Method of Statement For Installation of HVAC Equipment.


TABLE OF CONTENTS


1.        Scope of Work………………………………………………………………………Page No
2.        Reference…………………………………………………………………………...Page No
3         Responsibilities.....................................................................................................Page No
4.        Control Measures………..………………………………………………..….....Page No                
5.        Sequence of Activities……………………………………………………………….Page No
6.       Attachment…………………………………………………………………………...Page No
  
            * JSA (Job Safety Analysis)
            * SATIP
            * SAIC

           
             



1.               Scope of Work


1.1  This method statement explains the installation of HVAC units (AHU, ACCU & Ventilation Fan), including shifting the equipments and accessories at required location, assembling and installation of equipments.

2.            Reference Documents


2.1  Approved Drawings

2.2  Manufacturer’s Catalogues, Vendor Drawing
2.3   General Specifications for HVAC System
                                     

3.            Responsibilities


3.1  Mechanical / HVAC Engineer
    
·         He shall be overall responsible for the complete activity including, but not  limited to:

3.1.1 Assigning workman crew
3.1.2 Sequence of activities to be carried out for the work as per this Method
         Statement.
3.1.3 Stage inspection & surveillance
3.1.4 Notification to client engineer for inspection and daily commissioning activities.
3.1.5 Provide day to day guidance and delegate works as necessary.
3.1.6 Ensure that the equipment and tools required for carrying out the test are
         available, maintained and  used in safe manner.
3.1.7 Produce all necessary records for the confirmation of testing works completed
         and pass to QC inspector as required.

3.2 Mechanical/HVAC Supervisor

·         He shall be overall responsible for the activity including, but not limited to:

3.2.1      Assigning worksman crew.
3.2.2      Sequence of activities to be carried out for the work.
3.2.3      Ensure the quality levels are maintained.
3.2.4      Ensure that the equipment and tools required for carrying out the test are
available, maintained and used in safe manner.

                        3.3  QA/QC Inspector
                             
                         3.3.1 Maintain records of quality control ckeck sheets / report formats for the site
                                  Tests and inspection.
                         3.3.2 Carry out surveillance so as to ensure that the personel are working i accor-
                                   Dance with the approved standards.
                          3.3.3 Assurances of approved methods are being used for testing and material
                           receipt inspection.
                           3.3.4 Verification of material approval and vendor certification.

4.               Control Measures

4.1  Quality Control

4.1.1      Ensure availability of latest released for construction drawings and specifications.
4.1.2      Ensure the tools/equipment used for testing & commissioning purpose is calibrated and certificates available.

4.2  Safety

4.2.1      All equipment and accessories have been certified for their capacity
And integrity.
4.2.2      All personnel are issued with Personal Protective Equipment.
4.2.3      Care should be taken while lifting loads. Proper tagline must be used
          for guiding while lifting loads.
4.2.4      Should not impose any appreciable mechanical strain on fixing of th
connection and shall not cause any harmful mechanical damage
to the equipment.
4.2.5      Transfort material in stacked condition and secure all loads adequately
before transport. In case of loading by a loader,  no one shall be
present inside the vehicle. Do not keep the truck in running condition
while loading.
4.2.6      Inspect crane and all lifting tools & tackles before use. Never overload
any equipment/tools beyond their recommended SWL. Ensure no
overhead lines abstract the equipment movements in case it  happens proper isolation permit to be obtained from responsible
project engineer.
4.2.7      No one should move under load at any circumtances. Engage only
experienced person to make lifting arrangement.
4.2.8      Select correct type of fulling/lifting equipment and do not overload the
tackles.
4.2.9      Provide hand gloves  and educate workers for safe operation.
4.2.10   Always use trolley for gas cylinder keeps vertical position.
4.2.11   Always use fire blanket barricade and keep fire extinguisher during  brazing.

5.            Sequence of Activities


5.1 Installation Procedure (AHU)
                 
                    5.1.1 Check approval of IFC drawing.
                    5.1.2 Check approval of manufacturer and model.
                    5.1.3 Check equipment visually for any physical damage.
                    5.1.4 Lift and place the AHU by using crane or forklift.
                    5.1.5 Ensure that the pedestal for the equipment as per approved
                             drawing.
                   5.1.6 Assemble the AHU as per vendor drawing.
                   5.1.7 Ensure the anti-vibration rubber pads between the foundation and
                           units are provided.
                   5.1.8 Check the level of the unit.
                   5.1.9 Check the pulley alignment and belt tension for units.
                   5.1.10 Connect the refrigerant piping in the units.
                   5.1.11 Connect drain pipe to the units and P traps will be made according to
                              manufacture standard.
                   5.1.12 Connect final duct connections to the units.
                   5.1.13 Terminate the electrical cables as per manufactures instruction.
                   5.1.14 Check related all duct works are completed, building air conditioning
                              area is completed with doors, windows and partitions fixed and area
                              is dust free, as applicable.
                   5.1.15 Carry out the pre-commissioning checks and commission the units
                              and record the data.

5.2 Installation Procedure (ACCU)

                   5.2.1 Check approval of IFC drawings.
                   5.2.2 Check approval of manufacturer and model.
                   5.2.3 Check equipment visually for physical damage.
                   5.2.4 Ensure that the pedestal for the equipment as per approved drawing.
                   5.2.5 Ensure that the free air movement is available around the units without
                            any obstruction and provision for the refrigerant piping for the units as
                            per the approved drawing.
                   5.2.6 Install the condensing unit as per drawing.
                   5.2.7 Ensure units are mounted on pedestal/platform with foundation pads.
                   5.2.8 Check the level of the equipment.
                   5.2.9 Connect the refrigerant piping and terminate electrical connection and
                            control wiring to the units as per  the electrical wiring provided on the
                            unit.
                   5.2.10 Perform pipe flushing and pressure test as described in method
                              statement for copper pipe. When finish the above activities the
                              system is ready for commissioning.
                   5.2 12 Carry out the pre-commissioning checks and commission the  units
                             and record the data.

5.3 Installation Procedure (Exhaust Fan)

                   5.3.1 Check approval for IFC drawings.
                   5.3.2 Check approval of manufacturer and model.
                   5.3.3 Check wall/slab opening as per approved drawings.
                   5.3.4 Carry out the visual inspection of fan for any physical damage.
                   5.3.5 Install the fans and tighten the nuts and bolts tightly.
                   5.3.6 Ensure fans are mounted on the floor with foundation pads.
                   5.3.7 Check the position, levels of the extract fan as per approved drawings.
                   5.3.8 Carry out the pre-commissioning checks and commission the units
                             and record the data.


5.4 Installation Procedure for (Chemical Filtration Unit)

     5.4.1. Check approval of IFC drawings.
     5.4.2 Check approval of manufacturer and model
     5.4.3 Carry out the visual inspection of the unit for any physical damage.
     5.4.4 Lift and place the CFU by using crane or forklift.
     5.4.5 Ensure that for the equipment as per approved drawing.
     5.4.6 Ensure the anti-vibration rubber pads between the foundation and
              units are provided.
     5.4.7 Check the level of the unit.
     5.4.8 Check the pulley alignment and belt tension for unit.
     5.4.9 Connect final duct connection to the units.
     5.4.10 Terminate the CFU fan electrical cables as per manufactures
                instruction.
     5.4.11 Carry out pre-commissioning check and commission the units and
                record data.
    
5.5 Installation Procedure for (Package Air Handling Unit)

     5.5.1 Check approval of IFC drawings
     5.5.2 Check approval of manufacturer and model.
     5.5.3 Check equipment visually for any physical damage.
     5.5.4 Lift & place the PACU by using crane or forklift.
     5.5.5 Ensure that the pedestal for the equipment as per approved drawing.
     5.5.6 Ensure the anti-vibration rubber pads between the foundation and units
              are provided.
     5.5.7 Ensure that the free air movement is available around the compressors
              without any obstruction.
     5.5.8 Check the level of the unit.
     5.5.9 Check the fully alignment and belt tension for units.
     5.5.10 Connect drain pipe to the unit and P traps will be made according to
                manufacturer standard.
     5.5.11 Connect final duct connection to the units.
     5.5.12 Terminate the electrical cables as per manufacturer instruction.
     5.5.13 Check related all duct works are completed, building air conditioning
                Area is completed with doors, windows and partitions fixed and area is dust
                free ass applicable.
     5.5.14 Carry out the pre-commissioning checks and commission the units and record  
                the data.
    
5.6 Installation Procedure for (DX-Fan Coil Unit)

      5.6.1 Check approval of IFC drawing.
      5.6.2 Check approval of manufacturer and model.
      5.6.3 Check the equipment visually for any physical damage.
      5.6.4 Mark the location of the unit as per the approved drawing and mark the
               location for holes. Drill the hole with appropriate drill bit and install
               appropriate threaded rod of required length.
      5.6.5 Install the unit and ensure that it’s secured while lifting and bolting to
              anchor rod. Level the unit and check it as per drawing. Check the provision
               For the drainage and ensure the free flow of drainage water.
      5.6.6. Connect final duct connections according to the approved drawing.
      5.6.7 Install the outdoor compressor unit and connect the refrigerant pipes (refer
               To 5.2).
      5.6.8 Connect drain pipe to the unit and P trap will be made according to the
               Manufacture standard.
      5.6.9 Terminate the electrical and control wiring as per approved drawing and
               Wiring diagram provided on the units respectively.
      5.6.10 Carry out the pre-commissioning checks and commission the units
                 Prior to start up.

5.7 Installation Procedure for (Split Unit)

     5.7.1 Check the approval of IFC drawing.
     5.7.2 Check the approval of manufacturer and model.
     5.7.3 Check equipment visually for any physical damage.
     5.7.4 Mark the location of the unit as per approved drawing and mark the location
              for holes. Drill the hole with appropriate drill bit and install the unit direct on
              the wall as per manufacture recommendation method.
     5.7.5 Level the unit and check it as per the drawing. Check the provision for the
              drainage and ensure the free flow of drainage water.
     5.7.6 Install the thermostat on the wall.
     5.7.7 Install the outdoor compressor unit and connect the refrigerant pipes (refer
              to 5.2)
     5.7.8 Connect drain pipe to the unit and P trap will be made according to the
              manufacture standard.
     5.7.9 Terminate the electrical and control wiring as per the approved drawing
               and wiring diagram provided on the units respectively.
     5.7.10 Carry out the pre-commissioning checks and commission the units
                prior to start up.

        6.    Attachment

·         JSA (Job Safety Analysis)
·         SATIP-K-001-01 (Centrifugal Fan)
·         SATIP-K-001-06 (Packaged Air Conditioning Unit (PACU) System)
·         SATIP-K-001-02 (Air-Handling Unit (AHU) )
·         SATIP-K-001-11 ( A/C Split System-Direct Expansion (DX) Type)
·         SAIC-K-4001 ( Exhaust and Supply Fan Receiving Inspection/Handling, Storage and Preservation Inspection)
·         SAIC-K-4004 (AHU Receiving Inspection/AHU Handling, Storage and Preservation Inspection )
·         SAIC-K-4037 (Air Cooled Condenser/Air Cooled Condenser Handling< Storage and Preservation

·         SAIC-K-4038 (Fan Coil Handling, Storage and Preservation)