Thursday, 24 December 2015

METHOD STATEMENT FOR LEAK TESTING AND FLUSHING OF REFRIGERANT PIPING


CONTENT

1.   GENERAL

1.1  Introduction
1.2  Purpose
1.3  Scope Of Work
1.4  Location
1.5  Reference


2.   EXECUTION

2.1  Materials
2.2  Tools & Equipments
2.3  Procedure of Work
2.4  Responsibilities
2.5  Test Package Diagram (sample)


3.   QA / QC

3.1  Responsibilities
3.2  Test and Measurement
3.3  Inspection


4.   SAFETY

4.1  Guidelines
4.2  Responsibilities


5.   ATTACHMENTS

5.1  Job Hazard Analysis
5.2  Copper Brazer’s Qualification & Certification



1.   GENERAL INFORMATION

1.1  Introduction
 Main Contractor has awarded to  Constructions Saudi Arabia Ltd. the subcontract for the construction of  Project, JUBAIL and K.S.A.                                      


1.2  Purpose

                      To provide a procedure to be perform throughout the project to ensure conformity with project specifications and approved drawings.


1.3  Scope of Work

                      This Method Statement outlined the procedure for leak testing & flushing of copper piping for refrigerant piping system in the Building  Project in accordance with project specifications and approved drawings.


1.4  Location

                      Leak testing & flushing works for copper piping will be done within the building refrigerant piping system as specified in the approved drawings for the Project, JUBAIL, K.S.A.


1.5  Reference Standards


·        JERES-K-001
Heating, Ventilating and Air Conditioning (HVAC).
·        JERES-K-100
Mechanical (HVAC) Code.
·        JERES-S-060
Plumbing Code.
·        JERES-P-322
Performance Qualification Testing and Certification of JER Brazer.
2.   EXECUTION

2.1  Materials

·        Copper Tubing as per ASTM B280 Type ACR

·        Wrought copper fittings: ASTM B16.22

·        Brazing Filler Metals: AWS A5.8 Classification: BCup5 (15% silver) Bag-7 (50% silver)


2.2  Tools and Equipments

·        Nitrogen Gas

·        Nitrogen Regulator

·       

Latest calibration certificates to be provided in the test package
 
Test Manifold

·        Pressure Gauge                                           

·        Pressure Relief Valve

·        Various Hand Tools

·        Flood light / Flashlight



2.3  Procedure of Work

2.3.1       Manpower & Schedule


·        Only authorized technicians, pipe fitters and labours are allowed to conduct the leak testing & flushing works.

·        Leak testing & flushing works shall be done by trained personnel in the proper handling and usage of applicable tools and equipments prior to start testing & flushing.

·        One group of leak testing & flushing works consists of 1 technician. 1 pipe fitter, 1 stand-by man and 2 labours.

·        Flushing & Leak Testing for Substation 1104 & Substation 1105 can be completed within two weeks. Due to start on Sep. 17, 2011 (tentative).



2.3.2       Flushing Preparation


·        Prior to start of flushing works, survey the job site for potential hazards and shall be cleared before starting the work.

·        All tools & equipments shall be checked to make sure in good working condition.

·        All safety requirements shall be provided.

·        Nitrogen Gas shall be used for flushing the refrigerant piping system.

·        Nitrogen cylinders shall be placed in a firm ground.

·        Temporary fittings and connections shall be installed wherever required.

·        Nitrogen regulators shall be provided at the nitrogen cylinder shut-off valve to control the pressure outlet of the nitrogen.

·        A shut-off valve shall be installed at the pipe inlet to open & close the entry of the high pressure nitrogen gas.

·        At the other end of the piping system, it is open to atmosphere to discharge the dirt and other solid particles (if any).

2.3.3       Flushing

·        Flushing shall be done on each pipeline prior to leak testing.

·        Make sure that nitrogen gas will be discharged in a well ventilated area.

·        Flushing of nitrogen shall be controlled by regulators installed at nitrogen cylinder shut-off valve.

·        Nitrogen gas is injected on the piping system at high pressure by opening & closing on the shut-off valve provided on one end of the piping system and discharges to the atmosphere on the other end of the piping system.

·        Flushing is completed until no trace of dirt or foreign materials coming out from the piping system.

·        Time required for flushing on each pipeline depends on the cleanliness of the piping system and until the satisfaction of the inspection team.



2.3.4       Leak Test Preparation

·        Prior to start of leak testing, survey the job site for potential hazards and shall be cleared before starting the work.

·        All tools & equipments shall be checked to make sure in good conditions.

·        All safety requirements shall be provided.

·        Nitrogen Gas shall be used for leak testing the refrigerant piping system.

·        Nitrogen cylinders shall be placed in a firm ground.

·        Temporary fittings and connections shall be installed wherever required.

·        Nitrogen regulator shall be provided at the nitrogen cylinder shut-off valve to control the pressure outlet of the nitrogen.

·        Test manifold, pressure gauge & pressure relief valves shall be calibrated in accordance with project specifications.

·        Make sure all piping supports are installed in accordance with approved drawings.

·        Test package shall be approved by Company prior to start of Leak Testing.

·        Test package shall include test diagrams indicating test manifold location, pressure gauges and nitrogen cylinders.



2.3.5       Leak Test of Refrigerant Piping

·        After installation, all field erected refrigerant piping regardless of the quantity of refrigerant charge, shall be pressure tested in accordance with the requirements of the Uniform Mechanical Code (UMC) and ASHRAE Std. 15 the required test pressure shall be maintained for a minimum of 10 minutes as specified in JERES-K-001 section 6.3.2.

·        Test pressure shall be 250 psi at the Discharge Line and 150 psi at the Suction Line.

·        All joints, seals or connections shall be checked for leakage.

·        Pressure testing of refrigerant piping shall be controlled by nitrogen regulators installed at the nitrogen cylinder shut-off valve.

·        Minimum two pressure gauges shall be used for testing. One shall be installed at the end of the piping system and the other one on the test manifold.



2.4  Responsibilities

·     Site Engineer shall organize, manage and supervise all activities related to leak testing & flushing works with regards to safety, quality and productivity of the over-all performance of the work.

·     Site Supervisor and Foreman shall arrange all the necessary manpower, tools and equipments and implement the approved working procedure for a proper execution of the work with regards to safety, quality and productivity.



2.5  Test Package Diagrams

·     See attached sample diagrams.



3.   QA / QC

3.1  Responsibilities

·     QA / QC Inspector shall make sure that all activities related to leak testing & flushing works are carried out in accordance with the project specification and approved drawings. He shall arrange Inspections & Testings required with Company in accordance with the approved ITP JERITP-K-001-07. He shall maintain and keep records for all QC documents.

·     Site Engineer, Supervisor and Foreman shall assist the QA / QC Inspector whatever he required in relation to the quality of works, procedures or documents.

                    
3.2  Test and Measurement

·     Gauge and Manifold

·     Visual Inspection on Brazed Joints.


3.3  Inspection

·     Request for Inspection shall be issued to  Company Project Inspection 24 hours in advance on weekdays and 48 hours in advance for weekends and holidays.

·     Inspection shall be done in accordance with the approved ITP JERITP-K-001-07.

·     During Inspection, all brazed joints being tested shall be carefully examined for leakage.

·     The brazed joints being tested shall be satisfactory if there is no evidence of leakage or reasonable drop in pressure after the specified test period.

·     Leaking brazed joints shall be repaired and test shall be repeated until the system is proven satisfactory.




4.   SAFETY

4.1  Guidelines

·     Person working with leak testing & flushing works shall wear the Personal Protective Equipments at all times on the job site.

·     Warning sign boards and barricades shall be provided where necessary to isolate the working area and prevent un-authorised personnel.

·     All equipments shall be tagged and checked before using.

·     Aside from PPE, additional safety requirements shall be provided where necessary such as fire extinguishers & fire blankets.

·     Scaffolding shall be done before and after working to maintain cleanliness in the area.



4.2  Responsibilities

·     Safety Inspector / Officer in conjunction with the site supervisor or foreman shall physically check that all safety requirements has been provided and implemented.




5.   ATTACHMENTS

5.1  Job Hazard Analysis

5.2  Copper Brazer’s Qualification / Certification

5.3  Test Package Diagram


No comments:

Post a Comment