NO.
|
ACTIVITY
|
POTENTIAL
HAZARDS
|
RISK
RATING
|
PREVENTIVE
MEASURES
|
RESIDUAL
RISK
|
RESPONSIBLE
PERSON
|
1.
|
Preparation of working area, tools/equipment and
materials
|
· Untrained person/ poor
communication lead to Client rules violation or might cause.
· Uneven ground, scattered
tools and materials (tripping hazards
· Poor cable management might
Lead to tripping hazards
|
M
|
· All personnel shall be
undergone for Contractor/Company Safety induction and required necessary
training such as H2S awareness prior to enter process areas
· All work shall be carried
out with approved appropriate work permit, Mandatory for the permit receiver
and issuer to conduct site survey and inspection prior to release work
permit.
· Specific work permit shall
be obtained prior to start the activity. Content of work permit such as
actual location, activity and safety measure shall be discussed to all
involve person prior to start the activity during TBM.
· All access ways shall be
properly identify and maintained in good condition
· Contractor shall allocate
dedicated person to conduct regular housekeeping in each designated location.
· All tools and materials
shall be kept in approved designated storage area.
· All cable shall be properly
arrange and lay away from possible access way.
· Cable shall be installed
overhead as possible and applicable on the working area.
|
L
|
Task Supervisor/ PTWR
|
2.
|
Shifting of Tools
to elevated area by manual lifting
|
· Fall of materials that lead
to damage of property or injury due to failure of lifting tools and
materials, loose grip from person
|
M
|
· Task supervisor shall
ensure all workforces are received actual and specific safe instruction prior
to start the work.
· Heavy and bulky tools shall
not be manually lifted.
· Lifting area shall be
barricade and provided with appropriate barricade and signage and should be
free person in line of fire.
· Appropriate and inspected
lifting tools and materials shall be provided in all manual lifting activity
such as, pulley, rope and scaffold or lifting basket.
· Task supervisor to ensure
all damage and worn out lifting tools and materials shall be discard from
site.
· Task supervisor shall
identify or provide appropriate anchorage point for the pulley.
· All person involve in the
activity shall be provided with appropriate safety hand gloves to protect
from sharp object of the materials as well as maintaining proper grip of the
rope while lifting.
· Task supervisor is mandated to closely
monitor and correct all unsafe condition and action of the team during path
of the task.
|
L
|
Task supervisor
Worker
|
3
|
Alignment,
leveling, bolting and final torque of pipe spools and valves using hand tools
and bolt tensioning hydraulic pump
|
· Exposure to pinch point
hazards
· Hand injuries as a result
of improper use of tools and equipment
· Personnel struck by sudden
slip of hand tools
· Mechanical failure of bolt
tensioning equipment
· Fall of materials, tools or
person.
· Unsafe working platform
· Unauthorized person using
bolt tensioning equipment without proper training and competency to use equipment
· Poorly maintained equipment
resulting to mechanical failure
|
M
|
· Prior to start of hot work
all necessary pre-checks on work permit has been done.
· Appropriate PPE shall be
provided to all involve workforce such as, hard hat, FRC coverall,
appropriate safety gloves, safety shoe and face and eye protection (safety
glass and face shield)
· A full body harness shall
be worn by the team while on the scaffold with more than 1.8 meter elevation.
· All scaffolding shall be
erected, inspected and tag by competent persons as per client procedure and
standards.
· All persons shall be
undergone proper working at heights training and obtained proofs such as
training card or working at heights stickers mounted on their helmets prior
to work.
· All materials and tools
shall be kept on safe portion at working platform; all tools shall be
provided with restraining rope.
· Close monitoring and
supervision of workers
· Work area must have
sufficient clearance and remove any obstructions
· Use only the right tools
for the job, never use make shift tools or defective tools
· Only experienced and
competent person to do the job, focus on the work and avoid any distractions.
· Pre-check up of equipment
prior to use, ensure equipment is in good condition prior to start activity
· Secure all tools and
equipment when working at heights to restrain from falling, bolts and nuts
shall be secured in a covered container to avoid falling below.
· Only authorized and
competent person to use bolt tensioning machine
· Equipment must be properly
maintained at all times
|
L
|
Task Supervisor
and workers
|
3.A
|
Bolt
tensioning using bolt tensioning machine supplied with plant air or using air
compressor
|
· Failure of temporary
working platform.
· Unauthorized use of plant
air
· Uncontrolled release of
high pressure air
· Air hose dislodge from
connection, whipping effect
· Hand or body injury due to
improper positioning and pinch point
· Equipment mechanical
failure
· SIMOPS
· Heat stress, heat stroke
and heat cramps
|
M
|
· All scaffolding structure
shall be erected, inspected and tag by competent person in accordance with
client procedure and rules.
· Scaffolding platforms shall
used only as his purpose, pipe and other materials shall not allowed to stock
or rest on the platform.
· Task supervisor shall
ensure untagged or inspected scaffold shall not be used.
· Electrical extensions,
power tool and welding cables shall be inspected and obtained with current
monthly color code and neatly arranged and hung on insulated-hooks
· All power tools should be
110V and provided with GFCI, Power source such as welding machine and
portable generator shall be inspected by competent person, provided with
grounding system and properly earthed.
· Task supervisor to ensure
all damage and uninspected power tools shall not be use and discard from
working area
· Prior to commence activity
task supervisor should identify and determine and possible pinch point and
corrective action shall be emphasized to all involve person.
· Only competent fitters
shall do the task and under the close supervision by their person in-charge
such as supervisor or foreman.
· Task person in-charge shall
stop, correct unsafe condition and practice.
· Prior to use of plant air
secure valid approval from pre-com hydro test manager, only authorized person
shall operate downstream valves after removing LOTO. Work area must be
barricaded with signs.
· Ensure all hoses are
checked for correct pressure ratings, check for any signs of cracks and
leaks, ensure whip lashed arrestor installed, Chicago clamp fittings
installed with lock pins.
· Use of jubilee clips are
prohibited use only crimped type clamps to secure hose fittings
· Proper work planning and
proper coordination with other department working in same location.
· Task supervisor to ensure
adequate drinking water provided to workers and sufficient rest as per heat
stress flagging system.
|
L
|
Task supervisor
and workers
|
NO.
|
ACTIVITY
|
POTENTIAL
HAZARDS
|
RISK
RATING
|
PREVENTIVE
MEASURES
|
RESIDUAL
RISK
|
RESPONSIBLE
PERSON
|
Working near high noise area
|
· Hearing loss or impairment
|
M
|
· All personnel working near
high noise area exceeding to 85 db are required to use ear protection by
means of ear plugs or ear muffs
· Noise monitoring shall be
conducted and recorded as frequent as required by SSA HSE personnel.
· Task supervisor to ensure
all his work crew has readily available ear protection whenever working near
high noise areas.
|
L
|
Task Supervisor/ workers
|
|
Working near chemical storage areas or nearby chemical
cleaning activity
|
· Exposure or contact to
chemical liquids or inhalation of chemical vapors
· Sudden release of
pressurize chemical liquids
· Emergency situations
|
H
|
· Task supervisor shall
ensure all workforces have received actual and specific safety instruction
prior to start of work.
· Task supervisor to ensure that all workers
understood all hazards related to working near chemical storage or
pressurized chemical equipments.
· Gas testing shall be conducted
if necessary and as required.
· Proper identification of process lines or
equipments
· Warning signs, barricade
and pre-commissioning LOTO tags in place to identify live lines and
pressurized equipments.
· Proper PPE to be use as per
work requirements
· Stand by rescue equipment
and medical rescue team available
· Safety showers and eye wash
stations available and maintained.
|
L
|
Task supervisor/
Workers
|
|
Working near Live fuel gas lines
|
· Risk of fires and
explosions due to gas leaks
· Sudden release of
pressurized gas
· Inhalation of flammable gas
|
H
|
· Task supervisor shall
ensure all workforces have received actual and specific safety instruction
prior to start of work.
· Task supervisor to ensure
that all workers understood all hazards related to working near live fuel gas
lines.
· Continuous gas testing and
monitoring shall be conducted and recorded by authorized gas tester.
· Permanent gas detector and
alarms shall be fully functional near live fuel gas lines.
· All related requirements
for hot work activity shall be strictly applied and implemented.
· Approved and valid hot work
permit must be available.
· Proper PPE to be use as per
work requirements
· Stand by rescue equipment
and medical rescue team available
· Stand by fire truck and
fire fighting team and equipment available.
· Live fuel gas lines marked
and clearly identified for easy identification.
· Barricades and warning
signs available near fuel gas lines
· Close supervision and
monitoring by task supervisor
· Fire watchman must be
available and remain on hot work area 30 minutes after hot work has stopped.
· Ensure works area is
secured before leaving work area.
|
L
|
Task Supervisor/workers/ authorized gas tester
|
|
Working near live above and underground utilities and
energized equipments
|
· Electrocution, burns,
personnel injury
· Fires and explosion
· Sudden release of stored
energy
· Damage to plant facility
|
M
|
· Approved and valid work
permit available before commence of activity
· Task supervisor shall
ensure all workforces have received actual and specific safety instruction
prior to start of work.
· Task supervisor to ensure
that all workers understood all hazards related to working near live
utilities and energized equipment.
· Proper identification of
process lines or energized equipments
· Warning signs, barricade and
pre-commissioning LOTO tags in place to identify live lines and energized
equipments.
· Proper PPE to be use as per
work requirements
· Stand by rescue equipment
and medical rescue team available
· Close supervision and
monitoring by task supervisor
|
L
|
Task supervisor/
workers
|
|
Night
works
|
· Poor illumination leading
to slips trips and fall hazards
· Emergency situations
|
M
|
· Ensure during night works
all personnel use clear glass and reflective vest during work at night
· Sufficient illumination
must be provided on both access and work area.
· Ensure stand by medical
services available, work crew understands emergency response procedures and
how to deal with the situations.
|
L
|
Task supervisor/
workers
|