friday, 27 November 2015

роЪெрой்ройைропிро▓் роЙро│்ро│ роЪெроо்рокро░роо்рокாроХ்роХроо் роПро░ிропிрой் роХродை...

роХாроЮ்роЪீрокுро░роо் рооாро╡роЯ்роЯрод்родிро▓் роЪுрооாро░் роЖропிро░роо் роПро░ிроХро│் роЙро│்ро│рой. роЗро╡ை роЕройைрод்родுроо் рокро┤роЩ்роХாро▓род்родிро▓் роорой்ройро░்роХро│ாро▓் роПро▒்рокроЯுрод்родрок்рокроЯ்роЯродு.роЪெрой்ройைропை роороЯ்роЯுроо் роЗро▓்ро▓ாрооро▓், родрооிро┤роХрод்родைропே роХродி роХро▓роЩ்роХ ро╡ைроХ்роХுроо் рокெропро░ாроХிро╡ிроЯ்роЯродு роЪெроо்рокро░роо்рокாроХ்роХроо் роПро░ி. роТро╡்ро╡ொро░ு роиாро│ுроо் роПро░ிропைрок் рокро▒்ро▒ி роТро╡்ро╡ொро░ு родроХро╡ро▓்роХро│். роКроЯроХроЩ்роХро│ிро▓் ро╡ро░ுро╡родைро╡ிроЯро╡ுроо் роЪрооூроХ ро╡ро▓ை родро│роЩ்роХро│ிро▓் ро╡рои்род родроХро╡ро▓்роХро│் роЕродிро░ро╡ைрод்родрой. роЪெроо்рокро░роо்рокாроХ்роХроо் роПро░ி роОроЩ்роХு роЗро░ுроХ்роХிро▒родு роОрок்рокроЯி роЗро░ுроХ்роХிро▒родு роОрой்рокродро▒்роХாрой роХроЯ்роЯுро░ை роЗродு.

роХாроЮ்роЪிрокுро░роо் рооாро╡роЯ்роЯроо் роЪெроо்рокро░роо்рокாроХ்роХроо் роПро░ி роЪெрой்ройைропிро▓் роЗро░ுрои்родு 40 роХி.рооீ. родொро▓ைро╡ிро▓் роЙро│்ро│родு. роЗрои்род роЙрокро░ிроиீро░் ро╡ெро│ிропேро▒ுроо் роЗроЯрод்родிро▓் роЙро░ுро╡ாроХிро▒родு роЕроЯைропாро▒ு роЖро▒ு. роЪெроо்рокро░роо்рокாроХ்роХроо் роПро░ிропிро▓் родிро▒роХ்роХрок்рокроЯுроо் роиீро░ாройродு роЕроЯைропாро▒்ро▒ிро▓் роЗрогைрои்родு роорогрок்рокாроХ்роХроо் родொроЯроЩ்роХி родிро░ுроиீро░்рооро▓ை, роирои்родроо்рокாроХ்роХроо், роИроХ்роХாроЯ்роЯுродாроЩ்роХро▓், роЪைродாрок்рокேроЯ்роЯை, роХோроЯ்роЯூро░் ро╡ро┤ிропாроХ роЕроЯைропாро▒ு рооுроХрод்родுро╡ாро░род்родிро▓் роЗрогைрои்родு ро╡роЩ்роХроХ் роХроЯро▓ிро▓் роХро▓роХ்роХிро▒родு.

роЪெрой்ройை роХுроЯிроиீро░் ро╡ாро░ிропрод்родிрой் роХроЯ்роЯுрок்рокாроЯ்роЯிро▓் роЙро│்ро│ роПро░ிроХро│ிро▓ேропே рооிроХрок் рокெро░ிропродு роЪெроо்рокро░роо்рокாроХ்роХроо் роПро░ி. роПро░ிропிрой் роХொро│்ро│ро╡ு 3,645 рооிро▓்ро▓ிропрой் роХрой роЕроЯி. роЕродாро╡родு, родрооிро┤்роиாроЯ்роЯிро▓் роЙро│்ро│ роироЯுрод்родро░ роЕрогைроХро│ுроХ்роХு роЗрогைропாрой роХொро│்ро│ро│ро╡ு роХொрог்роЯ роПро░ி.


рокро░ுро╡ роХாро▓род்родிро▓் рокெроп்род роХройрооро┤ைропாро▓் роЗрои்род роПро░ி роЕродрой் рооுро┤ுроХொро│்ро│ро│ро╡ு 3645 рооிро▓்ро▓ிропрой் роХрой роЕроЯிропை роОроЯ்роЯிропродு. рокாродுроХாрок்рокு роХро░ுродி роХроЯрои்род 16-рои்родேродி рооுродро▓் роиீро░் ро╡ெро│ிропேро▒்ро▒рок்рокроЯ்роЯு ро╡ро░ுроХிро▒родு

роЪெрой்ройைропிрой் ро╡ро░ро▓ாро▒ு роХாрогாрод ро╡ெро│்ро│род்родுроХ்роХு роЪெроо்рокро░роо்рокாроХ்роХроо் роПро░ிропிро▓் роЕродிроХ роЕро│ро╡ு роиீро░் ро╡ெро│ிропேро▒்ро▒рок்рокроЯ்роЯродு роороЯ்роЯுрооே роХாро░рогрооா? роЗродிро▓் роЕро░роЪு роЙро░ிроп роЕроХ்роХро▒ை роХாроЯ்роЯрок்рокроЯро╡ிро▓்ро▓ைропா? роОрой рокро▓ роХேро│்ро╡ிроХро│் рооுрой்ро╡ைроХ்роХрок்рокроЯுроХிрой்ро▒рой.

роХேро│்ро╡ிроХро│ுроХ்роХு родроЩ்роХро│родு рокெропро░ைроЪ் роЪொро▓்ро▓ாрооро▓் роЕройைропிро▓் рокрогிропாро▒்ро▒ுроо் роКро┤ிропро░்роХро│் родро░ுроо் рокродிро▓் роЗродுродாрой்.,“роЕроЯைрооро┤ைроХ் роХாро▓род்родுро▓ ро╡ро░род்родுроХ்роХு роПрод்род рооாродிро░ி родрог்рогிропை ро╡ெро│ிропேрод்родро▓ைрой்ройா, роПро░ிропே роЙроЯைроЮ்роЪிро░ுроо். роЕродே роиேро░род்родுро▓, роЗродு роЪெрой்ройைропோроЯ роХுроЯிроиீро░்роЩ்роХிро▒род рооройроЪுро▓ ро╡ெроЪ்роЪுроХ்роХிроЯ்роЯு роЪெропро▓்рокроЯрогுроо். рооொрод்родрооா родிро▒рои்родுро╡ிроЯ்ро▒ рооுроЯிропாродு. роЯிроЪроо்рокро░் роТрог்рогாрои்родேродி роТро░ே роиாро│்ро▓ роороЯ்роЯுроо் 470 рооி.рооீроЯ்роЯро░் рооро┤ை рокродிро╡ாроЪ்роЪு. рооро│рооро│рой்ройு родрог்рогீро░் роПро▒ роЖро░роо்рокிроЪ்роЪிро░ுроЪ்роЪி. роЗро╡்ро╡ро│ро╡ு ро╡ேроХрооா роПро░ி роиிро░роо்рокுродுрой்ройா, роиீро░்ро╡ро░род்родு роЕрокாроп роХроЯ்роЯрод்родுроХ்роХுроо் роЕродிроХрооா роЗро░ுроХ்роХுрой்ройு роЕро░்род்родроо். роЕродройாро▓ роТро░ு роиிрооிро╖роо்роХூроЯ ро╡ீрогாроХ்роХாроо, роХродро╡рогை (ро╖роЯ்роЯро░்) ро╡ро┤ிропா родрог்рогிропை ро╡ெро│ிропேрод்родிроЯ்роЯு роЗро░ுрои்родோроо். роЕродே роиேро░род்родுро▓ родாроо்рокро░роо் роПро░ிропாро╡ுро▓ роЕродைроХ் роХாроЯ்роЯிро▓ுроо் роЕродிроХрооா рооро┤ை рокெроЮ்роЪிро░ுроХ்роХு. роПро░ிропிро▓ роЗро░ுрои்родு родிро▒рои்родுро╡ிроЯ்роЯродைро╡ிроЯ роиாро▓ு роороЯроЩ்роХு родрог்рогி рокро▓்ро╡ேро▒ு рокроХுродிропிро▓ роЗро░ுрои்родு роЕроЯைропாро▒ுроХ்роХு ро╡рои்родிро░ுроХ்роХு. роХிро┤роХ்роХு роиோроХ்роХிроЪ் роЪெро▓்ро▓роЪ் роЪெро▓்ро▓ родрог்рогீро░ிрой் роЕро│ро╡ு роЕродிроХрооாроХி, рокாродிрок்рокு роЕродிроХрооாроХிро╡ிроЯ்роЯродு.

роЗрок்рокроЯி роЪроо்рокрои்родрокроЯ்роЯ роЕродிроХாро░ிроХро│் роЪொрой்ройாро▓ுроо் роЪெроо்рокро░роо்рокாроХ்роХрод்родை роЪுро▒்ро▒ிродாрой் родро▒்рокோродைроп роЕро░роЪிропро▓் роТроЯிроХ்роХொрог்роЯிро░ுроХ்роХிро▒родு.

роЗрой்ро▒ைроп роиிро▓ро╡ро░рок்рокроЯி роЪெроо்рокро░роо்рокாроХ்роХроо் роПро░ிропிро▓் 3191 рооிро▓்ро▓ிропрой் роХройроЕроЯி роиீро░் роЗро░ுрок்рокு роЙро│்ро│родு. роПро░ிроХ்роХு 5620 роХройроЕроЯி роиீро░் ро╡рои்родு роХொрог்роЯு роЗро░ுроХ்роХிро▒родு. рокாродுроХாрок்рокு роХро░ுродி 15 ро╖роЯ்роЯро░்роХро│் рооூро▓роо் 5 роЖропிро░роо் роХройроЕроЯி роиீро░் ро╡ெро│ிропேро▒்ро▒рок்рокроЯ்роЯு ро╡ро░ுроХிро▒родு.

роЪெроо்рокро░роо்рокாроХ்роХроо் роПро░ி роОрои்род рокроХ்роХроо் роЗро░ுроХ்роХிро▒родு роОрой்рокродு родெро░ிропாро╡родро░்роХро│் роХூроЯ роЗрок்рокோродு роТро░ு роиாро│ைроХ்роХு роТро░ு рооுро▒ைропாро╡родு роПро░ிропிрой் рокெропро░ை роЙроЪ்роЪро░ிроХ்роХாрооро▓் роЗро░ுрок்рокродு роЗро▓்ро▓ை.

роЪெроо்рокро░роо்рокாроХ்роХроо் роПро░ிродро░ுроо் рокாроЯроо்родாрой் роЗрок்рокோродு рооிроХ рооுроХ்роХிропроо்.

роЕройைропிро▓் ро╡ிро┤ுрои்род роЪிро▒ு роТроЯ்роЯைропை роХைро╡ிро░ро▓ாро▓் роЕроЯைрод்родு роКро░்роХ்роХாро░ро░்роХро│் ро╡ிроЯிрои்родுро╡ро░ுроо் ро╡ро░ை роЕрок்рокроЯிропே родுாроЩ்роХிроХ்роХிроЯрои்родு роЕройைропைропுроо் роЕродு роЙроЯைрокроЯாрооро▓் роКро░ைропுроо் роХாрок்рокாро▒்ро▒ிроп роЪிро▒ுро╡ройிрой் роХродைропை рокாроЯрооாроХ рокроЯிроХ்роХாродро╡ро░்роХро│் роироо்рооிро▓் ропாро░ுроо் роЗро░ுроХ்роХрооாроЯ்роЯோроо்.

роЖроХ роЕройைроХ்роХு роТро░ு роЖрокрод்родு роОрой்ро▒ாро▓் роЕродро▒்роХாроХ роЖрогைропை роОродிро░்рокாро░்род்родு роХாрод்родிро░ாрооро▓் роЙроЯройுроХ்роХுроЯрой் рооுрой்роОроЪ்роЪро░ிроХ்роХை роироЯро╡роЯிроХ்роХை роОроЯுроХ்роХроХூроЯிроп ро╡роХைропிро▓் роЪроЯ்роЯрооுроо் роЕродிроХாро░рооுроо் родிро░ுрод்родрок்рокроЯро╡ேрог்роЯுроо்.

рооிрой்ро╡ெроЯ்роЯு роХாро░рогрооாроХ роХродро╡ройைропுроо் ро╡ேро▓ை роЪெроп்ропாрооро▓் роЪродிроЪெроп்родродு роОрой்ро▒ு ро╡ேро▒ு роХூро▒ுроХிрой்ро▒ройро░் роОрок்рокроЯி рооிрой்ро╡ெроЯ்роЯு рокிро░роЪ்ройைроХ்роХு роЪроо்рокрои்родрооிро▓்ро▓ாрооро▓் рооிрой்роЪாро░ро░ெропிро▓் родройிрод்родுро╡рооாроХ роТроЯுроХிро▒родோ роЕродு рокோро▓ роЕрогை ро╡ிро╖ропрод்родிро▓் рооிрой்ро╡ெроЯ்роЯு рокிро░роЪ்ройைропே роЗро░ுроХ்роХроХூроЯாродு роХாро░рогроо் роЗродு роороХ்роХро│ிрой் роЙропிро░் роЪроо்рокрои்родрок்рокроЯ்роЯ рокிро░роЪ்ройை роЕродро▒்роХேро▒்рок роЕройைропிрой் ро╖роЯ்роЯро░்роХро│் роПро▒்ро▒ி роЗро▒роХ்роХுро╡родро▒்роХு ро╡ро┤ிро╡роХை роХாрогрок்рокроЯро╡ேрог்роЯுроо்.

роЗродு роЪெроо்рокро░роо்рокாроХ்роХрод்родிро▒்роХு роороЯ்роЯுрооாрой рокிро░роЪ்ройை роХிроЯைропாродு роЕройைрод்родு роПро░ிроХро│ுроХ்роХுрооாрой рокிро░роЪ்ройைропுроо் роХூроЯ роЖроХро╡ே роЗрои்род рооро┤ைродрои்род рокாроЯроЩ்роХро│ை рооро▒роХ்роХாрооро▓் роЗройி ро╡ро░ுроЩ்роХாро▓род்родிро▓ாро╡родு роХроЯைрокிроЯிроХ்роХро╡ேрог்роЯுроо்.

Wednesday, 25 November 2015

Method Statement of Cathodic Protection Installation Procedure for Tank External & concrete structures !!

INSTALLATION PROCEDURE FOR TANK EXTERNAL

CONTENTS
1. INTRODUCTION .....................................................................
2. CODES & STANDARDS ......................................................... 
3. INSTALLATION AND INSPECTION METHOD ....................... 
3.1 Installation of Grid System ................................................
3.2 Spot Welding Specification ................................................
3.3 Installation of Reference Electrode ...................................
3.4 Installation of Monitoring Pipe ........................................... 
3.5 Common – Boxes, Tr/R) ...................................................... 

1. INTRODUCTION
The purpose of this procedure is to define the installation procedure and inspection method &
criterion for cathode protection system for tank bottom of  Project located in Dammam City1.
2. CODES & STANDARDS
This cathodic protection material specification specified here shall be in accordance with; but not
be limited by the following codes and standards:
•  RP0290-90 / NACE
Cathodic Protection of Reinforcing Steel in Atmospherically Exposed Concrete
Structures

3. INSTALLATION AND INSPECTION METHOD
3.1 Installation of Grid System
1) Installation of anode grid system shall start only after the execution of following civil works :
. Complete construction of the concrete ring foundation.
. Laying of a containment polyethylene flexible membrane liner.
. Laying and compaction of sand-gravel layer
. Installation of MMO Ti ribbon anode, conductor bar and reference electrode.
. Laying and compaction of a 500~700mm of clean sand layer
2) Rolling of MMO Ti ribbon anode from coils and positioning at the spacing required on approved drawing.
3) MMO Ti ribbon anode should hold in place with sand bags to keep from rising above the compacted sand.
4) The total installed MMO Ti ribbon anode length shall not be less than the total lengthon approved drawing.
5) Cut one small sample piece of each MMO Ti ribbon anode and Titanium Conductor Bar for sample connection and to adjust the timing for proper spot welding.
6) Conductor bar from coils shall be uncoiled and positioned at the spacing required.
7) Compression splice or solderless connector shall be used for connecting power feeder and cable core. And totally cover the connection point with a splice kit as per approved drawings.
8) The following inspection and tests shall be performed in the anode grid system and related accessories on approved drawings:
. Depth of the membrane liner with respect to the tank bottom
. Anode spacing
. Anode depth with respect to the tank bottom
. Anode quantity (Not less than approved total length - Refer to approved drawing)
. Conductor bar spacing
. Anode/conductor bar spot welding
. Before backfilling, Resistance shall be measured by a multi - meter. (Up to 1 ohm)
. After backfilling, Resistance shall be measured by a multi - meter. (Up to 1 ohm)
9) Visual and dimensional (Typ. ±10%) check of grid system accessories
10) The inspection will be recorded on form no. 007, 008, 009
3.2 Spot Welding Specification
1) A spot welder must be use for all welding work. Test welds between anode ribbon an
d conductor bar should be first carried out in order to produce good quality welds (i.e.,
which cannot be pulled apart by hand)
2) Welding Specification
Description Specification Remarks
Temporary generator Min. 50KVA
Spot Welder Capacity 1.5~3.5 KVA
Base Metal Conductor bar : Bare Ti, 0.9 mm
Anode : MMO coated Ti, 0.635mm
Welding Mode Single sided spot welding
Position of welding Flat
Welding time The welding time is different due to applied current. Therefore, it shall be determined after sample test as permentioned previous column.
Tip cleaning By confirmation of contamination after each spot welding with file or sand paper if
required.
Bare Metal Surface Cleaning
Surface of area to be welded shall be cleaned
3) Single Side Spot Welding
. Place conductor bar and ribbon anode on the mould which is contacted to the earth plate.
. Turn on the power switch.
. Touch “Single Side Weld Switch”.
. Make sure that the welding tip is clean and then put proper pressure at the welding point.
. Push the weld witch, and remove the tip about 1~2 second after the welding is co
mpleted.
. Nugget shall be made overlapped center in MMO ribbon anode as possible.
~ step for subsequent welding point
. After welding finish, turn off the power switch.

3.3 Installation of Reference Electrode

1) Installation of permanent reference electrode at location required on approved drawings
(prior to installation, reference electrodes to be soaked in a water container for 30 min
utes minimum)
2) Connect to the test station as per the approved drawing.
3) The following inspection and tests shall be performed for the installation of permanent reference electrode.
. Installed Electrodes shall be inspected to ensure the functional capability, their location and level is as per the detail drawing.
. The measured potential of the electrodes to standard electrode (Portable Reference
Electrode) shall be as follows:
- Ag/AgCl Permanent RE (LJ Type) vs Cu/CuSO4 Portable RE: 94 ± 50mV
- Zinc Permanent RE vs Cu/CuSO4 Portable RE: 1,116 ± 50mV
- Cu/CuSO4 Permanent RE vs Cu/CuSO4 Portable RE: 0 ± 50mv
. Check the reference cell soaked in water.
. The inspection will be recorded on form

3.4 Installation of Monitoring Pipe
1) Installation of monitoring pipe at location on approved drawing.
2) The monitoring PVC pipe shall be penetrated through PVC sleeve in the concrete ring foundation.
3) Attention to be paid to avoid sand ingress inside the pipe.
4) Any sand which can obstruct the passage of the potable electrode to be removed.
5) The monitoring pipe shall be provided with Geo textile cloth socks to avoid entry sand in the pipe.
6) Pipe connection point of monitoring pipe to be sealed by means of PVC bond.
7) Insure that portable reference electrode passes through the monitoring pipe.
8) Installation of a cable and polypropylene rope inside monitoring pipe for connection an d pulling potable electrode, in case of future measurement.
9) Check the smooth operation of passage through the monitoring pipe with a temporary electrode instead of a potable reference electrode.

3.5 Common – Boxes, Tr/R)
3.5.1 Installation of Box
1) Install the Boxes at a location on approved drawings.
2) A minimum suitable length of slack cable shall be left in the trench at points of termination/connection to above ground apparatus.
3) The following inspection shall be performed for the installation of boxes as per approved drawing.
. Shape & material check.
. Cables to, boxes will be checked for correct routing and termination.
4) The inspection result will be recorded on the attached form

3.5.2 Installation of TR/Rectifier
1) Location of TR/Rectifier shall be decided as per approved drawing.
2) Prior to installation, the foundations will be checked for level and civil clearance will be obtained.
3) Fix TR/Rectifer to base utilizing anchors and the fixing holes provide. Great care to be taken in identification of polarity of all cables ensuring they match they match the polarity of the marked terminals.
4) The installation of unit will be witnessed to ensure correct orientation alignment for cabling.
5) The following inspection and tests shall be performed for the installation of TR/Rectifier.
. Prior to removal to site the TR/Rectifier will be inspected for mechanical damage at enclosure of TR/Rectifier
. Particular attention will be paid to control panel measuring instruments and control devices.
. The installation of unit will be witnessed to ensure correct orientation and alignment for cabling.
. The winding insulation resistance will be megger tested as follow.
Using a 500-Volt megger for low Voltage transformer (up to 440 volts).
The tests will be conducted between the primary and secondary windings to
earth and between the two winding.
The value of insulating resistance shall not be less than 5M ohm.
. The inspection will be recorded on form


INSPECTION AND TEST SHEET
Reference Electrode Function Test

GRID SYSTEM CHECK LIST

1 Anode depth with respect to the tank bottom
2 Anode spacing
3 Anode line number
4 Conductor bar spacing
5 Conductor bar line number
6 Check the spot welding
7 Conductor bar and cable connection
8 No of power feed cables
9 Reference electrode depth with respect to the tankbottom
10 Installation of permanent reference electrode
11 Number of permanent reference electrode
12 Cable routing
13 Depth of the monitoring pipe with respect to the tank bottom
14 Number of monitoring pipe
15 Test for potable reference electrode passes through the monitoring pipe before backfilling

INSPECTION AND TEST SHEET
Resistance Measurement for Grid System before Backfilling

INSPECTION AND TEST SHEET
Resistance Measurement for Grid System after Backfilling


INSPECTION AND TEST SHEET (Boxes)

1 Support as per detail drawings
2 Foundation location and details correct
3 Installation as details drawing
4 Cable connection
5 Cable installed & termination complete
6 Cable identification


INSPECTION AND TEST SHEET (TR/Rectifier)

1 Equipment undamaged
2 Orientation and alignment correct
3 Accessories installed
4 Earth as per detail drawing
5 Insulation resistance
5.1 Primary winding-Earth
5.2 Secondary winding-Earth
5.3 Primary winding- Secondary winding

INSPECTION AND TEST SHEET Cabling
1 Sufficient slack
2 Buried depth
3 Backfilling
4 Cable tag as per drawing
5 Cable Trench Preparation as per Standard
6 Sand Bedding Provided as per the Standard
7 Cable Size Check




Cathodic protection installation procedure for concrete structures
Contents
1. Introduction ......................................................................
2. Codes &Standards…......................................................... 
3. Installation and Inspection Method………....................... 
3.1 Anode System ................................................................. 
3.2 Connection of Cable ....................................................... 
3.3 Installation of Steel Connections .................................. 
3.4 Installation of Reference Electrode ...............................
3.5 Common – Boxes, Tr/R, Cabling) .................................. 


1. INTRODUCTION


The purpose of this procedure is to define the installation procedure and inspection method &
The criterion for cathodic protection system for steel in concrete of   the project, located
in Jeddah.
2. CODES & STANDARDS
This cathodic protection material specification specified here shall be in accordance with; but not be limited by the following codes and standards:
• RP0290-90 / NACE
Cathodic Protection of Reinforcing Steel in Atmospherically Exposed Concrete Structures

3. INSTALLATION AND INSPECTION METHOD
3.1 Anode System
1) Rebar clips shall be pushed onto the reinforcement at designated point and tied securely with cable ties.
2) The mesh anode shall run along a line of rebar clip as per approved drawing.
3) The mesh anode shall be fixed to each rebar clip with two(2) cable ties and tensioned over its full length.
4) The end of the mesh anode should be looped and weld each other, and then the mesh The anode can be stretched by cable ties and rubber clip.
5) The conductor bar shall be positioned along a line of rebar clip that cross the mesh anode as Per approved drawing. The conductor bar shall be fixed to rebar clip with cable tie like mesh anode.
6) The mesh anode shall be spot welded to the conductor bar at every crossing point. Then
each welding point shall be secured with a cable tie.
7) The installation procedures for spot welding machine is as follows:
- Make sure the mesh anode and the conductor bar are clean and free from dust.
- Place the conductor bar underneath the section of the mesh anode.
- Welding gun insert between mesh anode and conductor bar
- Press the trigger to weld.
- The welding shall be done instantly when the trigger is pressed.
8) The rebar clip must be installed tightly to the rebar cage to reduce the possibility of meshanode displacement during the concrete pouring. In particular, it is important for the anode too be stretched tightly to avoid a node movement during the concrete pouring.
9) A discontinuity check between the anode system and the rebar shall be carried out by measuring the resistance between the anode lead cable and negative cables. Discontinuity is proven by failure of this test. If there is continuity between anode and cathode then the shortcircuit should be traced and eliminated before work proceeds. The successful elimination of the short circuit shall be demonstrated be re-measuring the continuity between anode and cathode.
10) All cable tie tails to be removed.
11) The following inspection and tests shall be performed for the anode system and related
accessories on approved drawing:
- Anode spacing
- Location of anode
- Anode quantity(Not less than approved total length- refer to approved drawing)
- Conductor bar quantity (Not less than approved total length-refer to approved drawing)
- Anode/Conductor bar welding spot weld is by making a cross and rubber hammering (1kg) one arm to shear the weld if a nugget pulls out of one of the sections-the weld is acceptable (Test sample)
- Resistance measurement before concrete pouring

• Continuity test between
(1) Anode & CB,
(2) Steel & Negative Cable
(3) Steel & Steel Signal Cable (up to 1 ohm)

• Discontinuity test between
(1) Anode & Cathode
(2) Different Zone
- Resistance measurement after concrete pouring

• Continuity test between
(1) Anode & CB
(2) Steel & Negative Cable
(3) Steel & Steel Signal Cable (up to 1 ohm)

• Discontinuity test between
(1) Anode & Cathode
(2) Different Zone
- Visual and dimensional (Typ. ±10%) check of anode system accessories
1) The inspection result will be recorded on attached forms

3.2 Connection of Cable
The connection from cable to the anode system shall be made as follows:
1) Anode lead cable of the specified rating, color and size shall be prepared in sufficient length to run from the anode lead connection to the appropriate junction box by the specified route  without a cable splice.
2) The pre-stripped copper core of the anode lead cable shall be compressed crimped to a titanium rod.
3) The assembly shall be encapsulated with a suitable, mechanically strong adhesive lined heat shrink type, which extends 50mm either side of the crimp. Care shall be taken during the application of heat shrink to ensure no damage results to the cable insulation.
4) The Titanium wire shall be positioned in the correct orientation and secured to the conductor bar.
5) The cable leading from the anode lead connection shall be securely fastened to the conductor bar and then to the reinforcement by the use of non-metallic cable ties.
6) A connection between the titanium wire and conductor bar shall be made by metallurgical welding, taking care to ensure that the process in no way damages conductor bar or the cable connection system.
7) The installation procedure for spot welding the anode lead connection to the conductor bar is as follows:
- Make sure the anode lead connection and the conductor bar are clean and free of dust
- Firmly fix the positive connection to the top of the conductor bar using 2 cable ties.
- Anode lead connection shall be placed onto the conductor bar to make a direct connection.
- Press the trigger to weld
8) The following inspection should be performed as per approved drawings :
 Check the connection of cables to boxes
 Cable identification.
9) The inspection result will be recorded on the attached form.

3.3 Installation of Steel Connections
The connection from negative cable and steel signal cable with the repair shall be made as follows:

1) Manufacturing
 A 30mm deep hole shall be drilled in one end of a 12mm diameter rebar that is 100 mm long.
 Negative cable of the specified rating, colour and size shall be prepared in sufficient length to run from the negative connection to the appropriate splice location by the Specified route.
 The pre-stripped copper core of the negative cable shall be placed inside the hole and braze welded to the rebar. Care shall be taken to ensure no damage results to the cable insulation.
 The assembled connection shall then be encapsulated with a suitable, mechanically strong, adhesive lined heat shrink tube once the connection has cooled to ambient temperature. This encapsulation shall cover 50mm of cable insulation and shall extend to the midpoint of the steel rod.
 The bare portion of the rebar shall be suitably welded to the designated steel reinforcement of the structure to be protected taking care to ensure no damage occurs to the cable or connection encapsulation.

2) Installation
 At the locations shown in general on the drawings, the reinforcement shall be thoroughly cleaned to expose the bright steel. The system negative cable shall then be connected to the reinforcing steel in the manner shown on the design drawings and as described below.
 The connection shall be positioned in the correct orientation and secured to the reinforcement as tack welding.
 The cable leading from the negative connection shall be securely fastened to the reinforcement by the use of non-metallic cable ties.
10) The following inspection should be performed as per approved drawings :
 Check the connection of cables to boxes
 Cable identification.
11) The inspection result will be recorded on the attached form.

 Installation of Reference Electrode
1) Installation of reference electrode at the location required on approved drawings. At a give n location, the reference electrode shall be placed at the level of and parallel to the reinforcing steel. All cables shall be secured to the reinforcement with cable ties, and routed to the location of the appropriate junction box as shown on the design drawing.
2) The following inspection and tests shall be performed before the installation of permanent reference electrode.
3) The measured potential of the electrodes to a standard electrode (Calomel Reference Ele  Strode) shall be as follows:
* Ref.electrodes shall be inspected to ensure its functional capability before & after concrete encapsulation.
A. Test procedure before encapsulation
- Prepare supplied Ag/AgCl ref. Electrode and calomel ref. Electrode.
- Fill a bucket with sea water
- The permanent Ag/AgCl ref. Electrode shall be at the left side of the bucket
- The calomel ref. Electrode shall be on the right side of the bucket.
- Measure potential difference between the two electrodes as shown on below diagram.
VOLTMETER (LC-4)
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Seawater
- A setting procedure for LC-4 meter carried out as follows:
a) Turn range switch to 200mV~2V range.
b) Turn function switch to DC. (Center of LC-4 meter)
c) Turn power switch to 10M position (Input Res range of the LC-4 meter). The display should turn on and within a few seconds indicates “ 000”. If “Lo bat ” appears in the display, then the 9V battery must be replaced as soon as possible.
d) Connect lead cable of Ag/AgCl ref. electrode to the center terminals (+) and lead cable
of Calomel ref. Electrode to com (-).
e) Turn range switch to a lower range if necessary to obtain a more detailed reading
(DC volt range of LC-4meter). When the display shows “1” followed by blanked digits, the input is higher than full scale. Use higher scale if available.
f) ╬ФV=±5mV maximum from the calibrated value (Portable Calomel ref. Electrode).
B. Test procedure after encapsulation
- Encapsulate max. 7~10 days before installation
- Surface of this encapsulation shall be rough ended to get a good bond with the concrete.
- After encapsulation, allow min. 2~3 days for concrete curing
- Keep in wet or moist condition until installation.
- Remove from water at least 1 hour before testing.
- Above concrete to be cured, put on a wet sponge, and then contact Calomel ref.
Electrode as show below diagram.


- A setting procedure for LC-4 meter carried out as follows:
a) Turn range switch to 200mV~ 2Vrange.
b) Turn function switch to DC. (Center of LC-4 meter)
c) Turn power switch to 10M position (Input Res range of the LC-4 meter). Display should turn on and within a few seconds indicate “ 000”. If “Lo bat ” appears in thedisplay, then the 9V battery must be replaced as soon as possible.
d) Connect lead cable of Ag/AgCl ref. electrode to center terminals (+) and lead cable of Calomel ref. Electrode to com (-).
e) Turn range switch to a lower range if necessary to obtain a more detailed reading.
(DC voltage range of LC-4 meter). When the display shows “1” followed by blanked digits, the input is higher than full scale. Use higher scale if available.
- After input res range turn to100M, measurable potential.
- After input res range turn to10M, measurable potential.
- Criteria of potential difference between 100M range and10M range is ╬ФV=2mV (Max.)
4) The inspection result will be recorded on attached form no. 001, 004, 005
5) After installation of the encapsulate RE, it shall be kept wet or moist until concrete pour.

3.5 Common – Boxes, Tr/R, Cabling)
3.5.1 Installation of Box
1) Install the Boxes at a location on approved drawings.
2) A minimum suitable length of slack cable shall be left in the trench at points of termination/connection to above ground apparatus.
3) The following inspection shall be performed for the installation of boxes as per approved drawing.
. Shape & material check.
. Cables to boxes will be checked for correct routing and termination.
4) The inspection result will be recorded on attached form no. 017.
3.5.2 Installation of TR/Rectifier
1) Location of TR/Rectifier shall be decided as per approved drawing.
2) Prior to installation, the foundations will be checked for level and civil clearance will be obtained.
3) Fix TR/Rectifer to base utilizing anchors and the fixing holes provide. Great care to be taken in identification of polarity of all cables ensuring they match, they match the polarity of the marked terminals.
4) The installation of the unit will be witnessed to ensure correct orientation alignment for cabling.
5) The following inspection and tests shall be performed for the installation of TR/Rectifier.
. Prior to removal to site the TR/Rectifier will be inspected for mechanical damage at enclosure of TR/Rectifier
. Particular attention will be paid to control panel measuring instruments and control devices.
. The installation of unit will be witnessed to ensure correct orientation and alignment for cabling.
. The winding insulation resistance will be meager tested as follows.
Using a 500-Volt Megger for Low Voltage transformer (up to 440 volts).
The tests will be conducted between the primary and secondary windings to earth and between the two winding.
The value of insulating resistance shall not be less than 5M ohm.
. The inspection will be recorded on form no. 018.


3.5.3 Cabling
All cables shall be laid in single run.
1) Buried cables should lie at a depth that will protect them from disturbance by plough or other excavations. Cable tiles or cable warning tape should be used to warn of the presence of the
cable during any subsequent excavation.
2) The cable shall then immediately be tagged with its unique ID as per approved drawing.
3) The cable lengths shall be checked against the cable schedule lengths or approved drawing in order that wastage is minimized.
4) Check the visual on form

REBAR IN CONCRETE CP SYSTEM CHECK LIST
Date:
No Description. Results Remark
Acc, Rej, N/A
1 Anode spacing
2 Location of anode
3 Anode quantity (m)
4 Conductor bar quantity
5 Number of conductor bar
6 Anode/ Conductor bar spot welding
7 Conductor bar and anode feeder cable connection
8 Number of anode feeder cables
9 Cable routing & installation
10 Resistance measurements
11 Installation of reference electrodes
12 Number and location of reference electrodes
13 Number & location of steel connections

INSPECTION AND TEST SHEET
Resistance Measurement (Before the concrete pour)
Multi-meter Used:
Structure name: Zone: Date:
Continuity between Anode & Conductorbar Compliance
Power Feeder No. Forward Reverse Pass Fail

INSPECTION AND TEST SHEET
Resistance Measurement (Before the concrete pour)
Multi-meter Used:
Structure name: Zone: Date:
Continuity between Steel & Negative Cable Compliance
Cable No. Cable No. Forward Reverse Pass Fail

INSPECTION AND TEST SHEET
Resistance Measurement (Before the concrete pour)
Multi-meter Used:
Structure name: Zone: Date:
Continuity between Steel & Steel Signal Cable Compliance
Cable No. Cable No. Forward Reverse Pass Fail
 A
INSPECTION AND TEST SHEET
Resistance Measurement (Before the concrete pour)
Multi-meter Used:
Structure name: Zone: Date:
Discontinuity between Anode to Cathode Compliance
Cable No. Cable No. Forward Reverse Pass Fail

INSPECTION AND TEST SHEET
Resistance Measurement (Before the concrete pour)

INSPECTION AND TEST SHEET
Resistance & Potential Measurement (After the concrete pour)
Multi-meter Used: Date Poured:
Structure name: Zone: Date: Time Between Anode & Steel
 Steel Potential Check (all embedded reference electrodes)
Resistance [╬й]     Potential[mV]   RE1[mV]  tp RE6[mV]

After 24Hours After 7Days After 28Days


INSPECTION AND TEST SHEET
Reference Electrode Function Test – Before Encapsulation
(For Rebar Installation)

INSPECTION AND TEST SHEET
Reference Electrode Function Test – After Encapsulation
(For Rebar Installation)


INSPECTION AND TEST SHEET (Boxes)
Box No: Date:
1 Support as per detail drawings □ Acc □ Rej
2 Foundation location and details correct □ Acc □ Rej
3 Installation as details drawing □ Acc □ Rej
4 Cable connection □ Acc □ Rej
5 Cable installed & termination complete □ Acc □ Rej
6 Cable identification □ Acc □ Rej


INSPECTION AND TEST SHEET
(TR/Rectifier)
TR/Rectifier No: Date:
No Description. AccR,e Rseujl,t sN /A Remark
1 Equipment undamaged □ Acc □ Rej
2 Orientation and alignment correct □ Acc □ Rej
3 Accessories installed □ Acc □ Rej
4 Earth as per detail drawing □ Acc □ Rej
5 Insulation resistance □ Acc □ Rej
5.1 Primary winding-Earth □ Acc □ Rej
5.2 Secondary winding-Earth □ Acc □ Rej
5.3 Primary winding- Secondary winding □ Acc □ Rej



INSPECTION AND TEST SHEET
Cabling

1 Sufficient slack □ Acc □ Rej
2 Buried depth □ Acc □ Rej
3 Backfilling □ Acc □ Rej
4 Cable tag as per drawing □ Acc □ Rej
5 Cable Trench Preparation □ Acc □ Rej
6 Sand Bedding Preparation □ Acc □ Rej

7 Warning tape or tiles □ Acc □ Rej