NO.
|
ACTIVITY
|
POTENTIAL
HAZARDS
|
RISK
RATING
|
PREVENTIVE
MEASURES
|
RESIDUAL
RISK
|
RESPONSIBLE
PERSON
|
1
|
Prepare work area and material arrangement for the job.
|
· Untrained crew
· Tools and equipment failure
· Slips, Trips and Fall
Hazards
|
M
|
· All personnel shall be
undergone for SSA Safety induction and required necessary training prior to
enter revamping areas
· All employees shall be
aware of the emergency evacuation plan and also shall be familiar that how to
react in an emergency. Location of assembly point areas and emergency number.
· Specific work permit shall
be obtained prior to start the activity.
· Before commencing job, JHA
shall be communicated to all involve person and available at worksite with
other required documents.
· All workers shall wear
appropriate P.P.E as per the recommendation of HSE department according to
the hazards.
· All tools and material
shall be in good condition and shall be color coded. Found damage shall be
mark “do not use” and shall be remove from site.
· Only skilled workers shall
perform the activity.
· All access ways shall be
properly identify and maintained in good condition
· SSA shall allocate
dedicated person to conduct regular housekeeping in each designated location.
· All tools and materials
shall be kept in approved designated storage area.
· Proper cable management
shall be implemented.
|
L
|
Task Supervisor/ PTWR
|
2
|
Setting up and connecting of test manifold, nitrogen
cylinder, hoses to to pipe system
|
· Tools are inappropriate,
defective, and fabricated
· Hoses obstructing access
ways
|
M
|
· Ensure that all hand tools
are properly inspected with current monthly color code.
· Supervisor shall ensure
that all tools are in the standard prior to its use. Fabricated tools are not
allowed to be used.
· All workers shall wear the
appropriate PPE at all times.
· Access to the work
locations shall be clear and free from any obstruction.
· Manifold must accordance in
client pressure testing standards and requirements and obtained valid testing
certificate.
· Manifold should be mark
with testing pressure capacity, indemnification number and other details
|
L
|
Task supervisor
Worker
|
3
|
Line pressurizing
|
· Loose /not properly
tightened connections
· Un-calibrated test manifold
and gauges
· Unavailability of whip lash
installed on hoses connections
· Nitrogen leak
|
M
|
· Supervisors shall ensure
that all connection is properly tightened.
· Work notification shall be
convey to all affected and responsible departments.
· All affected area will be
provided with barricade and appropriate, safe distance shall be in accordance
with LLOYDS’s Registry Standards.
· Pressurization shall be
stop immediately and pressure shall be gradually reduced to zero gauge
reading in case of pipe failure. Nitrogen cylinder valve shall also be
immediately turned off
· Pressurization shall be
immediately cancelled when a leak is detected.
· Workers shall immediately
vacate the area when leak is observed.
· Only approved and
calibrated gauges shall be used for the test. Calibration shall be done
within one month of the test and the ranges shall be 30 to 80% of the gauge’s
full range.
· There shall one pressure
gauge installed on both the manifold and system under test.
· Test manifold shall be
tested separately to 1.2 times of actual test pressure. Valid 3rd party
certificate shall be attached with the test package.
· Relief valves shall be
tested, dated, and tagged within 1 week prior the testing
· All hoses connection shall
be tight and secured by whiplash arrestor
· Rated capacity of hose
shall be more than the test pressure
· Testing crew shall obtain
required training for pressure testing.
· There shall be a person
dedicated to monitor the pressurization progress
· Holding pressure shall be
as per the test procedure approved by Client
· A person shall be assign to
operate the outlet valve of the nitrogen cylinder.
· All workforces shall be
aware on potential hazards in exposed of nitrogen such as frostbite and
displacement of oxygen amount.
|
L
|
Task supervisor
Worker
|
4
|
Leak Checking
|
· Unauthorized personnel
|
M
|
· Trained and authorized
crews only are allowed to do the leak inspection.
· Observation to be made away
from the joints. At any cost do not stand in front of the end joint.
· If any leak observed,
immediately reduce the pressure to zero.
· Reduce the pressure to
design pressure before start the leak checking
|
L
|
Task supervisor
Worker
|
5
|
Depressurizing
|
· Untimely release of
pressure
|
M
|
· Open the vent valve slowly
until the pressure was reduced.
· Coordinate with the other
worker. Give notice prior the release of pressure
· Task supervisor to ensure
no person in line of fire at vent area.
|
L
|
Task supervisor
Worker
|
Everything that happens to us, Happen for a reason, Reason that should make us even closer to Allah (Creator/God) - Education is foremost to shape a person's character in life. - Love is the oldest teaching in the world, for the history of our human existence is through love from our Creator. - Nothing can change a person but the person itself. If you want a happier life, change the way you view the world around you. Take off the negative glasses and put on the positive ones.
Saturday, 20 August 2016
JOB HAZARD OR JOB SAFETY ANALYSIS ( JHA/JSA0 ACTIVITY FOR REFRIGERANT PIPE TESTING