Total Marks 50
|
|||||||||
Name:
|
Company:
|
||||||||
A. Multiple Choices
|
1 × 20 =20
|
||||||||
1
|
Which Engineerig Procedure code is using for
HVAC Inspection Requirements?
|
||||||||
a) 27-SAIP-01
|
|||||||||
b) 15-SAIP-50
|
|||||||||
c) 32-SAIP-11
|
|||||||||
d) 00-SAIP-06
|
Answer:
|
||||||||
2
|
Which Test report mentioned for Fire Damper
Field Test?
|
||||||||
a) SATR-K-4003
|
|||||||||
b) SATR-K-4001
|
|||||||||
c) SATR-K-4004
|
|||||||||
d) SATR-K-4006
|
Answer:
|
||||||||
3
|
One Ton of refrigeration is equal to….
|
||||||||
a) 22000 Btu/hr
|
|||||||||
b) 18000 Btu/hr
|
|||||||||
c) 12000 Btu/hr
|
|||||||||
d) 6000 Btu/hr
|
Answer:
|
||||||||
4
|
Change of state from liquid to vapor is…..
|
||||||||
a) Evaporation
|
|||||||||
b) Condensation
|
|||||||||
c) Heat Exchange
|
|||||||||
d) Infiltration
|
Answer:
|
||||||||
5
|
Calibration Validity period of Pressure Gauge
is……
|
||||||||
a) One Month
|
|||||||||
b) Two Weeks
|
|||||||||
c) One Year
|
|||||||||
d) One Week
|
Answer:
|
||||||||
6
|
Calibration Validity period of Pressure Relief
Valve is…….
|
||||||||
a) One Month
|
|||||||||
c) One Year
|
|||||||||
b) Two Weeks
|
|||||||||
d) One Week
|
Answer:
|
||||||||
7
|
……………… is mentioned in SATIP-K-001-01.
|
||||||||
a) Centrifugul Fan
|
|||||||||
b) Air Handling unit
|
|||||||||
c) Tab of HVAC System
|
|||||||||
d) Refrigerent Piping
|
Answer:
|
||||||||
8
|
How Many Watt Power Lights to be used per
square feet for Duct leak test?
|
||||||||
a) 25 Watts
|
|||||||||
b) 50 Watts
|
|||||||||
c) 75 Watts
|
|||||||||
d) 100 Watts
|
Answer:
|
||||||||
9
|
Branch duct dampers shall be sheetmetal
……………………... Type.
|
||||||||
a) Gate
|
|||||||||
b) Butterfly
|
|||||||||
c) Louver
|
|||||||||
d) Radial vane
|
Answer:
|
||||||||
10
|
Equipment clearance shall be provided with a
minimum of……………………….
|
||||||||
a) 1 m
|
|||||||||
b) 1.5 m
|
|||||||||
c) 2 m
|
|||||||||
d) 2.5 m
|
Answer:
|
||||||||
11
|
Exhaust Fan shall have ………………which shall be
close when Fan is off.
|
||||||||
a) Smoke Dampers
|
|||||||||
b) Back draft Dampers
|
|||||||||
c) Fire Dampers
|
|||||||||
d) Volume Dampers
|
Answer:
|
||||||||
12
|
What is Mentioned in SATIP-N-001 & 002?
|
||||||||
a) Cold & Hot service insulation
|
|||||||||
b) Air Filteration Devices and Grease Filter
|
|||||||||
c) HVAC Metal Duct System
|
|||||||||
d) AC Split Systems-Direct Expansion (DX) Type
|
Answer:
|
||||||||
13
|
Which
SAIC to be used in AHU Receiving, Handling, Storage and Preservation?
|
||||||||
a) SAIC-K-4002
|
|||||||||
b) SAIC-K-4004
|
|||||||||
c) SAIC-K-4005
|
|||||||||
d) SAIC-K-4003
|
Answer:
|
||||||||
14
|
Location of fresh air intake shall be at a
minimum of ……….meters above grade.
|
||||||||
a) 1.5 m
|
|||||||||
b) 2.4 m
|
|||||||||
c) 3 m
|
|||||||||
d) 3.5 m
|
Answer:
|
||||||||
15
|
Why we use FACP connected in HVAC Control
panel?
|
||||||||
a) To reduce the power of HVAC Equipment
|
|||||||||
b) To control the Fire Alarm
|
|||||||||
c) To Energize the HVAC Equipment
|
|||||||||
d) To Shut down the HVAC Equipment
|
Answer:
|
||||||||
16
|
Smoke damper blades shall be minimum of
……… galvanized steel.
|
||||||||
a) 12 gauge
|
|||||||||
b) 24 gauge
|
|||||||||
c) 22 gauge
|
|||||||||
d) 14 gauge
|
Answer:
|
||||||||
17
|
Which SAIC has to be used in Refrigerant
Piping lay-out inspection?
|
||||||||
a) SAIC-K-4006
|
|||||||||
b) SAIC-K-4016
|
|||||||||
c) SAIC-K-4026
|
|||||||||
d) SAIC-K-4036
|
Answer:
|
||||||||
18
|
Why we are go for TAB?
|
||||||||
a) To encounter the trouble in the system.
|
|||||||||
b) To keep off the maintenance problem.
|
|||||||||
c) To Energize the Equipment.
|
|||||||||
d) None of above.
|
|||||||||
e) All of above.
|
Answer:
|
||||||||
19
|
Fan and Heat exchanger for cooling or heating
assembled in a common casing called as?
|
||||||||
a) ACCU
|
|||||||||
b) FCU
|
|||||||||
c) Duct Heater
|
|||||||||
d) Humidifier
|
Answer:
|
||||||||
20
|
Why Humidifier use in Air Conditioning System?
|
||||||||
a) Condensation
|
|||||||||
b) Moister removal
|
|||||||||
c) Humidification
|
|||||||||
d) Dehumidification
|
Answer:
|
||||||||
B. Abbreviation
|
|||||||||
21
|
What are the abbreviation of these legends in
SATIP?
|
2X5=10
|
|||||||
a) H -
|
|||||||||
b) W -
|
|||||||||
c) R -
|
|||||||||
d) S -
|
|||||||||
e) RH-
|
|||||||||
22
|
Give the abbreviation of the following
acronyms:
|
2X5=10
|
|||||||
a) SMACNA-
|
|||||||||
b) ASHRAE-
|
|||||||||
c) UPC-
|
|||||||||
d) ARI-
|
|||||||||
e) NEBB-
|
|||||||||
23
|
Explain
any 5 types of Insulation used in HVAC system?
|
2X5=10
|
|||||||
a)
|
|||||||||
b)
|
|||||||||
c)
|
|||||||||
d)
|
|||||||||
e)
|
|||||||||
C. Line Diagram
|
10X1=10
|
||||||||
24
|
Draw single line diagram of a refrigeration
cycle and identify the components.
|
||||||||
Saudi Aramco HVAC QC
Interview Questions (Sample-2)
Total Marks100
1 Marks Question 1x30=
30
1.
What is the Inspection engineering code for HVAC
Inspection Requirements?
Ans : 27-SAIP-01
2.
What
is SATR –K-001?
Ans:
fire damper test
3.
What SAES-K-003 mentioned in the about Saudi Aramco
standard?
4.
What
SATIP-A-004-02 Mentioned related in HVAC?
5.
What
is SATIP-K-001-11 Mentioned?ANS: split units (dx unts)
6.
What
is SATIP-A-004-05 mentioned?
Ans:CHW
system
7.
What
is SATIP-N-001&002 Mentioned
8.
Which
SA checklist used for Air Moving Cooling Valve and Apparatus
Arrangement Installation (DX Units)
Ans:SAIC-k-4027
.
9.
What
is SATIP-L-2006?
10. What SATR-K-006 mentioned
in HVAC?
ans:TAB hvac system
11. What is SATIP-K-001-01 Mentioned? ans: centrifugal
fan
12. What are the abbreviation legends for H,
W, S, R, RH, I in SAIC?
13. What is SAIC-S-4019?
14. What is SATIP-N-001&002 Mentioned?
15. What is SAIC-K-4001?ans:exshust fan receiving
16. What is SATIP-K-001-02 Mentioned? ans:ahu
17. Which data sheet mentioned about
reciprocating compressor?
18. Which
is SA standard mentioned about HVAC?ans: saes-k-4001
19. Which
SA checklist used for Final inspection of HVAC System)saic-k-4043
20. This
standard SAES-K-002 mentioned about Saudi Aramco?
21. Which
SATIP and SAIC used for Copper line?ans: satip-k-001-07&saic-k-4026
22. What is Ashrare, Smacna, DW 144, DW143
Standards?ans:sheet metal air condition contract association
23. What is vendor code? Explain.
24. Where
does shut off valve used in DX Line?ans:discharge line
25. What
SAEP-3101 mentioned?
26. What is the Inspection engineering code for HVAC
Inspection Requirements?
27. How long Calibration validity for pressure relief valve and pressure gauge?ans:1 week&1
month
28. What is SAIC-S-4032 ?ans:passivle cold
shelter installation
29. This
standard SAES-K-002 mentioned about Saudi Aramco?
30. Which
SA checklist used for Air Terminal Devices (Volume Dampers and
Duct Heaters) Receiving.ans: saic-k- 4009
2 Mark Question 20 x2 = 40 Marks.
1.
Why
Shaft provided in the Building? What are the MEP activities accessible from the
Shaft? Ans: Shaft is a life line of building .MEP activities are to use of HVAC
systems, electrical bus bar and cables, Plumbing & Drainage pipe to passing .
2.
How
many types of leak testing in ducts
3.
What
are HVAC equipments used in EPC (On Shore/ Off shore/ RIG)?
4.
What
are the document required to conduct the Material Inspection?
Ans
:purchasing order, Delivery Note, vender certificate. Material data sheet, Mill
Test Certificate.
5.
What is TEV and Feeler bulb and where will be
installed at what position?
6. Why
does Chemical filtration unit using Instead of Pressurization unit?
7. What
does Air stack? Why & Where it will be installed and requirements?
8.
How
many watt power lights used per
area for Duct leak test? Ans:500 watts
per 10 squre feet duct.
9.
Why does
Penetration (sleeve & Box outs) used on walls and ceiling? Ans: using sleeve
for removing material & box out using reduce sound drop pressure .
10. Describe Space heater requirement for
HVAC Equipment Motor?
11. .Explain about flushing and Vacuum Requirements in Ref.Piping?.
Ans :vacuum pump .pressure relief valve
.pressur gaje.nitrogen gas.bleed valve
12. What is the difference between Pressure
relief damper and Blast prove Damper? How it's working?
Ans:
pressure relief damper works depend on pressure of air in side the duct.
13. What relation between Gas damper and
fire damper Integrated Fire Panel and Gas panel? Explain briefly?
14. What is pressurization in the HVAC
System.
15. Why we have to provide u trap in Refrigerant
& condensation Line.
16. Merits & Demerits of Air cooled
system ?
17. What is the difference between NCR and
LBE? How will you observe at the site? How to Close it?
18. What is AK Factor ?
19. What is Sand Trap louver ? where will be
installed ? Why ?
20. What is VFD ? How to control the Air flow &
Liquid ?
10
Marks Question 6 X 5 = 30 Marks.
1.
What
have you lesson learned from your past jobs that related to HVAC QA/QC
Inspector?
2.
Do
you have Pressure testing, inspection experience in DX system? Explain briefly?
3.
Explain
Humidifier & Duct heater used in Supply Air Duct ?
4.
Explain
& Sketch P & E Diagram .
5.
Explain
& Sketch of Psychometric chart ?
6.
Explain about Home country and abroad Job experience briefly
No comments: