Saturday 27 April 2019

Construction Procedure for Instrument Calibration (MS)

TABLE OF CONTENTS

1           PURPOSE

2                        SCOPE

3                        REFERENCE, CODE & STANDARD

4                       DEFINITIONS

5                       RESPONSIBILITY AND AUTHORITY

6                        WORK PROCEDURE

7                        SAFETY

8                        QUALITY CONTROL





1       PURPOSE

The purpose of this procedure is to specify responsibilities and describe the
     steps Instrument Calibration work for United Steel Company (SULB) Project.

2          SCOPE
This method statement (M/S) shall be applied to Instrument Calibration work.

3          REFERENCE, CODE & STANDARD
3.1  Subcontractor document

3.2  Work index, symbol and detailed drawing

       3.3  Process Control And Automation Engineering Standard Specification.
            European (IEC and EN) standards shall be adopted throughout,
            unless otherwise Specified in the technical specification.

4          DEFINITIONS

                        4.1        Within this document following definitions shall apply.

                  OWNER / COMPANY        
                  CONTRACTOR                      
                  SUBCONTRACTOR      
                  PROJECT                                             



5          RESPONSIBILITY AND AUTHORITY

5.1             Site Manager

5.1.1      Site manager bears the responsibility and authority on work and quality related to this method statement.
                        51.2      Site manager approves work plans.

5.2 Construction Superintendent

5.2.1      A construction Superintendent bears the responsibility and authority to train their staff and subcontractor’s after preparing work plan according to this method statement.
5.2.2      A construction team manager takes the responsibility of all Instrument calibration work execution and preparation. 

5.3            Construction Supervisor
5.3.1      Construction Supervisor shall execute inspections and tests to secure quality materials, take adequate measures, manage results as quality records, and utilize checklist.

5.3.2      Construction supervisor bears the responsibility of Instrument Calibration according to the dimensions specified in specifications or drawings, and submits reports to the owner for approval

5.4            Quality Manager

5.4.1      Site Quality Manager is responsible for management and supervision of implementing inspection work as specified in this method statement.

5.4.2      Inspection request to QC when portions of the work are ready for inspection, as depicted in the ITP’s.

5.4.3      Responsible for preservation and maintenance of equipment at site.

6.0     INSTRUMENT CALIBRATION PROCEDURE

6.1       General Requirements

6.1.1       All instruments in a loop are calibrated, installed and inspected prior to commencing loop check in accordance with the applicable procedures and specifications.

6.1.2       Ensure that all procedures, IFC drawings, specifications, manufacturer’s instruction manual and other relevant references are available prior to commencing any activities.

6.1.3       Special tools (as applicable) and calibration equipment to be used shall bear a valid     calibration certificate. All Calibration equipments shall be initially calibrated & periodically
        checked.

6.1.4       Calibration of instruments shall be carried out in accordance with OWNER specification & procedure and Manufacturer’s Instruction Manual.

6.1.5       Particular attention shall be observed when connecting electrical power supply to electrical and electronic instruments ensuring its correct voltage, frequency, polarity and grounding.

6.1.6       Ensure that there is sufficient available qualified & competent  Instrument Calibration Technician to conduct the required instrument calibration and works.

6.1.7       All calibration shall be recorded on approved forms, signed, dated and approved by OWNER, Keep in QC Section, and incorporated in the Inspection Record Books.


6.2       Calibration Room (Workshop) Facility Requirements

6.2.1       A fully equipped instrument calibration workshop and it is intended only for calibration works which is required for instrumentation.

6.2.2       Instruments shall be calibrated in a clean, dry and air-conditioned calibration workshop. Ensure daily housekeeping before and after worked. Use appropriate vacuum cleaner and rugs to keep away dirt / foreign materials.

6.2.3       Always ensure that the calibration facilities must be orderly and systematically arranged. It should also be equipped and complete with correct electrical and pneumatic supplies. A stable supply of clean dry air must be provided for instrument air and pneumatic signal generation.

6.3        Calibration Procedure

6.3.1       Calibration for each kind of instrument shall be covered by individual Application for Inspection (AFI) form and be witnessed in accordance with Inspection Test Plan (ITP).

6.3.2       To ensure instrument operability, remove all shipping stops, check pointer travels and verify capability of instrument to measure, operate and stroke in the direction and manner required to the process application.
6.3.3       Instruments shall be checked to ensure that there is no sign of physical damage upon receipt at site prior to calibration. Any damage found shall be recorded in Non Confirmation Report (NCR) and shall be handled in accordance with NCR procedure.

6.3.4       Instruments shall be identified by tag number and checked against its corresponding data / specification sheet, ensuring particular attention that it is supplied with the correct calibration range. All name plate details shall be noted on the calibration data sheet.

6.3.5       Maintain an Instrument Calibration Log for each piece of test and calibration equipment. Valid calibration stickers must be fixed to the equipment and calibration certificates available for each item.

6.3.6       Calibration shall be done as per manufacturer’s instruction, where available. Zero, span, range adjustments, repairing and modification of instruments to be carried out only after getting permission from OWNER and added updating to data sheet specification.

6.3.7       For all instruments / gauges calibration where applicable, five (5) point testing method shall be followed, say 0%, 25%, 50%, 75% and 100%. After completion of each calibration, the instrument shall be attached with a calibration sticker bearing the date of the calibration and the initials of the witnessing parties. The following colour code stickers shall be applied:

a)      Blue        -      Pre-installation Tested (Calibrated)
b)    Yellow                 -       Pressure Tested
c)     Green      -       Cables Tested
d)    White       -       Pre-commissioned
e)     Red             -   Test Failed (written message is attached the cause of failure)               

6.3.8       This identification shall be shown on all components in the loop making all personnel aware of the current status of any installation.

6.3.9       All instruments are to be calibrated and adjusted in both rising and falling directions until accuracy is within the specified limits.

6.3.10     Fluid introduced to instrument bodies for the purpose of calibration shall be compatible with the fluidized material of the instrument and the fluid with which the instrument will be filled during normal operation.

6.3.11      Fluid shall be drained after calibration, and if necessary, blown dry with dry air or nitrogen. Any air system, permanent or temporary used must be dry and clean and shall be blown down thoroughly before using. In case permanent instrument air is not available, nitrogen cylinder as a temporary air source.

6.3.12     Seal all connections and entries to prevent moisture and dirt.

6.3.13     No test shall be carried out on electronic instruments until an adequate warm-up period has elapsed as per Vendor’s recommendation. (Ex. EJA Transmitter more than 5 minutes, YTA Transmitters more than 3 minutes).

6.3.14     A 100% calibration check is required for all transmitters prior to installation.

6.3.15     Bench test for smart transmitters shall include a configuration check out. The following configuration parameters, as a minimum, shall be set or checked against the instrument data sheet:
    a)      Software Tag
           b)      Calibration Range
           c)      Output Unit
           e)      Output Type ( FF/Hart)
           d)      Sensor Type (Temperature transmitter only)
           f)       Damping Value
           g)      Transfer Function (linear / square root)
        Note : Refer to other parameter specification in specification data sheet,
              where applicable specifically for FF parameter 

All parameters can be read and written using FF/HART communicator.

6.3.16     During configuration check full tag number shall be input into descriptor field.

6.3.17     Incoming Instrument Procedure:

a)   Instruments to be bench calibrated will be withdrawn from warehouse and stored in the Calibration shop “incoming shelves”.
b)   Calibration shop Foreman will keep a record book to monitor incoming and outgoing calibrated instrument.

c)   Instrument Engineer / Supervisor shall checked and ensure that copies of Manufacturer’s Instructions (If applicable) and Test Certificates, Instrument Data / Specification sheets are available and latest revisions ( IFC ).

d)   QC Supervisor / Calibration Foreman will prepare Calibration Sheets or incoming instruments.



6.4           Detail Calibration Method for each type of instruments

6.4.1  Flow Instruments

6.4.2  Differential Pressure Flow Type Transmitter

Prefer to be Bench calibrated

Hook up testing equipment as shown below:
                                                                              

LP
 

VENT
 

HP
 


                                                                                                 Differential Pressure Flow Type Transmitter

a)   Vent low side.

b)   When no pressure is applied to the high side, the transmitter should be 0% of output range. If it is not, adjust zero adjustment until the output indicates 0% by FF/HART communicator.

c)   Increase input signal to full range (100%) as shown in the specification sheet. The transmitter output shall be 100% of its range. If it is not, adjust span adjustment by FF/HART communicator.

d)   Recheck zero after span adjustment. Repeat until both reading are correct.

e)   Check output signal and scale readings at 0, 25, 50, 75 & 100% of the input signal instrument range (Measuring DP range) with signal rising and falling.

         f)  Corresponding mA or FF output signals is as follows:
 Square-root extraction from transmitter is usually 0%, 25%, 50%, 75%, 100%.             Using FF/HART communicator to enter the tag number/ scale range (LRV, URV)
            Damping, /Display range. Refer to other parameter specification in specification
            data sheet ,where applicable specifically for FF type.

g)   Every output reading shall be within error limit specified by manufacturer. If it is not, adjust linearity adjustment and repeat steps c) thru f) until output reading corresponds with input signal within acceptable error limit. FF/HART communicator will be utilized for adjustment.

h)   If the instrument is equipped with high/low range limit mechanism, adjust it to meet proper
    requirements. After the initial calibration test, the high and low pressure sides of the
    meter element shall be subject, in turn, to a static pressure equal to the
    maximum expected working pressure. The calibration test shall then be repeated to
    ensure that the results are unaffected by the static pressure loading (Refer to spec.
    for the static pressure test).

i)    After the tests have been completed, the instrument shall be identified with a colour sticker.

j)    Test results / readings will be filed and recorded on applicable calibration form including
    vendor specific requirement/information.
                       



6.4.3    Vortex Flow Meter

Hook up testing equipment as shown below:                                                            
                               Vortex Flow Transmitter

a)   Visual check and smart transmitter configuration check shall be performed.

b)   Check the tag number, Scale range (LRV, URV),Units and damping ect.
   Note : Refer to other parameter specification in specification data sheet ,

c)   FF/Hart communicator should be used for configuration check.

d)   After the tests have been completed, the instrument shall be identified with a colour sticker.

f)      Test results / readings will be filed and recorded on applicable calibration form including
  vendor specific requirement/information.


6.4.4   Ultrasonic Flow Meter

            Hook up testing equipment as shown below:  
 

Ultrasonic flow meters

a)   Visual check of transmitter configuration shall be performed.

b)   Check the tag number, Scale range (LRV, URV),Units and damping ect.
   Note : Refer to other parameter specification data sheet ,

c)   FF/Hart communicator should be used for configuration check.

d)   After the tests have been completed, the instrument shall be identified with a colour sticker.

e)   Test results / readings will be filed and recorded on applicable calibration form including
    vendor specific requirement/information.


6.5         Pressure Instruments

6.5.1      Pressure Transmitter


Prefer to be Bench calibrated
Hook up testing equipment as shown below:                                           
                                   Pressure Transmitter
         Note : Refer to other parameter in specification data sheet

a)     When no pressure is applied to the instrument, the output of transmitter should be 0% of its range. If it is not, adjust zero adjustment until the output indicates 0% of its range by FF/HART Communicator.

b)    Increase input signal to full range (100%) as shown in the specification sheet. The transmitter output should be 100% of its range. If is not, adjust the span by FF/HART communicator.

c)     Recheck zero after span adjustment. Repeat until both reading are correct.

d)    Check output signal and/or scale readings at 0, 25, 50, 75 & 100% of the instrument range with signal rising and falling.

e)     Every output reading shall be within error limit specified by manufacturer. If it is not, adjust linearity adjustment and repeat steps a) to d) until output reading corresponds with input signal within acceptable error limit.

f)     After the tests have been completed, the instrument shall be identified with a colour sticker.

g)    Test results / readings will be filed and recorded on applicable calibration form including vendor specific requirement/information.

6.5.2   Differential Pressure Transmitter

              Prefer to be Bench Calibrated

              Hook up testing equipment as shown below:


VENT
 

LP
 

HP
 
                                                         Differential Pressure Type Transmitter
a)     Vent low side.

b)    When no pressure is applied to the high side, the transmitter should be 0% of output range. If it is not, adjust zero adjustment until the output indicates 0% by FF/HART communicator.

c)     Increase input signal to full range (100%) as shown in the specification sheet. The transmitter output shall be 100% of its range. If it is not, adjust span adjustment by FF/HART communicator.

d)    Recheck zero after span adjustment. Repeat until both reading are correct.

e)     Check output signal and/or scale readings at 0, 25, 50, 75 & 100% of the instrument input signal range (Measuring DP range ) with signal rising and falling.

f)     Every output reading shall be within error limit specified by manufacturer. If it is not, adjust linearity adjustment and repeat steps c) to f) until output reading corresponds with input signal within acceptable error limit. FF/HART communicator will be utilized for adjustment.

g)    If the instrument is equipped with high/low range limit mechanism, adjust it to meet proper requirements. After the initial calibration test, the high and low pressure sides of the meter element shall be subject, in turn, to a static pressure equal to the maximum expected working pressure. The calibration test shall then be repeated to ensure that the results are unaffected by the static pressure loading.

h)     After the tests have been completed, the instrument shall be identified with a
                 colour sticker.

i)      Test results / readings will be filed and recorded on applicable calibration form
    including vendor Specific requirement/information..

6.5.3    Pressure & Differential Pressure Gauges

a)         Pressure and Differential gauges shall be checked by means of Hydraulic Gauge Comparator. This is a means of testing a gauge against a Standard pressure gauge.

b)        The gauge Comparator is firmly fixed to a bench. A test gauge with range comparable to the gauge under test is fitted to one branch of comparator. The gauge to be tested is fitted to the other branch and the hand pump on comparator in order to check the gauge readings against the test gauge. Reading shall be checked for pressures corresponding to 0, 25, 50, 75 and 100% of the range of the gauge under test. Actual gauge reading shall be noted for both rising and falling.

c)         Test gauges shall have an accuracy of or better than 0.25% of full scale and shall be periodically checked for accuracy against a dead-weight tester.

d)        Low side on differential pressure gauge must be vented to atmosphere.

e)         After the initial calibration test, the high & low-pressure sides of the PDI shall be subjected in turn to a static pressure equal to the maximum expected working pressure. The calibration test shall then repeated to ensure that the results are unaffected by static pressure loading.


f)         After the tests have been completed, the instrument shall be identified with a colour sticker.

g)        Test results / readings will be filed and recorded on applicable calibration form including vendor specific requirement/information.

6.6    Level Instruments

6.6.1   Differential Pressure Type Level Transmitter

               Prefer to be Bench calibrated.
               Hook up testing equipment as shown below

VENT
 

LP
 

HP
 


Differential Pressure Type Level Transmitter

Note: Hook up Testing Procedural Step: (Refer to Differential Pressure Type Transmitter on the above Fig 10.4.2.4)


6.6.2   Level Switch

           Support the level switch on a test stand vertically

           Hook up testing equipment as shown below:
                       

VIBRATION TYPE
 
 



                                                             Level Switch

          Vibration Type:
a)          Check switching action with ohmmeter (multimeter) while simulating level condition. Actual operating fluid preferred as a testing fluid, if the fluid available, similar characteristic (specific gravity or conductivity) fluid should be used.

b)         Marked switching level on level switch so that mark can be used as a reference during field installation.

c)          Test results / readings will be filed & recorded on applicable calibration form.

6.7     Temperature Instruments

6.7.1   Thermocouple Type Temperature Transmitter

        Prefer to be Bench calibrated.
Determine mV value at 0, 25, 50, 75 & 100% of temperature range from temperature conversion table.
        
Hook up testing equipment as shown below:



                                Thermocouple Type Temperature transmitter

           Types of Thermocouple: K, T, J, E, R, S,…ect.
                                   
a)          If the transmitter is equipped with type and/or range changing jumpers or switches,
put them on proper position.

b)      Measure ambient temperature and determine mV value from the conversion table.

c)      Calculate calibration value at each calibration point using the formula below:
mVcal = mVoper. – mVamb.
where:
mVcal = millivolt value of calibration
mVoper = millivolt value of operating temperature
mVamb = millivolt value of ambient temperature

d)      Hook Simulate 0% of calibration signal and check output. The output should be 0% of its range. If it is not, adjust zero by FF/HART communicator until correct value is obtained.

f)       Simulate 100% of calibration signal and check output. Adjust span by FF/HART communicator when error is found.

g)      Recheck zero after span adjustment and repeat step d) to f) until both are correct.

h)      Check output at 0, 25, 50, 75 and 100% of input range with signal rising and falling. Every output reading shall be within error limit. If it is not, adjust linearity adjustment and repeat steps d) to f) until every output reading correspond with input signal within acceptable error limit.

i)       Ambient temperature effect is to be checked, change ambient temperature of the instrument and check output change.

j)       If the instrument is equipped with burnout option, check this function by opening the input terminal and check output changing. When improper burnout action is observed, correct it by changing jumper or switching in accordance with the manufacturer’s instruction.

k)      After the tests have been completed, the instrument shall be identified with a colour sticker.

l)       Test results / readings will be filed and recorded on applicable calibration form.

6.7.2          RTD Type Temperature Transmitter

        Prefer to be Bench calibrated.

Determine RTD (Resistance Temperature Detector) type and operating conversion table.
           
Determine resistance value at 0, 25, 50, 75 & 100% of input range from temperature conversion table.
           
Hook up testing equipment as follows:


                                                   RTD Type Temperature Transmitter
a)      Simulate 0% of input signal by adjusting decade resistance box and check output. Adjust zero by FF/HART communicator until 0% of output is obtained.

b)      Increase input signal up to 100% of its range and check output. The output shall be 100% of its range. If it is not, adjust span by FF/HART communicator.

c)      Recheck zero after span adjustment and repeat until both are correct.

d)      Check output at 0, 25, 50, 75 and 100% of input range with signal rising and falling. Every output reading shall be within error limit. If it is not, adjust linearity adjustment and repeat steps a) to f) until every output reading correspond with input signal within acceptable error limit.

e)      After the tests have been completed, the instrument shall be identified with a colour sticker.

f)       Test results / readings will be filed and recorded on applicable calibration form.


6.7.3     Resistance Temperature Detector

a)      Sheath shall be removed from the thermowell and checked for damage.

b)      Resistance between terminals shall be measured and recorded. Measured resistance value shall be compared with the value obtained from the conversion charts correspondent to ambient temperature. If accuracy is within the required limit, it is acceptable.
c)      Resistance between terminals and sheath to be checked. If sheath and terminals are isolated, it is acceptable.

d)      After testing, sheath shall be replaced in their thermowells, it is important to ensure that the sheath is “bottomed” in the thermowell.

e)      Test results / readings will be filed and recorded on applicable calibration form.

6.7.4    Thermocouple Element

a)      Sheath shall be removed from the thermowell and checked for damage.

b)      Continuity between terminals shall be checked. If continuity is confirmed, it is acceptable.

c)      After testing, sheath shall be replaced in their thermowells, it is important to ensure that the sheath tip is “bottomed” in the thermowell.

d)      Test results / readings will be filed and recorded on applicable calibration Form.


6.8.        CONVERTER

6.8.1      Current to Air Converter (I/P)

          Hook up testing equipment as shown below:



 






                                                      
                mA / FF Signal

                                                                        I/P Converter
a)     Inject 0% of input signal and check output. Adjust zero when error found.

b)    Inject 100% of input signal and check output. Adjust span when the output deviates more than the error limit from 100% of its range.

c)     Recheck zero after span adjustment and repeat steps a) to c) until both are correct.

d)    Simulate input signal 0, 25. 50, 75 and 100% and check output (0.2kg/cm sq., 0.4kg/cm sq., 0.6kg/cm sq., 0.8kg/cm sq. and 1.0kg/cm sq.) with input rising and falling. Every output reading shall be within error limit. If it is not, adjust linearity and repeat a) to d) until desired input-output is obtained.

e)     After the tests have been completed, the instrument shall be identified with a colour sticker.

f)     Test results / readings will be filed and recorded on applicable calibration Form.

6.9         Control Valve

6.9.1          General

a)      Calibration test will be carried out in the instrument workshop for 4” to 6” or smaller valves. For large size valves calibration will be done in site, after the valve has been installed in the line. Test should not be carried out until the valves in its final operating state, ex., after line flushing operations and hydrostatic tests have been completed.

b)      Hydrostatic testing and line flushing should be carried out with the valve removed.

c)      Check that the valve and data plate agree with the control valve specification.

6.9.2         Diaphragm actuator spring adjustment (Bench Set).

a)     The diaphragm actuator shall be checked thru the following items :
-   Size and type
-   Stroke and range
-   Spring range

b)    Adjust pneumatic signal so that the valve close slowly, and stop when the valve fully closed.

c)     Read the pneumatic signal value and compare it with the actuator range. If the difference is greater than 2%, adjust spring adjusting nut and repeat steps c) to d) until the desired value is obtained. If the desired value cannot be obtain with spring adjustment, change stem length by adjusting connector assembly and repeat steps c) to d).

d)    Adjust pneumatic signal so that the valve open slowly, and stop when the valve is fully opened.

e)     Read the pneumatic signal value and compare it with the actuator range. If the difference is greater than 15%, change spring and recheck closing and opening.

f)     Adjust position indicator scale so that the indication works correctly.

g)    Inject pneumatic signal 0, 25, 50, 75 and 100% of its range and read valve position with signal rising and falling.

h)     Speed of stroking time from full open to full close is to be checked, if required.

6.9.3         Other Type Actuator

a)     The actuators other than diaphragm type shall be tested for stroking and failure action in  
  accordance with manufacturer's instructions. In addition the following items shall
  be checked before the stroke check (positioner calibration).

                      A. Piston Type Actuator
 -  Size and type
 -  Stroke range
 -  Leakage

b)    Control valves having leakage class V and VII (TSO), leakage testing shall
   be performed. A test ring must be fabricated comprising a blind flange on the
   valve outlet fitted with a 6mm bleed pipe and a suitably rated isolation valve from
   the center of the flange. The open end of the bleed pipe shall be immersed
           in a container of water so that the discharge bubbles can be observed. The valve inlet shall be connected to a source of pressure equal to the valve shut-off pressure. The specified signal corresponding to the valve closed position under normal operating conditions shall be applied to the valve actuator and if necessary adjustments made to the valve until the leakage bubble rate is within the specified tolerance (Specify        standard to be followed per project spec).



6.10          Positioner (Stroke check)

a)        After checking the valve stroke without the positioner shall be checked.

b)        Determine signal range and characteristic curve through full stroke of the valve. Before calibration characteristic curve shall be provided. Select proper travel character cam if provided.

c)        Connect power supply and/or air supply to the positioner and actuator.

d)        Connect proper input signal source (4mA to 20mA or 24VDC) to the positioner.

e)        Adjust input signal so that the valve open slowly, and stop when the valve is fully closed.

f)         Read the input signal and adjust zero adjustment when error found. Repeat step e) and f) until valve corresponds with closing signal within error limit.

g)        Adjust input signal so that the valve open slowly, and stop when the valve fully opened.

h)        Read the input signal and adjust zero adjustment when error found. Repeat step g) and h) until the valve corresponds with closing and opening signal within error limit.

i)         Inject 0, 25, 50, 75 and 100% of its range and read valve position with signal rising and falling. Action of the positioner shall be checked (direct or reverse).

j)         Analyze the stroke characteristic curve and figure out the reproducibility, which include dead band and hysteresis.

k)        If the character of the reproducibility are not acceptable, check feed back cam style and / or mechanical condition of all moving parts and correct deficiency if exist. Repeat step j) and k)

l)         Mechanical stops shall be checked as per data sheet.


6.11            Valve Action on Supply Failure

a)       The action of the valve on supply failure shall be checked with appropriate method.

b)       If the control valve is equipped with special accessories for the action of supply failure. The functional check and / or calibration shall be executed.

c)       Volume tank and lock up valves operability will also be checked.

d)       After the tests have been completed, the instrument shall be identified with a colour sticker.

e)       Test results / readings will be filed and recorded on applicable calibration form.

6.12      Limit Switches / Proximity sensor

6.12.1    The function of the limit switches / Proximity sensor shall be checked using a continuity test
          set, for correctness of setting and operation.

6.12.2   On motorized valves, care shall be taken to check the setting of limit switches before putting power on the actuator and the actuator manually placed at mid-travel prior to attempting to stroke the valve for the first time. Reference manufacturer’s instructions.

6.12.3    After the tests have been completed, the instrument shall be identified with a colour sticker.

6.12.3    Test results / readings will be filed and recorded on applicable calibration form.

6.13   Solenoid Valves

6.13.1     Connect an appropriate power supply via a switch.

6.13.2     Connect an air supply to the appropriate port or ports.

6.13.3     Check the operation of the valve by operating the switch and observing correct change over action.

6.13.4     Check the tightness of shut-off by connecting a flexible tube to the outlet ports or port an immersing the free end in the water to ensure that the valve closure is bubble-tight at the stated design pressure.

6.13.5     Check where applicable, electrical & manual reset, override and time delay features as called for on the valve specification.

6.13.6     Check that the coil resistance is correct to the specification.

6.13.7     After the test had been completed, the instrument shall be identified with a colour sticker.

6.13.8     Test results / readings will be filed and recorded on applicable calibration form.

6.14.   Flow Elements

6.14.1     Flow elements e.g. orifice plates, vortex, etc. shall not be installed until the flushing has been completed.

6.14.2     Flow elements such as vortex meters, magnetic flow meters, etc., which are not usually tested in the field shall be checked at the workshop or for its manufacturer’s test certificate.

6.14.3     Before installation, the flow element should be checked to ensure that the data and material specification stamped on the data plate or tab handle is the same as the specification sheet.

6.14.4     Orifice plate should be examined for flatness, bore siize and other dimensions against
        Vendor appproved drawings and to ensure that they are undamaged. Do not damage
        orifice edge. The bore shall be checked with Vernier caliper. Flow direction to be also    verified prior to on line installation.
6.14.5     Venturi system shall be checked against specification for bore diameter, length and throat diameter.

6.14.6     Test results / readings will be filed and recorded on applicable calibration form.

6.15   Analyzers (Conductivity meter/ PH meter)

        Analyzers shall check out by Vendor’s representative with the assistance of subcontractor
        technicians based on vendor approved procedure or SAT where applicable.

7      SAFETY

7.1.1     To ensure best practice HSE control is being implemented throughout all Instrumentation work, Contractor Instrument Supervisors and HSE Supervisor with Sub contractors Instrumentation Supervisors and HSE Supervisor shall carry out inspections prior to Work commencing and at regular intervals during the activities.

7.1.2       Persons working at height (above 1.8 meters) shall be protected from falling by the installation of safe access/ egress and working platforms.

7.1.3       Persons involved in Instrument calibration work shall be provided with and use the necessary PPE and as a standard each person shall wear a Safety Helmet and Safety footwear. The requirement for additional PPE shall be identified in the Risk Assessment and may include the use of the following:

7.1.4       Eye protection.
7.1.5        Hand Protection.
7.1.6        Dust masks.
7.1.7        Reflective jackets if working in the vicinity of moving traffic.
7.1.8        Any other necessary PPE

Note: - The issue and use of PPE is the final step in protecting people and must not be see as the only safety control method. Risks must be reduced to the smallest amount possible and the PPE is the back up equipment.

8          QUALITY CONTROL
8.1         ITP is a document submitted to the owner or owner’s representative formulated in an orderly manner by the construction supervisor or site quality manager to record main working processes for tests and quality inspections, and to enable the owner or owner’s representative to assign inspection points.
     
     8.2         Witness Point
8.2.1                Point where permission to the next level is granted without Owner’s agreement.

     8.3             Hold Point
8.3.1      Point where further progress is not allowed without Owner’s written permission

     8.4         Inspector

8.4.1      Person that inspects whether processes quality of materials or specifications are consistent with prescribed or desired requisites.

No comments:

Post a Comment