Functional Loop Test for HART
Temperature
Transmitter
Purpose
|
Provide instructions to the Functional Loop Check
Team that will conduct the Functional Loop Test on a Temperature Transmitter connected to an ABB 800xA DCS that uses HART device integration.
|
Scope
|
This procedure is to be used to ensure the correct
functionality of the entire loop and that all individual components have been
installed and are functioning according to the design specification. The
Functional Loop Test is to be the last test prior to turnover to the Owner.
|
Required Prerequisites
|
Prior to completing this procedure:
-
All pressure testing
requirements must be completed
-
All associated instrument and
electrical wiring must be checked for proper continuity, grounding, labelling,
and terminations
-
All A and B punch
list items associated with this loop must be cleared
-
Physical installation has
been inspected and signed off by Owner
-
Place a wrap of yellow tape
on the transmitter to indicate the steps above have been completed
-
Loops are powered up by Owner
Process Automation
-
Owner Process Automation has
established communication with the instrument and completed configuration of
the DCS and check of instrument settings
|
Functional
Loop Check Team
|
Each team will consist of 2 qualified Excel
Instrument Technicians and 1 Owner operations person.
|
EH&S
|
Normal site safe work and permitting practices
apply.
|
Special tools
|
-
HART communicator with up to
date DDLs for the instruments being tested
|
References
|
Loop folder
|
Executed By
|
Action
|
Inside Person
|
Positively identify the termination point in the
ICJB and standby to provide support as needed.
|
Outside Person
|
Positively identify the instrument in the field and connect
the communicator. Monitor the communicator during power-up to ensure there
are no faults detected.
|
DCS Operator
|
Verify that the instrument location on graphics
matches the PID.
Pull up the face plate for the loop being tested on
the operator workstation.
|
Outside Person
|
Refer to the instrument index for the proper FAIL
LOW value. Make any needed changes so that the transmitter settings match the
index. Using the communicator, simulate the failure current output. (3.5mA)
Note: Typically the desired value
is ≤3.6mA per NAMUR NE43.
|
DCS Operator
|
Verify that the instrument failure alarm has been
activated.
|
Outside Person
|
Refer to the instrument index for the HIGH/LOW
saturation values. Using the communicator, simulate both high and
low saturation current outputs.
Note: Typically the values
are 3.8mA and 20.5mA per NAMUR NE43
|
DCS Operator
|
Verify that the instrument failure alarm has NOT been activated when input
is saturated high or low.
|
Outside Person
|
Check for proper output with no flow (4mA). Simulate
the output by HART communicator as 25%, 50%, 75% and 100% .
|
DCS Operator
|
Verify DCS reading correctly responds to the simulated
values being applied.
Note: This is not a calibration. It is only to
confirm that the transmitter has not been damaged and is responding as
expected.
|
Outside Person
|
Disconnect the HART
communicator. Ensure that all covers are properly installed to prevent water
ingress.
|
Inside Person
|
Document the results of the test. If the loop did
not pass the test, document the symptoms for the Advanced Trouble Shooting
Team.
|
Outside Person
|
-
If the loop passed, place a
wrap of blue tape on the transmitter.
-
If the loop did not pass,
place a wrap of red tape on the transmitter.
|
Functional Loop Test for HART Pressure Transmitter
Purpose
|
Provide instructions to the Functional Loop Check
Team that will conduct the Functional Loop Test on a pressure transmitter
connected to an ABB 800xA DCS that uses HART device integration.
|
Scope
|
This procedure is to be used to ensure the correct
functionality of the entire loop and that all individual components have been
installed and are functioning according to the design specification. The
Functional Loop Test is to be the last test prior to turnover to the Owner.
|
Required Prerequisites
|
Prior to completing this procedure:
-
All pressure testing
requirements must be completed
-
All associated instrument and
electrical wiring must be checked for proper continuity, grounding, labelling,
and terminations
-
All category 1 and 2 punch
list items associated with this loop must be cleared
-
Physical installation has
been inspected and signed off by Owner
-
Place a wrap of yellow tape
on the transmitter to indicate the steps above have been completed
-
Loops are powered up by Owner
Process Automation
-
Owner Process Automation has
established communication with the instrument and completed configuration of
the DCS and check of instrument settings
|
Functional
Loop Check Team
|
Each team will consist of 2 qualified Excel
Instrument Technicians and 1 Owner operations person.
|
EH&S
|
Normal site safe work and permitting practices
apply.
|
Special tools
|
-
HART communicator with up to
date DDLs for the instruments being tested
-
Hand pump (pressure/vacuum)
|
References
|
Loop folder
|
Executed By
|
Action
|
Inside Person
|
Positively identify the termination point in the
ICJB and standby to provide support as needed.
|
Outside Person
|
Positively identify the instrument in the field and connect
the communicator. Monitor the communicator during power-up to ensure there
are no faults detected.
|
DCS Operator
|
Verify that the instrument location on graphics
matches the PID.
Pull up the face plate for the loop being tested on
the operator workstation.
|
Outside Person
|
Refer to the instrument index for the FAIL LOW value
(typically 3.6mA). Using the communicator, simulate the failure current
output.
|
DCS Operator
|
Verify that the instrument failure alarm has been
activated.
|
Outside Person
|
Refer to the instrument index for the HIGH/LOW
saturation values. Typically 20.5mA/3.8mA.Using the communicator, simulate
both high and low saturation current outputs.
|
DCS Operator
|
Verify that the instrument failure alarm is NOT been activated when input
is saturated high or low.
|
Outside Person
|
Check for proper output with transmitter referenced
to atmosphere. If the lower range is a
negative value, apply vacuum that correspond to 0%. Gradually increase the
pressure to the upper range value and then slowly vent off the pressure.
|
DCS Operator
|
Verify DCS reading correctly responds to the
pressure values being applied.
Note: This is not a calibration. It is only to
confirm that the transmitter has not been damaged and is responding as
expected.
|
Outside Person
|
Reinstall any impulse connections and ports that may
have been removed. Ensure that all covers are properly installed to prevent
water ingress.
|
Inside Person
|
Document the results of the test. If the loop did
not pass the test, document the symptoms for the Advanced Trouble Shooting
Team.
|
Outside Person
|
-
If the loop passed, place a
wrap of blue tape on the transmitter.
-
If the loop did not pass,
place a wrap of red tape on the transmitter.
|
Functional Loop Test for HART
pH,ORP,Conductivity
meter
Purpose
|
Provide instructions to the Functional Loop Check
Team that will conduct the Functional Loop Test on a pH, ORP and Conductivity meter connected to an ABB 800xA DCS that uses HART device integration.
|
Scope
|
This procedure is to be used to ensure the correct
functionality of the entire loop and that all individual components have been
installed and are functioning according to the design specification. The
Functional Loop Test is to be the last test prior to turnover to the Owner.
|
Required Prerequisites
|
Prior to completing this procedure:
-
All pressure testing
requirements must be completed
-
All associated instrument and
electrical wiring must be checked for proper continuity, grounding, labelling,
and terminations
-
All A and B punch
list items associated with this loop must be cleared
-
Physical installation has
been inspected and signed off by Owner
-
Place a wrap of yellow tape
on the transmitter to indicate the steps above have been completed
-
Loops are powered up by Owner
Process Automation
-
Owner Process Automation has
established communication with the instrument and completed configuration of
the DCS and check of instrument settings
|
Functional
Loop Check Team
|
Each team will consist of 2 qualified Excel
Instrument Technicians and 1 Owner operations person.
|
EH&S
|
Normal site safe work and permitting practices
apply.
|
Special tools
|
-
HART communicator with up to
date DDLs for the instruments being tested
|
References
|
Loop folder
|
Executed By
|
Action
|
Inside Person
|
Positively identify the termination point in the
ICJB and standby to provide support as needed.
|
Outside Person
|
Positively identify the instrument in the field and connect
the communicator. Monitor the communicator during power-up to ensure there
are no faults detected.
|
DCS Operator
|
Verify that the instrument location on graphics
matches the PID.
Pull up the face plate for the loop being tested on
the operator workstation.
|
Outside Person
|
Refer to the instrument index for the proper FAIL
LOW value. Make any needed changes so that the transmitter settings match the
index. Using the communicator, simulate the failure current output. (3.6mA)
|
DCS Operator
|
Verify that the instrument failure alarm has been
activated.
|
Outside Person
|
Put the transmitter
as simulation mode. (This will override all the alarms). Simulate by keypad on transmitter as 25%, 50%, 75%
and 100% .
|
DCS Operator
|
Verify DCS reading correctly responds to the simulated
values being applied.
Note: This is not a calibration. It is only to
confirm that the transmitter has not been damaged and is responding as
expected.
|
Outside Person
|
Disconnect the HART
communicator. Ensure that all covers are properly installed to prevent water
ingress. Disconnect
the test probe.
|
Inside Person
|
Document the results of the test. If the loop did
not pass the test, document the symptoms for the Advanced Trouble Shooting
Team.
|
Outside Person
|
-
If the loop passed, place a
wrap of blue tape on the transmitter.
-
If the loop did not pass,
place a wrap of red tape on the transmitter.
|
|
|
|
|
Functional Loop Test for HART Radar Level Transmitter
Purpose
|
Provide instructions to the Functional Loop Check
Team that will conduct the Functional Loop Test on a Radar Level Transmitter connected to an ABB 800xA DCS that uses HART device integration.
|
Scope
|
This procedure is to be used to ensure the correct
functionality of the entire loop and that all individual components have been
installed and are functioning according to the design specification. The
Functional Loop Test is to be the last test prior to turnover to the Owner.
|
Required Prerequisites
|
Prior to completing this procedure:
-
All pressure testing
requirements must be completed
-
All associated instrument and
electrical wiring must be checked for proper continuity, grounding, labelling,
and terminations
-
All A and B punch
list items associated with this loop must be cleared
-
Physical installation has
been inspected and signed off by Owner
-
Place a wrap of yellow tape
on the transmitter to indicate the steps above have been completed
-
Loops are powered up by Owner
Process Automation
-
Owner Process Automation has
established communication with the instrument and completed configuration of
the DCS and check of instrument settings
|
Functional
Loop Check Team
|
Each team will consist of 2 qualified Excel
Instrument Technicians and 1 Owner operations person.
|
EH&S
|
Normal site safe work and permitting practices
apply.
|
Special tools
|
-
HART communicator with up to
date DDLs for the instruments being tested
|
References
|
Loop folder
|
Executed By
|
Action
|
Inside Person
|
Positively identify the termination point in the
ICJB and standby to provide support as needed.
|
Outside Person
|
Positively identify the instrument in the field and connect
the communicator. Monitor the communicator during power-up to ensure there
are no faults detected.
|
DCS Operator
|
Verify that the instrument location on graphics
matches the PID.
Pull up the face plate for the loop being tested on
the operator workstation.
|
Outside Person
|
Refer to the instrument index for the proper FAIL
LOW value. Make any needed changes so that the transmitter settings match the
index. Using the communicator, simulate the failure current output. (3.6mA)
Note: Typically the desired value
is ≤3.6mA per NAMUR NE43.
|
DCS Operator
|
Verify that the instrument failure alarm has been
activated.
|
Outside Person
|
Refer to the instrument index for the HIGH/LOW
saturation values. Using the communicator, simulate both high and
low saturation current outputs.
Note: Typically the values
are 3.8mA and 20.5mA per NAMUR NE43
|
DCS Operator
|
Verify that the instrument failure alarm has NOT been activated when input
is saturated high or low.
|
Outside Person
|
Simulate the output
by HART communicator as 25%, 50%, 75% and 100% .
|
DCS Operator
|
Verify DCS reading correctly responds to the simulated
values being applied.
Note: This is not a calibration. It is only to
confirm that the transmitter has not been damaged and is responding as expected.
|
Outside Person
|
Disconnect the HART
communicator. Ensure that all covers are properly installed to prevent water
ingress.
|
Inside Person
|
Document the results of the test. If the loop did
not pass the test, document the symptoms for the Advanced Trouble Shooting
Team.
|
Outside Person
|
-
If the loop passed, place a
wrap of blue tape on the transmitter.
-
If the loop did not pass,
place a wrap of red tape on the transmitter.
|
Purpose
|
Provide instructions to the Functional Loop Check
Team that will conduct the Functional Loop Test on a Control valve connected to an ABB 800xA DCS that uses HART device integration.
|
Scope
|
This procedure is to be used to ensure the correct
functionality of the entire loop and that all individual components have been
installed and are functioning according to the design specification. The
Functional Loop Test is to be the last test prior to turnover to the Owner.
|
Required Prerequisites
|
Prior to completing this procedure:
-
All pressure testing
requirements must be completed
-
All associated instrument and
electrical wiring must be checked for proper continuity, grounding, labelling,
and terminations
-
All A and B punch
list items associated with this loop must be cleared
-
Physical installation has
been inspected and signed off by Owner
-
Place a wrap of yellow tape
on the transmitter to indicate the steps above have been completed
-
The instrument air is serviced and verified if there is no water. (The
isolation valve to the Control valve to be closed)
-
The Instrument air tube to be hooked up to the Control valve
-
Confirmation from Commissioning team if the valve can be any position
(Open or close) during test
-
Loops are powered up by Owner
Process Automation
|
Functional
Loop Check Team
|
Each team will consist of 2 qualified Excel
Instrument Technicians and 1 Owner operations person.
|
EH&S
|
Normal site safe work and permitting practices
apply.
|
Special tools
|
-
Multi Meter (Fluke)
-
Portable 24VDC Power Supply (Just in case)
|
References
|
Loop folder
|
|
Functional Loop Test for HART WIND MONITOR
Purpose
|
Provide instructions to the Functional Loop Check
Team that will conduct the Functional Loop Test on a Wind Monitor connected to an ABB 800xA DCS.
|
Scope
|
This procedure is to be used to ensure the correct
functionality of the entire loop and that all individual components have been
installed and are functioning according to the design specification. The
Functional Loop Test is to be the last test prior to turnover to the Owner.
|
Required Prerequisites
|
Prior to completing this procedure:
-
All associated instrument and
electrical wiring must be checked for proper continuity, grounding, labelling,
and terminations
-
All A and B punch
list items associated with this loop must be cleared
-
Physical installation has
been inspected and signed off by Owner
-
Place a wrap of yellow tape
on the transmitter to indicate the steps above have been completed
-
Loops are powered up by Owner
Process Automation
|
Functional
Loop Check Team
|
Each team will consist of 2 qualified Excel
Instrument Technicians and 1 Owner operations person.
|
EH&S
|
Normal site safe work and permitting practices
apply.
|
Special tools
|
-
Multi-Meter (Fluke or Similar)
|
References
|
Loop folder
|
Executed By
|
Action
|
Inside Person
|
Positively identify the termination point in the
ICJB and standby to provide support as needed.
|
Outside Person
|
Positively identify the instrument in the field.
|
DCS Operator
|
Verify that the instrument location on graphics
matches the PID.
Pull up the face plate for the loop being tested on
the operator workstation.
Check the wind
speed, direction and ambient temperature signal is coming to DCS.
|
Outside Person
|
Change the wind
speed manually.
Change the wind
direction manually.
|
DCS Operator
|
Check the wind speed
value at DCS is responding to the simulation at field.
Check the wind
direction value at DCS is responding to the simulation at field.
|
Outside Person
|
Return the wind
monitor as it is (Release any manual force)
|
Inside Person
|
Document the results of the test. If the loop did
not pass the test, document the symptoms for the Advanced Trouble Shooting
Team.
|
Outside Person
|
If the loop passed, place a wrap of blue tape on the
transmitter.
If the loop did not pass, place a wrap of red tape
on the transmitter.
|
|
|
Functional Loop Test for HART
Vortex flow
meter
Purpose
|
Provide instructions to the Functional Loop Check Team that will conduct the Functional Loop Test on a Vortex Flowmeter connected to an ABB 800xA DCS that uses HART device integration.
|
Scope
|
This procedure is to be used to ensure the correct functionality of the entire loop and that all individual components have been installed and are functioning according to the design specification. The Functional Loop Test is to be the last test prior to turnover to the Owner.
|
Required Prerequisites
|
Prior to completing this procedure:
- All pressure testing requirements must be completed
- All associated instrument and electrical wiring must be checked for proper continuity, grounding, labelling, and terminations
- All A and B punch list items associated with this loop must be cleared
- Physical installation has been inspected and signed off by Owner
- Place a wrap of yellow tape on the transmitter to indicate the steps above have been completed
- Loops are powered up by Owner Process Automation
- Owner Process Automation has established communication with the instrument and completed configuration of the DCS and check of instrument settings
|
Functional Loop Check Team
|
Each team will consist of 2 qualified Excel Instrument Technicians and 1 Owner operations person.
|
EH&S
|
Normal site safe work and permitting practices apply.
|
Special tools
|
- HART communicator with up to date DDLs for the instruments being tested
|
References
|
Loop folder
|
Executed By
|
Action
|
Inside Person
|
Positively identify the termination point in the
ICJB and standby to provide support as needed.
|
Outside Person
|
Positively identify the instrument in the field and connect
the communicator. Monitor the communicator during power-up to ensure there
are no faults detected.
|
DCS Operator
|
Verify that the instrument location on graphics
matches the PID.
Pull up the face plate for the loop being tested on
the operator workstation.
|
Outside Person
|
Refer to the instrument index for the proper FAIL
LOW value. Make any needed changes so that the transmitter settings match the
index. Using the communicator, simulate the failure current output. (3.6mA)
Note: Typically the desired
value is ≤3.6mA per NAMUR NE43.
|
DCS Operator
|
Verify that the instrument failure alarm has been
activated.
|
Outside Person
|
Refer to the instrument index for the HIGH/LOW
saturation values. Using the communicator, simulate both high and
low saturation current outputs.
Note: Typically the values
are 3.8mA and 20.5mA per NAMUR NE43
|
DCS Operator
|
Verify that the instrument failure alarm has NOT been activated when input
is saturated high or low.
|
Outside Person
|
Check for proper output with no flow (4mA). Simulate
the output by HART communicator as 25%, 50%, 75% and 100% .
|
DCS Operator
|
Verify DCS reading correctly responds to the simulated
values being applied.
Note: This is not a calibration. It is only to
confirm that the transmitter has not been damaged and is responding as
expected.
|
Outside Person
|
Disconnect the HART
communicator. Ensure that all covers are properly installed to prevent water
ingress.
|
Inside Person
|
Document the results of the test. If the loop did
not pass the test, document the symptoms for the Advanced Trouble Shooting
Team.
|
Outside Person
|
-
If the loop passed, place a
wrap of blue tape on the transmitter.
-
If the loop did not pass,
place a wrap of red tape on the transmitter.
|
Functional Loop Test for HART Magnetic flow meter
Purpose
|
Provide instructions to the Functional Loop Check
Team that will conduct the Functional Loop Test on a Magnetic Flowmeter connected to an ABB 800xA DCS that uses HART device integration.
|
Scope
|
This procedure is to be used to ensure the correct
functionality of the entire loop and that all individual components have been
installed and are functioning according to the design specification. The
Functional Loop Test is to be the last test prior to turnover to the Owner.
|
Required Prerequisites
|
Prior to completing this procedure:
-
All pressure testing
requirements must be completed
-
All associated instrument and
electrical wiring must be checked for proper continuity, grounding, labelling,
and terminations
-
All A and B punch
list items associated with this loop must be cleared
-
Physical installation has
been inspected and signed off by Owner
-
Place a wrap of yellow tape
on the transmitter to indicate the steps above have been completed
-
Loops are powered up by Owner
Process Automation
-
Owner Process Automation has
established communication with the instrument and completed configuration of
the DCS and check of instrument settings
|
Functional
Loop Check Team
|
Each team will consist of 2 qualified Excel
Instrument Technicians and 1 Owner operations person.
|
EH&S
|
Normal site safe work and permitting practices
apply.
|
Special tools
|
-
HART communicator with up to
date DDLs for the instruments being tested
|
References
|
Loop folder
|
Executed By
|
Action
|
Inside Person
|
Positively identify the termination point in the
ICJB and standby to provide support as needed.
|
Outside Person
|
Positively identify the instrument in the field and connect
the communicator. Monitor the communicator during power-up to ensure there
are no faults detected.
|
DCS Operator
|
Verify that the instrument location on graphics
matches the PID.
Pull up the face plate for the loop being tested on
the operator workstation.
|
Outside Person
|
Refer to the instrument index for the proper FAIL
LOW value. Make any needed changes so that the transmitter settings match the
index. Using the communicator, simulate the failure current output. (3.6mA)
Note: Typically the desired
value is ≤3.6mA per NAMUR NE43.
|
DCS Operator
|
Verify that the instrument failure alarm has been
activated.
|
Outside Person
|
Refer to the instrument index for the HIGH/LOW
saturation values. Using the communicator, simulate both high and
low saturation current outputs.
Note: Typically the values
are 3.8mA and 20.5mA per NAMUR NE43
|
DCS Operator
|
Verify that the instrument failure alarm has NOT been activated when input
is saturated high or low.
|
Outside Person
|
Check for proper output with no flow (4mA). Simulate
the output by HART communicator as 25%, 50%, 75% and 100% .
Check the
flow switch Function by simulating the set point specified in Index, if the
loop has the switch function.
|
DCS Operator
|
Verify DCS reading correctly responds to the simulated
values being applied. Verify the flow switch function respond to
simulated value.
Note: This is not a calibration. It is only to
confirm that the transmitter has not been damaged and is responding as
expected.
|
Outside Person
|
Disconnect the HART communicator. Ensure that all
covers are properly installed to prevent water ingress.
|
Inside Person
|
Document the results of the test. If the loop did
not pass the test, document the symptoms for the Advanced Trouble Shooting
Team.
|
Outside Person
|
-
If the loop passed, place a
wrap of blue tape on the transmitter.
-
If the loop did not pass,
place a wrap of red tape on the transmitter.
|
Functional Loop Test for Control Valve
Executed By
|
Action
|
Inside Person
|
Positively identify the termination point in the
ICJB and standby to provide support as needed.
|
Outside Person
|
Positively identify the Control Valve in the
field.
|
DCS Operator
|
Verify that the instrument location on graphics
matches the PID.
Pull up the face plate for the loop being tested on
the operator workstation.
Check with
commissioning team if the Control Valve can be tested.
|
Outside Person
|
Get confirmation
from operator for open/close the valve.
Drain the air
filter/regulator if any water. Open the Inst. Air block valve.
|
DCS Operator
|
Simulate the OP
Signal (Analog Output) 0%, 25%, 50%, 75%
and 100%
to the I/P
Positioner. (Check the Output direction depend on the Air fail position)
|
Outside Person
|
Check the valve
position is corresponding to the
simulated DCS output.
Check the valve is
moving smoothly.
|
DCS Operator
|
If there is a limit
switch on the control valve, simulated the OP as 0% to 7% Opening (Or 93% to 100% opening in case Open limit switch)
and check the limit switch is activated less than 5% open. (Or More than 95%
open in case open limit switch).
|
Outside Person
|
If the limit switch
is not activated within 0~5% open,
adjust the limit switch activation point setting by moving the proximity
Namur senor.
|
DCS Operator
|
Check the limit
switch activation point by simulating the Output value.
|
Outside Person
|
Cut-off the Inst.
Air to the valve for Air Fail Position Test (block in
the air supply and bleed the pressure off at the filter).
Verify the Air fail
position
Re-open the supply
air block valve.
|
Inside Person
|
Open the AO signal
(to Positioner) disconnect switch located in the ICJB for the Power Fail Position
Test
|
Outside Person
|
Verify the power
fail position at field
|
Inside Person
|
Close the AO disconnect switch
|
Inside Person
|
Document the results of the test. If the loop did
not pass the test, document the symptoms for the Advanced Trouble Shooting
Team.
|
Outside Person
|
If the loop passed, place a wrap of blue tape on the positioner enclosure.
If the loop did not pass, place a wrap of red tape
on the transmitter positioner
enclosure.
|
Functional Loop Test for Automatic Block Valve (ABV)
Purpose
|
Provide instructions to the Functional Loop Check
Team that will conduct the Functional Loop Test on a Automatic Block Valve (ABV) connected to an ABB 800xA DCS that uses HART device integration.
|
Scope
|
This procedure is to be used to ensure the correct
functionality of the entire loop and that all individual components have been
installed and are functioning according to the design specification. The
Functional Loop Test is to be the last test prior to turnover to the Owner.
|
Required Prerequisites
|
Prior to completing this procedure:
-
All pressure testing
requirements must be completed
-
All associated instrument and
electrical wiring must be checked for proper continuity, grounding, labelling,
and terminations
-
All A and B punch
list items associated with this loop must be cleared
-
Physical installation has
been inspected and signed off by Owner
-
Place a wrap of yellow tape
on the transmitter to indicate the steps above have been completed
-
The instrument air is serviced and verified there is no water. (The
isolation valve to the ABV to be closed)
-
The Instrument air tube to be hooked up to the ABV
-
Confirmation from Commissioning team if the valve can be any position
(Open or close) during test
-
Loops are powered up by Owner
Process Automation
|
Functional
Loop Check Team
|
Each team will consist of 2 qualified Excel
Instrument Technicians and 1 Owner operations person.
|
EH&S
|
Normal site safe work and permitting practices
apply.
|
Special tools
|
-
Multi Meter (Fluke)
-
Stopwatch (for valve stroke times)
-
Portable 24VDC Power Supply (Just in case)
|
References
|
Loop folder
|
Executed By
|
Action
|
Inside Person
|
Positively identify the termination point in the
ICJB and standby to provide support as needed.
|
Outside Person
|
Positively identify the ABV in the field.
|
DCS Operator
|
Verify that the instrument location on graphics
matches the PID.
Pull up the face plate for the loop being tested on
the operator workstation.
Check with
commissioning team if the ABV can be tested.
|
Outside Person
|
Get confirmation
from operator for open/close the valve.
Drain the air
filter/regulator if any water. Open the Inst. Air block valve.
|
DCS Operator
|
Confirm
that the ZSC/ZSO signal is correct for the current valve position. Ask
Outside Person to adjust if necessary.
Simulate the 24VDC
DO for solenoid.
|
Outside Person
|
Using a
stopwatch, check the Open/Close times and document for QC.
Check the valve is
moving smoothly
Check the valve
position indicator and actual valve status (Groove at the valve stem) is
matched. Make adjustments to the ZSC/ZSO if required.
|
DCS Operator
|
Verify that the valve open/close status is matched to
field status
Keep the solenoid
energized (24VDC) for the next step.
|
Outside Person
|
Cut-off the Inst. Air to the valve for Air
Fail Position Test (block in the air supply and bleed the pressure off at the
filter).
Verify the Air fail
position
Reopen the
supply air block valve.
|
Inside Person
|
Open the
solenoid DO disconnect switch located in the ICJB for the Power Fail Position
Test
|
Outside Person
|
Verify the power
fail position at field
|
Inside Person
|
Close the
solenoid DO disconnect switch
|
Inside Person
|
Document the results of the test. If the loop did
not pass the test, document the symptoms for the Advanced Trouble Shooting
Team.
|
Outside Person
|
-
If the loop passed, place a
wrap of blue tape on
the switch enclosure
-
If the loop did not pass,
place a wrap of red tape on the transmitter switch
enclosure.
|
Functional Loop Test HART Area Monitor
Purpose
|
Provide instructions to the Functional Loop Check
Team that will conduct the Functional Loop Test on a Area Monitor connected to an ABB 800xA DCS that uses HART device integration.
|
Scope
|
This procedure is to be used to ensure the correct
functionality of the entire loop and that all individual components have been
installed and are functioning according to the design specification. The
Functional Loop Test is to be the last test prior to turnover to the Owner.
|
Required Prerequisites
|
Prior to completing this procedure:
-
All associated instrument and
electrical wiring must be checked for proper continuity, grounding, labelling,
and terminations
-
All A and B punch
list items associated with this loop must be cleared
-
Physical installation has
been inspected and signed off by Owner
-
Place a wrap of yellow tape
on the transmitter to indicate the steps above have been completed
-
Loops are powered up by Owner
Process Automation
-
Owner Process Automation has
established communication with the instrument and completed configuration of
the DCS and check of instrument settings
|
Functional
Loop Check Team
|
Each team will consist of 2 qualified Excel
Instrument Technicians and 1 Owner operations person.
|
EH&S
|
Normal site safe work and permitting practices
apply.
|
Special tools
|
-
HART communicator with up to
date DDLs for the instruments being tested
|
References
|
Loop folder
|
Executed By
|
Action
|
Inside Person
|
Positively identify the termination point in the
ICJB and standby to provide support as needed.
|
Outside Person
|
Positively identify the instrument in the field and connect
the communicator. Monitor the communicator during power-up to ensure there
are no faults detected.
|
DCS Operator
|
Verify that the instrument location on graphics
matches the PID.
Pull up the face plate for the loop being tested on
the operator workstation.
|
Outside Person
|
Refer to the instrument index for the proper FAIL
LOW value. Make any needed changes so that the transmitter settings match the
index. Using the communicator, simulate the failure current output. (3.2mA for Polytron 7000 and
1.2mA for Polytron 2XP)
|
DCS Operator
|
Verify that the instrument failure alarm has been
activated.
|
Outside Person
|
Check for proper output with SENSOR installed. Simulate
the output by HART communicator as 25%, 50%, 75% and 100% .
|
DCS Operator
|
Verify DCS reading correctly responds to the simulated
values being applied.
Note: This is not a calibration. It is only to
confirm that the transmitter has not been damaged and is responding as
expected.
|
Outside Person
|
Disconnect the HART
communicator. Ensure that all covers are properly installed to prevent water
ingress.
|
Inside Person
|
Document the results of the test. If the loop did
not pass the test, document the symptoms for the Advanced Trouble Shooting
Team.
|
Outside Person
|
-
If the loop passed, place a
wrap of blue tape on the transmitter.
-
If the loop did not pass,
place a wrap of red tape on the transmitter.
|
|
|
|
-
|
Functional Loop Test for Flow Switch on Seal Purge Box
Purpose
|
Provide instructions to the Functional Loop Check
Team that will conduct the Functional Loop Test on a flow switch (Rotameter) on seal
purge box connected to an ABB 800xA DCS that uses
HART device integration.
|
Scope
|
This procedure is to be used to ensure the correct
functionality of the entire loop and that all individual components have been
installed and are functioning according to the design specification. The
Functional Loop Test is to be the last test prior to turnover to the Owner.
|
Required Prerequisites
|
Prior to completing this procedure:
-
All pressure testing
requirements must be completed
-
All associated instrument and
electrical wiring must be checked for proper continuity, grounding, labelling,
and terminations
-
All A and B punch
list items associated with this loop must be cleared
-
Physical installation has
been inspected and signed off by Owner
-
Place a wrap of yellow tape
on the transmitter to indicate the steps above have been completed
-
Loops are powered up by Owner
Process Automation
|
Functional
Loop Check Team
|
Each team will consist of 2 qualified Excel
Instrument Technicians and 1 Owner operations person.
|
EH&S
|
Normal site safe work and permitting practices
apply.
|
Special tools
|
-
Multi-Meter (Fluke or Similar)
|
References
|
Loop folder
|
Executed By
|
Action
|
Inside Person
|
Positively identify the termination point in the
ICJB and standby to provide support as needed.
|
Outside Person
|
Positively identify the instrument in the field.
|
DCS Operator
|
Verify that the instrument location on graphics
matches the PID.
Pull up the face plate for the loop being tested on
the operator workstation.
|
Outside Person
|
Check the Contact
output (Contact output is as per the inst. Index Spread sheet)
|
DCS Operator
|
Verify DCS status is
matched to field status. (Low flow or Normal)
|
Outside Person
|
Jumper 1 pair cable
at the terminal block. Remove the jumper at the terminal block at seal purge
box. Repeat 2 times.
|
DCS Operator
|
Verify DCS status is
matched to field simulation.
|
Outside Person
|
Remove all jumper.
Ensure that all covers are properly installed to
prevent water ingress
|
Inside Person
|
Document the results of the test. If the loop did
not pass the test, document the symptoms for the Advanced Trouble Shooting
Team.
|
Outside Person
|
-
If the loop passed, place a
wrap of blue tape on the transmitter.
-
If the loop did not pass,
place a wrap of red tape on the transmitter.
|
|
|
|
-
|
No comments:
Post a Comment