TABLE OF CONTENTS
1. Purpose………………………………………………………………………………….Page No
2. Scope……………………………………………………………………………………Page No
3 References.................................................................................................................Page No
4. Material…………………………………………………………………………………Page No
5. Procedure……………………………………………………………………………..…Page No
6. Safety………………………………………………………………………………….... Page No
7. Responsibilities…………………………………………………………………………. Page No
8. Attachment………………………………………………………………………………Page No
* Gravity Test Format
* SATIP AND SAIC
* JSA (Job Safety Analysis)
1. Purpose
·
The purpose of this method
statement is to set guidelines and methodology to be followed during
installation of upvc pipes underground and above ground and testing for
drainege and sanitary line system.
2. Scope
·
This scope of this procedure is to
standardize method of statement details the method for installation and
hydrostatic gravity testing of underground drainage piping works. Hence,
execution of the work shall be done as per acceptable standards and
specifications.
3. References
·
SAES-A-004 (General
Requirements for Pressure Testing)
·
SAES-S-010 (Sanitary
Sewers)
·
SAES-S-060 (Saudi Aramco Plumbing
Code)
4.
Material
·
UPVC Pipes and Fittings, Solvent
Cement Glue
5.
Procedure
·
Storage
a.) For Material receiving, storing and handling visual and mechanical
inspection must be done. Any damage and discrepancies must be recorded and
reported.
b.) Checked and inspected material must comply with specification
requirements and shall conform with the Purchase Order.
c.) Pipe shall be given added protection when storing on a flat surface free
from sharp objects.
d.) Storing of pipe shall not be exposed on direct sunlight.
e.) Tags and appropriate marking for pipes must be installed for
identification.
·
Trench Preparation for Underground
a.) Trench excavation must be installed depending on the pipe size, type of
ground and depth required.
b.) Bedding for pipes shall be constructed by spreading and compacting. Only
approved bedding material shall be used for bedding of pipes. After pipe have
been installed, additional material be placed (if required) and compacted
equally on each side of the pipe, this shall be done in sequence practicably.
c.) Pipes are required to be bedded directly on the trench bottom, the final
excavated surface shall be trimmed and leveled to provide even bedding for the
pipeline and shall be free from all foreign matter that may damage the pipe.
When rock is encountered, the trench shall be cut at least 150 deeper than the
ground and made up with well compacted selected fill material.
·
Pipe Laying and Installation
a.) All pipe are laid with due regard to the fall and invert levels set out
in the shop drawing.
b.) Pipe requiring socket joints are required to be installed directly on a
trench bottom, on gradual/sand bed, joint holes/spaces shall be formed in the
bedding material or final excavated surface to ensure that each pipe is
smoothly and uniformly supported throughout its length.
c.) Pipe and fittings shall be examined for damage and joint surfaces and
components shall be cleaned immediately before laying.
d.) No protective cap, disc or other appliance on the end of a pipe or
fitting shall be removed permanently until the pipe or fitting which it
protects is about to be jointed.
e.) Suitable measure shall be taken to prevent soil or other material from
entering pipes and to anchor each pipe to prevent flotation or other movement
before works are complete.
·
Solvent Weld Joint
Pipe sizes 2000mm
and below are joined together by the solvent weld method. Only approved solvent
and glue shall be used. The MSDS must be attached for handling and using these
materials. A job safety analysis must be prepared for handling of this
hazardous material.
a.) Using cleaning fluid, both surfaces to be joined must be cleaned.
Surface must be free from dirt and machine release agents and softens the
surface ready for weld.
b.) The solvent cement shall applied evenly over the mating surfaces of both
pipe and socket weld.
c.) Pipe shall be inserted to the socket with a slight twisting action to
full socket depth. Removed surplus cement using cloth.
d.) Joint shall be firm enough to handle in 5 minutes.
e.) All open ends of pipe must be cover with end caps or wrapped with
polyethylene sheets to prevent entry of dust and other foreign object.
·
Backfilling
a.)
Pipe surround
After pipe laying,
Inspection and testing a further 3oomm of approved bedding material shall be
used for pipe surround, compacted with hand from all sides while tamping
lightly over the crown. The bedding material shall span the entire width of the
trench and shall be laid in not more 150mm deep layers, each layer being
compacted by hand.
b.)
Main Backfill
This is usually
compacted infill with the original trench soil over the layer of pipe surround.
Heavy mechanical rammers shall not be used until the fill has reached a
sufficient height above the top of the pipe.
c.)
Above Ground Drainage Pipes
a.) All .pipe work shall be adequately supported in such manner as to permit
free movement due to expansion, contraction and vibration or other changes in
the system.
b.) All above drainage pipes are joined using either Push-fit or solvent
method.
c.) Supporting of pipes shall be arranged as near as possible to joints and
changes in direction. For supporting of pipes, galvanized steel split clamps
shall be used.
d.) All vertical pipes (160mm dia. And below) shall supported using split
clamps screwed to the wall using threaded rods, diameters of which shall according to the clamps manufacturer recommendations.
e.) Where soil and vent pipe are suspended from the underside of the slab,
they shall be held rigid position. Based on the pipe diameters, single or
double iron supports shall be used as required.
f.) Pipe supports shall be provided at intervals as per specification and/or
BS Standard.
d.)
Hydrostatic Gravity Head Testing
a.) Water test is conducted to ensure and prove the tightness of the joints
and ensure there are no leaks in the piping system.
b.) Medium of fluid shall be potable water, well water or raw water.
c.) The pipe shall be support a water head of 1.2 m at its upper end and not
more than 2.4 m at its lower end for the period of four hours or as specified.
d.) The water shall be kept in the system or in the portion under test for
at least 30 minutes before inspection starts. While the system is under
pressure, a careful inspection shall be made on all pipes and joints. If any
leak in joints or evidence of defective pipe or fittings is revealed, the
defective pipe/fitting should be immediately replaced with new joints and
materials.
e.) Make sure that all open stub-up are properly plugged-off with test plug
and properly vented.
f.) After correction is made, the test pressure will be maintained for
minimum 30 minutes and witnessed by contractor QA/QC.
g.) Testing will be inspected by main contractor/consultant to their
satisfaction and the test results are recorded in the inspection report by
getting approval in test certificate which will maintained with the QC
documentation for records.
h.) Drain water after approval by the consultant and make sure water is
disposed and discharged in a remote location. After the testing backfilling of trench
will be allowed.
6.
Safety
·
Protection and safety shall
be in accordance with the approved Safety Procedure. All labors shall be
equipped with safety shoes, helmet, safety glass, gloves, ear protection,
protective clothing and face shield against any injuries from the work.
·
Extra care shall be taken
during cutting and shaving of pipe ends.
·
Sign board must be placed
when hydrostatic gravity test is in progress.
·
Permits shall be obtained
prior to start of job.
·
Barricade is a must when
testing.
7.
Responsibilities
·
Site
Engineer has to ensure that the site QC section is provided by the necessary
facilities and cooperation from all supervisors, foremen and laborers to enable
satisfactory inspection and verification performed by the building section.
·
The
safety manager has to ensure that all safety requirements will be enforce by
manners to prevent injury to personnel. He should provide written instruction
to established working method; explain the sequence of the operation, outline
the potential hazards at each stage and indicate precaution to be adopted.
·
The
mechanical engineer/plumbing supervisors are the solely responsible for works
being implemented are in conformance with specifications.
8.
Attachment
·
Gravity Test Format
·
SATIP and SAIC.
SATIP-S-010-01
Gravity Sanitary Sewer Pipe and Manhole.
SATIP-S-030-01 Strom Water Drainage System.
SATIP-S-060-05
Roof Drain and Drainage Pipe.
SATIP-S-060-06
Building DWV Pipe.
SATIP-S-070-01 Gravity Sanitary Sewer Pipe
and Manhole.
SATIP-S-060-02
Thermoplastic and RTR Pipe.
SAIC-S-4038
Roof Drain Installation Inspection.
SAIC-S-4039
Roof Drain Receiving and Storage.
SAIC-S-4040
Drainage System Layout.
SAIC-S-4043
Indirect Waste Piping Installation.
SAIC-S-4054
RTR & Thermoplastic Pipe Installer Qualification.
SAIC-S-4055
RTR & Thermoplastic Pipe Receiving (Pressure and Sewer Pipe).
SAIC-S-4056
RTR & Thermoplastic Pipe Handling, Storage and Preservation.
SAIC-S-4057
Assembly of Thermoplastic (PVC. UPVC, CPVC and HDPE) Piping.
SAIC-S-4060
Strom Water Drainage System Installation.
·
JSA Gravity (Job Safety
Analysis)
No comments:
Post a Comment